AES Brasil Energia S.A. Overview
| Field | Detail |
|---|---|
| Entity profiled | Auren Energia S.A. (successor to AES Brasil Energia S.A.) |
| Legal name (current) | Auren Energia S.A. |
| CNPJ | 28.594.234/0001-23 (per HG Brasil market data page, Oct 2026) |
| Former names (Auren lineage) | Companhia Energética de São Paulo (CESP) was the predecessor listed vehicle until the March 2022 combination that formed Auren. CESP survives as a subsidiary. |
| Former names (AES lineage) | Companhia de Geração de Energia Elétrica Tietê (1999); AES Tietê S.A.; AES Tietê Energia S.A. (2015–2021); AES Brasil Energia S.A. (2021–2024) |
| Founding year | CESP: 1966. AES Tietê: privatized 1999. Auren Energia: listed March 2022 (B3 trading data begins 28 March 2022, per Auren institutional presentations). |
| Incorporation jurisdiction | Federative Republic of Brazil (sociedade anônima, CVM Category A registrant) |
| Headquarters | São Paulo, SP, Brazil. see ri.aurenenergia.com.br. |
| Exchange / ticker | B3, Novo Mercado segment: AURE3 (common shares; listed in B3 notices as "AUREN (AURE-NM)") |
| Legacy ticker (delisted) | AESB3 (B3; last traded 31 October 2024). Earlier tickers TIET3/TIET4/TIET11 were replaced by AESB3 in 2021. |
| ISIN | Auren Energia 3rd debenture ISIN: BRAUREDBS027. Auren Participações 3rd debenture ISIN: BRAURPDBS031 (offering notices). |
| CUSIP | Not applicable (no US listing) |
| Fiscal year end | 31 December |
| Employees | Not publicly disclosed in sources reviewed; see Auren's Annual/Sustainability Report (GRI 2-7) |
| Auditor | see the 2025 DFP filed with the CVM |
| Shares outstanding | About 1.05 billion common shares (HG Brasil). Free float about 317.7 million shares; about 5.7 million in treasury (Investidor10, 19 Oct 2026). |
| Share price | BRL 14.82 to 14.89 (close 16 Oct 2026 / BTG data 19 Oct 2026) |
| Market capitalization | About BRL 15.6 billion (derived: 1.05 billion shares × BRL 14.82). Investidor10 cites "above BRL 15.5 billion". One aggregator (HG Brasil) shows BRL 11.89 billion, which appears stale or uses a different share count; this is flagged as a discrepancy. |
| Controlling shareholders | Votorantim S.A. and CPP Investments. Before the deal they jointly held 70.8% (NeoFeed, May 2024). The current combined stake is about 69%, derived from the free-float data. |
| Websites | aurenenergia.com.br; ri.aurenenergia.com.br. Legacy aesbrasil.com.br is no longer the operating site. |
| National credit ratings | Fitch AAA(bra), outlook revised to Negative around 14 July 2026. Moody's Local AAA.br, stable (2025 debenture rating). |
Auren Energia is Brazil's third-largest power generator and, by its own account, the country's largest independent energy trader. It runs a 100% renewable portfolio of about 8.7–8.8 GW, split roughly 54% hydro, 36% wind and 10% solar, with physical guarantee of about 4,077 average MW (Auren Modelling Guide, Jan 2026).
The company was built through a series of transactions. Votorantim's former self-production energy arm, Votorantim Energia, partnered with CPP Investments in the late 2010s. The partners acquired CESP in 2018, combined their assets into Auren in 2022, and bought AES Brasil in 2024.
The investment case now rests on four things:
-
a highly contracted portfolio through 2028,
-
growing exposure to expected higher power prices from 2029, with more than 30% of the portfolio uncontracted from that year,
-
"modulation" gains from hourly price volatility, and
-
deleveraging from 5.3x net debt/EBITDA toward a 3.0–3.5x target.
Curtailment of wind and solar output, weak hydrology, and high debt costs under elevated Brazilian interest rates are the main challenges.
What the company does
Auren generates electricity from hydroelectric, wind and solar plants and sells it, together with energy bought from third parties, mainly into Brazil's free contracting environment (ACL). It also holds legacy contracts in the regulated environment (ACR) and earns income from spot-market (PLD) settlement.
The company reports two operating activities:
Generation: owned and controlled plants, plus dividends from minority hydro stakes.
Commercialization (trading): buying and selling energy contracts, managing the portfolio's energy balance, and serving free-market customers.
Since 2024 the commercialization arm has added energy-management and retail-facing capabilities. It acquired Esfera Energia, a free-market energy manager, announced in June 2024. Auren's 2024 Annual Report also describes GUD Energia, a partnership launched to reach smaller free-market consumers.
The company's own description
In its 2024 Annual Report executive summary, Auren describes itself as the third-largest generator in Brazil. It highlights 8.8 GW of capacity across hydro, wind and solar, a 100% renewable portfolio, controlling shareholders Votorantim S.A. and CPP Investments, and 6.2 average GW of energy traded in 2024 (Auren Relatório Anual 2024, Resumo Executivo; paraphrased).
Its September 2026 corporate presentation summarizes the profile as follows:
-
third-largest generator with 8.7 GW of installed capacity,
-
100% renewable assets and a leading trading platform,
-
a portfolio diversified across sources and submarkets,
-
high contracting through 2028, with rising exposure to energy prices from 2029 (Quartr summary of corporate presentation, 17 Sep 2026).
Business and revenue model
| Revenue stream | Description | Character |
|---|---|---|
| Bilateral PPAs in the free market (ACL) | Medium- and long-term contracts with industrial, commercial and trading counterparties, including 15-year contracts signed for the remaining capacity of new projects (CEO interview, InvestNews 2025) | Contracted; inflation-indexed (IPCA/IGP-M); the core annuity-like stream |
| Regulated contracts (ACR) | Legacy auction contracts held by acquired assets (for example AES wind farms) and remaining CESP/AES hydro contracts | Contracted; regulated pricing |
| Energy trading | Buying and reselling energy, managing open positions, earning margins on volume (4.9 GWm traded in 1Q25) | Volume- and price-sensitive; includes mark-to-market on forward contracts |
| Spot settlement (PLD) and modulation | Settling surplus or deficit energy at hourly PLD. "Modulation" gains come from shifting hydro and wind output into high-price hours. These gains were BRL 70.5 million in 2Q26 (2Q26 release). | Volatile; increasingly material |
| Energy management services | Esfera Energia (acquired 2024) and GUD Energia | Service and fee-based; small |
| Equity-method income and dividends | Minority hydro holdings (CBA Energia, Pollarix, VC Pinheiro Machado, among others); dividends of BRL 110 million in 2Q26, up 45% year on year (Quartr 2Q26) | Passive cash flow |
Product / service / subscription / licensing mix: Essentially all revenue is "product" revenue, meaning energy measured in MWh. Service revenue from energy management is immaterial and not separately disclosed. There is no licensing or subscription revenue.
Value chain position
Auren sits in the generation and wholesale/retail commercialization segments of Brazil's electricity value chain. It has no material transmission or distribution business; distribution is a regulated activity run by companies such as Enel, CPFL, Neoenergia and others. Its customers are mainly:
-
large free-market industrial consumers (mining, metals, chemicals, pulp and paper; Votorantim group companies historically formed part of the self-production base),
-
medium-voltage commercial consumers, a market opened by Ministry of Mines and Energy Ordinance 50/2022 effective January 2024,
-
trading companies and other generators, and
-
the regulated pool, through legacy auction contracts.
Independent characterization
Auren is best understood as a merchant-tilted renewable generator with an embedded trading desk and a large hydro anchor. Hydro supplies the flexibility and storage that wind and solar lack. That combination drives the "modulation" gains management now emphasizes, and it partly hedges intermittency and curtailment risk: modulation offset 72% of curtailment losses in 2Q26 and 91% in 1Q26 (2Q26 earnings call).
The AES acquisition more than doubled capacity, but it also brought about BRL 19 billion of net debt, and leverage peaked at 5.7x in December 2024. The company is effectively in a deleveraging and integration-harvest phase. Dividends were cut to near zero for 2026, while investors position for the 2029+ uncontracted window and the outcome of battery and capacity auctions.
Strategy
Stated strategy (themes, paraphrased from company materials)
-
Integration and deleveraging (2025 priorities). At Auren Day 2025 management set two priorities: finish the AES integration efficiently during 2025 and deleverage consistently (1Q25 release; Visno). Integration was declared complete. Deleveraging has slipped, with leverage now expected to stabilize in 2026 and fall from 2027 toward a 3.0–3.5x target.
-
Balanced renewable portfolio. Auren calls its mix of hydro, wind and solar the most balanced in Brazil and says its capacity is close to the "optimal" mix it targets (Moody's Local summary of company materials).
-
Trading leadership and portfolio flexibility. The company aims to monetize hourly price volatility through modulation, to scale customer-facing commercialization (Esfera, GUD Energia), and to keep high contracting levels. Management has called flexibility the key word for the power system (CEO, InvestNews 2025).
-
Selective growth through new technologies. Management is focusing on the battery storage auction expected in December 2026 and studying hydro capacity auctions. The CEO said whoever masters batteries fastest will reap future benefits (Reuters via Money Times, Mar 2026, paraphrased).
-
Positioning for higher long-term prices. More than 30% of the consolidated portfolio is uncontracted from 2029, when management expects power prices to rise (2Q26).
-
Corporate simplification. A two-phase reorganization concentrates hydro assets in CESP, reduces the number of listed companies, and improves cash and debt management.
Strategic initiatives, last 24 months
| Initiative | Date | Detail | Status |
|---|---|---|---|
| AES Brasil integration and synergies | Nov 2024 – Sep 2025 | Opex synergies of about BRL 250 million a year; wind availability turnaround | Completed |
| Liability management | Apr–Aug 2025 | BRL 2.0 billion (CDI minus 0.50%), BRL 1.15 billion (IPCA + 6.92%, swapped to CDI minus 0.90%) and BRL 2.1 billion CESP (CDI + 0.62%) debentures used to prepay acquisition debt | Completed |
| Corporate reorganization, Phase 1 | Completed 31 May 2026 | Auren Participações merged into Auren Operações. Auren Operações' net debt/EBITDA covenants were temporarily eliminated, and its debts now carry an Auren Energia guarantee. | Completed |
| Corporate reorganization, Phase 2 | Approved 24 Jun 2026 | CESP capital increase of BRL 1.12 billion (76.9 million shares); Auren Operações merged into CESP; drop-down of Auren Energia's BRL 2.5 billion 3rd debenture to CESP; estimated cost BRL 10.5 million | Pending ANEEL and other conditions. CVM Category A filing made 23 Sep 2026. Completion targeted by end-2026. |
| Cajuína 3 wind | 2,026 | 88% complete; COD December 2026 | In testing |
| Curtailment compensation | Deadline 10 Aug 2026 | Auren expressed interest in the Ministry of Mines and Energy mechanism; estimated compensation about BRL 300 million, received 2H27–2028 | Pending board and shareholder decision |
| Battery auction | Dec 2026 (expected) | Selective participation under evaluation | Monitoring |
| Pró-Ética seal | 1 Jul 2026 | Recognition from the federal Comptroller General (CGU) for integrity and anti-corruption programs | Awarded |
| Buyback #3 | 19 Oct 2026 | Up to 1.95 million shares through 31 Dec 2026 | Active |
Medium-term guidance and targets
| Item | Guidance |
|---|---|
| Leverage | Stable in 2026, declining from 2027; target 3.0–3.5x net debt/adjusted EBITDA |
| Contracting | Highly contracted through 2028; more than 30% uncontracted from 2029 |
| Cajuína 3 | Full COD December 2026 |
| Dividends | Management describes dividends as supported by contract coverage. Market consensus expects low payouts until about 2027 (Acionista; A Revista). |
| Formal EBITDA or earnings guidance | Not provided. The January 2026 Modelling Guide gives analysts the building blocks instead. |
Products & Services
Installed capacities are shown where verified. Totals: about 8.8 GW (2024 Annual Report; Moody's Local, June 2025) and 8,723 MW with 4,077 average MW of physical guarantee (Modelling Guide, Jan 2026). Moody's Local (June 2025) splits capacity into about 4.7 GW hydro (derived as the residual), 3.2 GW wind and 876 MWac solar.
Hydro generation
| Asset / brand | Origin | Description and specifications | Customer / contract | Status |
|---|---|---|---|---|
| UHE Porto Primavera (Eng. Sérgio Motta) | CESP (2018 privatization) | Large run-of-river plant on the Paraná River, SP/MS; about 1.5 GW (historical public data; not re-verified) | ACL bilateral; MRE participant | Operating |
| UHE Paraibuna; UHE Jaguari | CESP | Smaller storage plants in the Paraíba do Sul basin, SP | ACL / MRE | Operating |
| UHE Água Vermelha | AES Tietê (1999) | Largest ex-AES plant, on the Grande River; about 1.4 GW (historical public data) | ACL / MRE | Operating (concession term: see filings) |
| Tietê cascade plants (Barra Bonita, Bariri, Ibitinga, Promissão, Nova Avanhandava) and Pardo river plants (Caconde, Euclides da Cunha, Limoeiro), plus small hydros | AES Tietê | Mid-size run-of-river and storage plants in SP | ACL / MRE | Operating (concession terms: see filings) |
| Minority hydro stakes: CBA Energia, Pollarix, VC Pinheiro Machado | Votorantim Energia | Holdings with enhanced dividend rights at holding level: CBA Energia +10%, Pollarix +25%, Pinheiro Machado +50% (Auren listing prospectus/reference form) | Dividends; equity income | Operating. Dividends were BRL 110 million in 2Q26, up 45%. |
| UHE Campos Novos (purchase right) | Votorantim Energia | Auren exercised a purchase right that raised its exposure (Auren institutional presentation, Oct 2023) | — | Operating |
Wind generation
| Asset | Origin | Location | Notes |
|---|---|---|---|
| Ventos do Piauí I, II, III | VTRM / Auren | Piauí | Auren's founding wind portfolio. Auren's legacy 1 GW generation matrix was 71% hydro and 29% wind (Oct 2023 presentation). |
| Ventos do Araripe (Auren portion) | Auren | Piauí/Pernambuco | Part of the Auren legacy portfolio |
| Alto Sertão II | AES (from Renova) | Bahia | Contracted under federal regulated auctions |
| Ventus | AES | Rio Grande do Norte | Acquired 2020 |
| Mandacaru / Salinas | AES | Northeast | Acquired 2021–2022 (details not re-verified) |
| Tucano | AES | Bahia | Built with industrial offtaker PPAs; contributed to 2023 EBITDA growth (InfoMoney 4Q23) |
| Cajuína 1 & 2 | AES | Rio Grande do Norte | Self-production structures with industrial partners; contributed to 2023 EBITDA |
| Cajuína 3 | AES pipeline, now Auren | Rio Grande do Norte | 88% complete; 8 of 19 turbines generating under test. Full commercial operation expected December 2026. Energy produced during tests is settled at PLD (2Q26 call / release). |
| Ventos do Araripe / Caetés (AES portion) | AES | Northeast | Contributed to 2023 EBITDA growth (InfoMoney 4Q23) |
| Cassino | AES | Rio Grande do Sul | Contributed to 2023 EBITDA growth |
The wind assets acquired from AES were a turnaround story. Availability reached 90.7% in March 2025, up 11.3 percentage points year on year (Visno 1Q25). Management says each additional percentage point of availability adds about BRL 20 million of revenue (InfoMoney, Mar 2026).
Solar generation
| Asset | Origin | Specification (where disclosed) |
|---|---|---|
| Guaimbê solar complex | AES | São Paulo state; acquired 2017 |
| Boa Hora solar complex | AES | São Paulo state |
| Ouroeste / AGV solar | AES | São Paulo state (details not re-verified) |
| Sol do Piauí (hybrid wind-solar) | Auren | 68.7 MW (Auren 2022 materials) |
| Jaíba V | Auren | 516 MW listed capacity; second column reads 154.2 (unit not stated; likely average MW). Minas Gerais. |
| Helios | Auren | 1,210 MW listed capacity; second column reads 355.3 (likely average MW). Minas Gerais. |
| Sol de Jaíba | Auren (acquired) | Referenced as an acquisition in investor materials |
| Distributed-generation assets (500 MWac / 626 MWp and 48 MWac / 59 MWp blocks) | Auren | Per Oct 2023 institutional presentation |
Commercialization and energy services
| Offering | Description | Target customer | Launch |
|---|---|---|---|
| Auren Comercializadora (wholesale trading) | Bilateral purchase and sale, portfolio hedging, structured energy products. Traded volume was 6.2 GWm in 2024 and 4.9 GWm in 1Q25. | Traders, generators, large consumers | Pre-2022 (Votorantim Energia) |
| Free-market supply (retail ACL) | Long-term renewable supply to industrial and commercial customers, including 15-year PPAs | Medium and high-voltage consumers | Ongoing; expanded after Ordinance 50/2022 |
| Esfera Energia | Energy management for free-market consumers, run independently with its former partners | Mid-size commercial and industrial users | Acquired 2024 |
| GUD Energia | Partnership to reach a broader customer base (named in the 2024 Annual Report) | Smaller free-market and retail customers | 2,024 |
| Selo Energia Verde (green energy certification) | Auren cites certification under a green-energy program in its 2024 Annual Report | Corporate ESG buyers | 2,024 |
| Carbon credits | Auren's 2022 presentation cites carbon credits sold (volume not legible in source) | Corporate buyers | 2,022 |
| Flora Energia (minority investment) | Startup giving regulated-market customers access to distributed-generation energy | Low-voltage consumers | 2022 investment |
Pricing model: Contract prices are generally confidential. Management has noted locking in contracts at around BRL 165/MWh for 2024–26 (BTG note on Investor Day). For reference, Goldman Sachs forecasts a Southeast/Center-West average of BRL 220/MWh for 2026–28 (initiation note, November 2025).
Financial Narrative
Basis of presentation
Because of the October 2024 combination, no single entity has a clean five-year history:
FY2021–FY2023: AES Brasil Energia S.A. standalone, as reported in its quarterly results releases.
FY2024: Auren Energia pro forma, as if combined all year, as disclosed by Auren.
FY2025: Auren Energia consolidated (AES included for the full year).
1H26 / LTM: Auren Energia.
Auren standalone reported figures for FY2021–FY2023 were not fully retrievable. AES Brasil and Auren rows are kept separate and should not be added together.
Income statement
Sources and notes:
-
AES 2021 and 2022: Suno, AES 4Q22. 2021 reported EBITDA and net income: Money Times / Reuters, 3 Mar 2022.
-
AES 2023: Suno / Estadão, 4Q23. The 2022 reported net income is derived: 333.3 / 1.041 ≈ 320.
-
Auren FY2025: Monitor do Mercado / InfoMoney, 3 Mar 2026.
-
Auren FY2024 pro forma (derived): revenue = 13,180 / 1.171; EBITDA = 3,970 / 1.199, consistent with Quartr's "BRL 3.3 billion". Net loss of BRL 32.7 million as reported pro forma.
-
EPS: AURE3 LTM EPS was about BRL -1.24 (Renova Invest data, 31 Jul 2026).
Margins (%)
The 2023 AES margin of 49.1% is as reported. Other margins are derived from the tables above.
Quarterly trajectory, Auren
Sources: Nord Investimentos (1Q25, 2Q25, 3Q25, 1Q26); Monitor do Mercado (4Q25); Visno and Quartr (2Q26).
Notes:
-
The 4Q25 adjusted EBITDA of BRL 1,010 million includes about BRL 143 million of non-recurring items. Safra's "clean" figure, excluding equity income and one-offs, is BRL 736 million.
-
4Q25 net income adjusted for one-offs would have been a loss of about BRL 134 million (Citi, via Monitor do Mercado).
-
1Q26 net income includes about BRL 506 million of negative mark-to-market on energy forward contracts.
Balance sheet
Sources and derivations:
-
AES FY2021 (derived): March 2022 net debt was BRL 4,233 million, 24.6% below March 2021 (InfoMoney). The 2021 year-end figure of about BRL 5.6 billion is an approximation implied by leverage, so treat it with caution.
-
AES FY2022 (derived): December 2023 net debt of BRL 9,044 million was +37.7% year on year (InfoMoney), implying about BRL 6.6 billion. Suno instead reports BRL 11.7 billion at December 2023, +6.4% year on year, implying about BRL 11.0 billion for December 2022. The two sources conflict materially. The FY2022 cell shows a midpoint and is unreliable.
-
AES FY2023: the BRL 9,044 million net debt is the leverage-covenant basis (InfoMoney). The BRL 11.8 billion gross debt is as of 2Q23 (Genial).
-
Auren FY2024: gross debt of BRL 27.0 billion (Visno 1Q25). Net debt derived as 19,240 / 1.017.
-
Total assets and equity are aggregator figures (Suno Analítica, about September 2026), shown in the FY2025 column as the latest available.
-
Auren states that its cash position covers more than three years of maturities (corporate presentation, Sep 2026).
Cash flow and shareholder returns
Notes:
-
FY2024: BRL 0.40 per share, a 4.6% yield (Acionista). The total of about BRL 420 million is derived from roughly 1.05 billion shares, and the share count changed during 2024.
-
Last-12-months yield to October 2026: 0.0% per most aggregators, or BRL 0.06 per share per Investidor10. This discrepancy is flagged.
-
AES Brasil planned BRL 3.35 billion of investment through 2027 (InfoMoney, 1Q23). Fitch expects robust free cash flow from 2026 (Nov 2024 rating action).
-
Buybacks: three programs to date, the latest up to 1.95 million shares for the restricted share plan (19 Oct 2026).
Commentary on trends and drivers
1. AES Brasil's legacy decade: diversification bought with leverage. AES Brasil grew revenue at about 17% a year and adjusted EBITDA at about 40% a year between 2021 and 2023. The driver was the shift from a hydro-only base, highly exposed to the GSF hydrological deficit, toward wind and solar. Management said in 2022 that it had doubled in size over five years with a 100% renewable strategy (CEO Clarissa Sadock, 4Q22 release, paraphrased). Its CFO said that by 2024 more than half of EBITDA would come from wind and solar (Reuters, Mar 2022).
The price was leverage. Leverage reached 5.31x net debt/EBITDA in December 2023, and quarterly financial expenses nearly tripled in 4Q23 compared with 4Q22. That balance-sheet strain, together with The AES Corporation's strategic retreat, set up the sale.
2. Auren after the deal: EBITDA up, earnings negative. Pro forma adjusted EBITDA rose about 20% in 2025 to a record BRL 3.97 billion, helped by synergies (about BRL 250 million a year of opex savings, per Acionista) and the wind availability turnaround. Net income nevertheless went negative (a BRL 558 million loss). Three factors explain this:
-
(a) net financial expense on about BRL 19 billion of net debt at roughly 15% CDI-linked rates,
-
(b) higher depreciation and amortization from purchase-price allocation (D&A up 21–36% year on year in 2Q–3Q25), and
-
(c) mark-to-market volatility on trading books.
3. 2026 inflection: down. 1H26 adjusted EBITDA fell about 18% year on year. The causes were weaker trading results, lower wind resources, worse curtailment and weak hydrology (2Q26 inflows at 82% of the long-term average). Leverage rose back to 5.3x. Management now expects leverage to stabilize in 2026 and decline from 2027, a delay from the earlier narrative of rapid deleveraging.
4. What drives the turn. The main swing factors for a recovery are:
-
Cajuína 3 COD (December 2026),
-
curtailment compensation (about BRL 300 million, cash expected 2H27–2028),
-
maturing hedges and new contracts, and
-
price recovery in the 2029+ uncontracted window.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansFinancial Detail
Segment Overview
| Segment | Contents | Products / services |
|---|---|---|
Generation – Hydro | Wholly owned and controlled hydro plants (ex-CESP: Porto Primavera, Paraibuna, Jaguari; ex-AES Tietê: Água Vermelha and other Tietê/Grande/Pardo river plants) plus minority hydro stakes (CBA Energia, Pollarix, VC Pinheiro Machado and others) | Energy sales, MRE/GSF settlements, modulation, dividends from minority stakes |
Generation – Wind | Ventos do Piauí, Ventos do Araripe (Auren legacy); Alto Sertão II, Ventus, Mandacaru/Salinas, Tucano, Cajuína, Cassino, Caetés (AES legacy) | Energy under ACR and ACL PPAs, self-production structures |
Generation – Solar | Guaimbê, Boa Hora, Ouroeste/AGV (AES legacy); Sol do Piauí (hybrid), Jaíba V, Helios (Auren) | Energy under ACL PPAs and ACR contracts |
Commercialization | Auren Comercializadora, Esfera Energia, GUD Energia (partnership) | Energy trading, portfolio balancing, free-market retail, energy management |
Holding / Corporate | Auren Energia, CESP, Auren Operações (post-Phase 1) | Financing, treasury, governance |
Segment Metric Details
| Segment metric (BRL Mn) | 1Q24 | 1Q25 | 2Q25 | 2Q26 |
|---|---|---|---|---|
Commercialization net revenue | 1,200 | 1,780 | — | — |
Generation net revenue | 1,328 | 1,620 | — | — |
Commercialization adjusted EBITDA | 52 | 165 | — | — |
Generation adjusted EBITDA | — | 1,100 | 947 | 902 |
Income Statement
| Metric (BRL Mn) | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|---|
AES Brasil net revenue | 2,511 | 2,845 | 3,431 | — | — |
AES Brasil adjusted EBITDA | 865 | 1,183 | 1,686 | — | — |
AES Brasil reported EBITDA | 904 | — | — | — | — |
AES Brasil adjusted net income | -39 | 320 | 333 | — | — |
AES Brasil reported net income | 517 | 320 | 333 | — | — |
Auren net revenue (pro forma 2024) | — | — | — | 11,255 | 13,180 |
Auren adjusted EBITDA (pro forma 2024) | — | — | — | 3,311 | 3,970 |
Auren net income (pro forma 2024) | — | — | — | -33 | -558 |
Margin Analysis (%)
| Metric (%) | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|---|
AES Brasil adjusted EBITDA margin | 34.4 | 41.6 | 49.1 | — | — |
AES Brasil adjusted net margin | -1.5 | 11.3 | 9.7 | — | — |
Auren adjusted EBITDA margin | — | — | — | 29.4 | 30.1 |
Auren net margin | — | — | — | -0.3 | -4.2 |
Financial Analysis
| Metric (BRL Mn) | 1Q25 | 2Q25 | 3Q25 | 4Q25 | 1Q26 | 2Q26 |
|---|---|---|---|---|---|---|
Net revenue | 2,950 | 2,885 | 3,500 | 3,800 | 3,100 | 3,056 |
Adjusted EBITDA | 1,200 | 981 | 773 | 1,010 | 926 | 859 |
Adjusted EBITDA margin (%) | 40.8 | 34.0 | 22.1 | 26.6 | 29.9 | 28.1 |
Net income | 54 | -563 | -404 | 355 | -602 | -379 |
Net financial result | — | — | — | -432 | — | -732 |
Net debt (BRL Bn) | 18.9 | 18.8 | 19.0 | 19.24 | 19.1 | 18.9 |
Net debt / adjusted EBITDA (x) | 5.0 | 4.8 | 4.9 | 4.8 | 5.2 | 5.3 |
Valuation Snapshot
| Metric | Value |
|---|---|
AES Brasil net revenue CAGR, FY2021–FY2023 | 16.9% (derived: (3,431 / 2,511)^(1/2) − 1) |
AES Brasil adjusted EBITDA CAGR, FY2021–FY2023 | 39.6% (derived) |
Auren pro forma net revenue growth, FY2024–FY2025 | 17.1% (reported) |
Auren adjusted EBITDA growth, FY2024–FY2025 | 19.9% (reported) |
Auren net revenue, 1H26 vs 1H25 | +5.0% (derived: 6,156 vs 5,835) |
Auren adjusted EBITDA, 1H26 vs 1H25 | -18.0% (derived: 1,785 vs 2,181) |
Balance Sheet
| Metric (BRL Mn) | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|---|
AES Brasil net debt | 5,600 | 8,500 | 9,044 | — | — |
AES Brasil gross debt | — | — | 11,800 | — | — |
Auren gross debt | — | — | — | 27,000 | — |
Auren net debt | — | — | — | 18,920 | 19,240 |
Auren total assets (latest available) | — | — | — | — | 46,700 |
Auren shareholders' equity (latest available) | — | — | — | — | 11,500 |
Dividends & Capital Returns and Per-Share Data
| Metric (BRL Mn) | FY2024 | FY2025 |
|---|---|---|
Auren dividends paid | 420 | 233 |
Auren dividends per share (BRL) | 0.40 | — |
Financial Analysis — ROE
| Ratio | Value | Basis / source |
|---|---|---|
ROE (LTM) | -9.5% to -10.2% | Investidor10 (Oct 2026); Renova (Jul 2026) |
ROA (LTM) | about -2.6% | Renova (Jul 2026) |
Net debt / equity | about 1.64x (derived: 18.9 / 11.5); Suno shows 1.74x | — |
Net debt / adjusted EBITDA | 5.3x (Jun 2026) | Company |
Interest coverage (adjusted EBITDA / net financial expense), 2Q26 | about 1.2x (derived: 858.9 / 732.1) | Derived |
Asset turnover (LTM revenue / total assets) | about 0.29x (derived: 13,455 / 46,700) | Derived |
Cash conversion cycle | Not meaningful / not disclosed | — |
Sector average leverage | 2.85x | Investidor10 sector data |
Revenue by Region
| Region (BRL Mn) | FY2023 | FY2024 | FY2025 |
|---|---|---|---|
Brazil – AES Brasil standalone | 3,431 | — | — |
Brazil – Auren consolidated (pro forma 2024) | — | 11,255 | 13,180 |
Outside Brazil | 0 | 0 | 0 |
Capital Markets Data (BRL)
| Price point (BRL) | May 2024 | Dec 2024 | Mar 2026 | Jul 2026 | Oct 2026 |
|---|---|---|---|---|---|
AURE3 close | 12.03 | 9.83 | 11.56 | 11.20 | 14.82 |
AESB3 close (legacy) | 9.78 | — | — | — | — |
Return metric
| Return metric | Value |
|---|---|
Year to date 2026 | about +25% (BRL 11.87 at the start of the year to BRL 14.82; Investidor10) |
1-year | +35.6% (Investidor10) or +54.1% (TradingView around 7 Oct). Sources differ by date. |
5-year | Not applicable; AURE3 listed March 2022 |
10-year total return (CESP/Auren lineage) | BRL 1,000 grew to BRL 1,070.90 with dividends reinvested (Investidor10, Aug 2026) |
Valuation Multiples
| Multiple | Auren | Peer reference |
|---|---|---|
P/E (LTM) | Negative (-14.3x, Investidor10) | Sector about 22x (Suno) |
EV/EBITDA (LTM) | about 9.7x (derived) | Engie about 7.2x (2025) |
EV/Sales (LTM) | about 2.6x (derived: about BRL 34.5 billion / BRL 13,455 million) | — |
P/B | about 1.35x (Investidor10) | — |
Analyst Ratings & Targets
| Broker | Rating | Target (BRL) | Date |
|---|---|---|---|
BTG Pactual | Buy | 19.00 | Oct 2026 |
Goldman Sachs | Buy | — | Nov 2025 initiation |
JPMorgan | Neutral | 13.60 | Oct 2025 |
Safra | Neutral | — | Mar 2026 |
Itaú BBA | Neutral (Dec 2024); flagged as a negative highlight for 1Q26 | — | 2024–26 |
UBS BB | Positive on operational improvement | — | Mar 2026 |
Range of targets | 13.00 – 19.00 | — | TradingView, Oct 2026 |
“—” = not publicly disclosed.
Capital Markets
| Item | Detail |
|---|---|
Policy | Brazilian statutory minimum of 25% of adjusted net income, unless the bylaws set more. Management targets recurring dividends subject to deleveraging (NeoFeed, 2024). |
History | 2024: BRL 0.40 per share (4.6% yield). 2025: BRL 233.3 million in 9M25. LTM to October 2026: about zero. |
Buybacks | Third program: up to 1.95 million shares (0.19% of capital), on market until 31 Dec 2026, funded from the capital reserve |
Credit Ratings
| Agency | Rating | Outlook | Date |
|---|---|---|---|
Fitch (national scale) | AAA(bra) | Negative | ~14 Jul 2026 (revised from Stable) |
Moody's Local Brasil | AAA.br | Stable | 2025 |
Capital Instruments
| Instrument | Amount (BRL Mn) | Tenor | Cost |
|---|---|---|---|
Auren Energia 3rd debenture (2024) | 2,500 | — | — |
Auren Participações 2nd debenture (2025) | 2,000 | 10 years (2035) | CDI minus 0.50% |
Auren Participações 3rd debenture (2025) | 1,150 | 12 years (2037) | IPCA + 6.9164%, swapped to CDI minus 0.90% |
CESP 14th debenture (2025) | 2,100 | 7 years (2032) | CDI + 0.62% |
Analyst Conclusions
Management guidance
-
Leverage stable in 2026 and falling from 2027 toward 3.0–3.5x.
-
Cajuína 3 at full COD in December 2026.
-
Reorganization Phase 2 completed by end-2026.
-
Curtailment compensation of about BRL 300 million received 2H27–2028.
-
Selective participation in the December 2026 battery auction.
-
Portfolio highly contracted through 2028, with more than 30% uncontracted from 2029.
Consensus
Formal consensus EPS and EBITDA are not publicly accessible. Directionally, the sell side expects FY2026 adjusted EBITDA below FY2025's BRL 3.97 billion: 1H26 is down about 18%, and JPMorgan cut 2025–26 estimates by 10–15%. Recovery is expected from 2027 on the factors above. Fitch projects 2026 leverage at 5.7x.
Bull case
-
Price leverage to 2029+. More than 30% of the portfolio is uncontracted when Goldman and management expect higher prices. A BRL 10/MWh move is worth about 10% of NPV (JPMorgan).
-
Visible recovery levers. Cajuína 3 COD, about BRL 300 million of curtailment compensation, about BRL 200 million a year of modulation (Fitch), and debt-cost savings as Selic eases could lift EBITDA back above BRL 4 billion and cut leverage toward 4x by 2027–28.
-
Valuation and sponsor backing. About 9.7x EV/EBITDA for a 100% renewable, hydro-anchored platform with AAA sponsors. Buybacks and the BTG BRL 19 target imply about 28% upside.
Bear case
-
Leverage stuck above 5x. If curtailment (BRL 520 million a year) and weak hydrology persist, Fitch's 5.7x 2026 projection could lead to a downgrade, which would raise funding costs on BRL 19 billion of debt.
-
Earnings quality. Net losses in five of the last six quarters, about 1.2x interest coverage, and mark-to-market swings of BRL 500 million or more make the equity a leveraged option on prices.
-
Dividend drought and controlled structure. A yield near zero until about 2027, and minority shareholders depend on controlling-shareholder capital allocation.
Catalysts and monitorables (next 12 months)
| Catalyst | Timing |
|---|---|
| 3Q26 results | ~November 2026 |
| Battery auction outcome | December 2026 |
| Cajuína 3 full COD | December 2026 |
| Phase 2 closing (ANEEL approval) | By end-2026 |
| Fitch rating review | 2026–27 |
| Curtailment compensation regulation and payments | 2,027 |
| 2026 hydrology (wet season November–April) | Ongoing |
| Selic trajectory | Ongoing |
| FY2026 results and dividend decision | ~March 2027 |
| Recontracting progress for 2029+ | Ongoing |
Analyst verdict
The AES Brasil story is finished as a standalone equity, and the question for investors is now Auren. AES Brasil spent 2016–2023 turning a hydro concession business from the 1999 privatization into a diversified renewable platform. Revenue grew from about BRL 2.5 billion to BRL 3.4 billion and EBITDA from about BRL 0.9 billion to BRL 1.7 billion between 2021 and 2023, but leverage climbed above 5x. Auren bought that platform at the bottom of a renewable-pricing cycle and showed real operational skill: synergies above plan, double-digit gains in wind availability, and record EBITDA of BRL 3.97 billion in 2025.
The equity case is less clear than the operating case. Auren is a highly leveraged company: 5.3x net debt/EBITDA, about 1.2x interest coverage, and five loss-making quarters out of six. Three things outside management's control matter most:
-
curtailment, worth about BRL 520 million a year in Fitch's estimate,
-
hydrology, and
the Selic rate: Modulation and trading partly hedge these, but trading has also become a source of volatility, as the BRL 506 million mark-to-market loss in 1Q26 showed.
The 2026 rally (about +25% year to date, and possibly more in October) suggests the market is already pricing the 2029+ uncontracted window, falling interest rates and a 2027 deleveraging turn. At about 9.7x EV/EBITDA, the stock is no longer cheap against lower-leverage Engie, though still reasonable for a hydro-anchored renewable platform with strong sponsors.
Verdict: constructive on the assets, Neutral to cautiously positive on the equity. Upside depends on evidence in 3Q26–4Q26 of three things: leverage peaking at or below 5.3x, Cajuína 3 reaching COD on time, and curtailment compensation being regulated. A Fitch downgrade or another quarter of large trading losses would weaken the thesis. A clear deleveraging path toward 4x by 2027–28 would support the bull-case BRL 19 target.
SOURCES CONSULTED (selected)
-
Auren Energia: 2Q26 earnings release (Aug 2026); 2024 Annual Report and Executive Summary; 2022 Management Report; institutional presentations (Mar 2023, Oct 2023, 2025); Material Facts of 24 Jun 2026, 23 Sep 2026 and 19 Oct 2026 (via ri.aurenenergia.com.br, api.mziq.com, Investidor10 filings links)
-
Fitch Ratings rating action commentary (14 Nov 2024); Moody's Local Brasil credit report (June 2025); debenture offering notices (XP Ofertas Públicas)
-
Quartr event summaries (2Q26; corporate presentation, 17 Sep 2026); Yahoo Finance 2Q26 call highlights
-
Press: Money Times; InfoMoney; Estadão / Times Brasil; Monitor do Mercado; Visno Invest; Nord Investimentos; Investidor10; BP Money; Suno; NeoFeed; Forbes Brasil; InvestNews; Canal Solar; Seu Dinheiro; Acionista; Safra O Especialista; Genial Investimentos; Guia do Investidor; Cenário Energia; ADVFN; Analise de Ações; Atlas Público; BTG Pactual research page; HG Brasil; TradingView; Renova Invest; Suno Analítica
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansExecutive Leadership
Executive Leadership Team
| Name | Title | Tenure / notes | Prior roles |
|---|---|---|---|
Fabio Zanfelice | CEO (Diretor-Presidente) | Led Votorantim Energia from 2015 and Auren since its 2022 formation (InvestNews) | CEO of Votorantim Energia; led the CESP privatization integration |
Mateus Gomes Ferreira | VP Finance and Investor Relations (CFO) | Since 1 July 2024; mandate extended in line with the bylaws | Chairman of Auren's board until 1 July 2024 |
Mario Bertoncini | VP Clients and Commercialization | Statutory officer since 1 July 2024 | — |
Joaquim Spinola | — | Listed among executives in a 2025 corporate presentation | — |
Daniel Marrocos | — | Listed among executives in a 2025 corporate presentation | — |
Priscila Lino | Director, Regulatory Affairs | Spokesperson at Investor Day (BTG note) | — |
Board of Directors
| Name | Role | Notes |
|---|---|---|
João Henrique Batista de Souza Schmidt | Chairman | Elected effective 1 July 2024; returned to the board after previously serving (Visno). Senior Votorantim executive. |
Other members | Votorantim and CPP Investments nominees plus independent members | — |
Board & Management Changes
| Date | Change | Context |
|---|---|---|
25 Jun 2024 (effective 1 Jul 2024) | Mateus Ferreira moves from chairman to CFO/IRO; João Schmidt becomes chairman; Mario Bertoncini becomes VP Clients and Trading | Preparation for the AES integration and its financing |
2023–2024 (AES legacy) | AES Brasil leadership: CEO Clarissa Sadock (quoted 2022–23) and CFO Alessandro Gregori (2021–22). | AES executives left or were integrated after closing |
Major Shareholders
| Holder | Stake | Source / note |
|---|---|---|
Votorantim S.A. plus CPP Investments (controlling bloc) | about 69% (derived); 70.8% before the deal | NeoFeed (May 2024); derived from free float of about 317.7 million out of about 1.03–1.05 billion shares |
Free float | about 30–31% | Investidor10 (Oct 2026) |
Treasury shares | about 5.7 million | Investidor10 (Oct 2026) |
Luiz Barsi (individual investor) | Undisclosed; described as monitoring the stock | Investidor10 headline |
Competitive Landscape
Key Competitors
| Competitor | Segment overlap | Positioning vs Auren |
|---|---|---|
Eletrobras / Axia Energia | Hydro generation, trading | Largest generator in Brazil (ranked 1st in Auren's ranking slide); privatized 2022 |
Engie Brasil Energia (EGIE3) | Hydro, wind, solar, transmission | Ranked 2nd; lower leverage; EV/EBITDA about 7.2x vs Auren 12.2x (Acionista, 2025) |
Enel Green Power Brasil | Wind, solar, hydro | Ranked after Auren in Auren's slide; multinational parent |
Copel (CPLE) | Hydro, wind | Ranked after Auren; more uncontracted energy before 2027 than Auren (Zanfelice, Reuters, Mar 2026) |
CTG Brasil (China Three Gorges) | Hydro | Large hydro owner (including ex-CESP Ilha Solteira and Jupiá); unlisted |
Cemig (CMIG4) | Hydro, trading | State-controlled utility; flagged by Itaú BBA alongside Auren as weak in 1Q26 |
Neoenergia (NEOE3) | Wind, hydro | Iberdrola subsidiary |
Serena Energia (formerly Omega) | Wind, solar, trading | Pure-play renewable; also exposed to curtailment (Fitch puts Auren, Engie and Serena in the same group) |
CPFL Energia (CPFE3) / CPFL Renováveis | Wind, hydro, trading | Integrated utility |
Statkraft, Casa dos Ventos, Comerc / Vibra, Matrix, 2W Ecobank | Renewables and free-market trading | Competing traders and retailers |
Peer Comparison FY2025
| Metric | Auren | Engie Brasil |
|---|---|---|
FY2025 net revenue (BRL Mn) | 13,180 | — |
FY2025 revenue growth (%) | 17.1 | — |
FY2025 adjusted EBITDA margin (%) | 30.1 | — |
Net debt / EBITDA (x) | 5.3 | — |
EV / EBITDA (x) | 9.7 | 7.2 |