AJR Infra and Tolling Limited Overview
| Attribute | Detail | Source |
|---|---|---|
| Legal name | AJR Infra and Tolling Limited | Company filings, 2026 |
| Former names | Gammon Infrastructure Projects and Investments Limited (at incorporation); Gammon Infrastructure Projects Limited (to Aug 2021) | Company history (Goodreturns, IIFL); Investing.com |
| Name change to current | August 2021 | Investing.com company profile |
| Founding / incorporation | April 2001, promoted by Gammon India Limited | IIFL company summary; Goodreturns history; CARE Jul 2026 |
| Incorporation jurisdiction | Maharashtra, India (Companies Act) | CIN L45203MH2001PLC131728 |
| CIN | L45203MH2001PLC131728 | Company letterhead, all 2024–2026 filings |
| Registered office / HQ | 3rd Floor, Plot No. 3/8, Hamilton House, J.N. Heredia Marg, Ballard Estate, Mumbai 400 038, India | Company letterhead |
| Telephone / email | +91-22-6748 7200 / info@ajrinfra.in | Company letterhead |
| Website | www.ajrinfra.in (legacy: www.gammoninfra.com) | Company letterhead |
| Stock exchanges | National Stock Exchange of India (symbol AJRINFRA, currently in "BZ" series); BSE Limited (scrip code 532959) | Company filings; Screener |
| Legacy ticker | GAMMNINFRA (NSE) — still referenced in a 30 Sep 2024 filing | Company Reg. 30 letter, 30 Sep 2024 |
| ISIN | INE181G01025 | CARE Ratings, Jul 2026; Multibagg Aug 2026 |
| CUSIP | Not applicable (no US listing) | — |
| Trading status | Suspended; last traded price INR 0.70 on 3 October 2023 | Screener; IndMoney |
| Face value | INR 2 per share | Screener; company results |
| Paid-up equity capital | INR 189.18 crore (INR 18,917.64 lakh) | Q1 FY2027 results |
| Shares outstanding (derived) | ~945.9 million (paid-up capital ÷ INR 2 face value) | Derived from Q1 FY2027 results |
| Fiscal year end | 31 March | Company filings |
| Employees | 3–5 (latest data-provider figures); 3-year trend not publicly disclosed in sources reviewed | Morningstar (3 and 5 in different snapshots); Zonebourse (5); Investing.com (5) |
| Statutory auditor | N V C & Associates LLP, Chartered Accountants, Mumbai (formerly Natvarlal Vepari & Co; converted to LLP 23 Mar 2025); engagement partner Nuzhat Khan | Q1 FY2027 limited review report |
| Internal auditor (FY2027) | M/s A K Anand & Co, appointed 13 Aug 2026 | Board outcome, 13 Aug 2026 |
| Market capitalisation (at last traded price) | ~INR 66 crore (Screener: INR 65.9 crore; derived: ~INR 66.2 crore) | Screener; derived |
| Promoter | Gammon India Limited — 10.72% stake, 100% pledged/encumbered | Screener shareholding Sep 2026; Investing.com |
| Credit rating | CARE D; Issuer Not Cooperating (LT INR 25 crore, ST INR 35 crore), reaffirmed 24 Jul 2026 | CARE Ratings PR, 24 Jul 2026 |
| Segment reporting | Single segment: "Infrastructure Development" (standalone); "Construction and Engineering" (consolidated); single geography: India | Q1 FY2027 results, notes 8 |
The entity on the supplied list (Gammon Infrastructure Projects / NSE: GAMMNINFRA / gammoninfra.com) has changed its name. The legacy NSE symbol GAMMNINFRA has been replaced by AJRINFRA, and the website is now ajrinfra.in.
AJR Infra and Tolling Limited, formerly Gammon Infrastructure Projects, was created in 2001 by Gammon India as one of India's first dedicated PPP infrastructure developer holding companies, building and operating toll roads, bridges, port terminals, hydro, biomass and cogeneration assets through project SPVs. After a decade of rapid expansion funded by heavy project-level leverage, the group entered a prolonged distress cycle from about 2016: cost overruns, concession disputes, lender NPAs and insolvency petitions progressively stripped it of its assets. Today the company has no revenue from operations, a handful of employees, negative net worth of roughly INR 855 crore (consolidated, March 2026), a suspended share listing and defaulted bank ratings. Its residual value rests on a minority stake in Vizag Seaport, a beneficial interest in Indira Container Terminal, arbitration and litigation outcomes (notably a Supreme Court appeal over Patna Highway Projects), and its ability to neutralise roughly INR 1,500 crore of contested guarantee exposure.
Company's own description
The company describes itself, in its results filings and annual reports, as an infrastructure project development company incorporated by Gammon India to participate in PPP infrastructure, with investments across roads and expressways, ports, hydropower, urban infrastructure, airports, special economic zones, water and wastewater, railways, power transmission and agricultural infrastructure (Screener summary of FY2022 Annual Report; ajrinfra.in). Older annual reports classify its activities into three streams: Project Development, Project Advisory, and Sector-Specific Operations & Maintenance (IIFL company summary, drawing on annual reports). CARE Ratings (July 2026) summarises the model as development of PPP projects through project-specific SPVs, with a diversified portfolio across roads, power and ports.
For segment reporting under Ind AS 108, the company states that its standalone operations constitute a single segment, "Infrastructure Development", and that the group operates in one segment, "Construction and Engineering", entirely within India (Q1 FY2027 results, note 8 to standalone and consolidated statements). Some data providers still describe two segments, Real Estate and Infrastructure (Morningstar), which reflects historical disclosures and is no longer how the company reports.
Independent characterisation
In substance, AJR Infra is a legacy PPP holding company in run-off and litigation mode. The business model it was built on — win concessions, construct through the parent (Gammon India) as EPC contractor, finance SPVs with 70–80% non-recourse-in-name but parent-guaranteed debt, then earn toll/annuity/port revenue over 15–30 year concessions — has collapsed. The parent guarantees turned "non-recourse" project debt into holding-company liabilities when SPVs defaulted.
Key features of the current model:
Revenue model: No product, subscription or licensing revenue. Historically, revenue was concession revenue (toll collection, annuities from NHAI/state authorities, port cargo handling charges, power sales) recognised at SPV level, plus construction revenue under Ind AS 115 / Appendix C (service concession arrangements). Since Q3 FY2025, consolidated revenue from operations is nil (Screener consolidated quarterly data). The holding company's income now consists almost entirely of "other income" — interest, guarantee commissions, fair-value gains and settlement-related reversals.
Value chain position: Historically, the developer/concessionaire layer, sitting between government concession grantors (NHAI, MoRTH, state road development corporations, port trusts, state power utilities, a sugar cooperative) and EPC contractors (principally Gammon India). Today it is closer to a claims-holding and liability-management vehicle.
Customer types: Government concession authorities (NHAI, MoRTH, Madhya Pradesh Road Development Corporation, Visakhapatnam Port Trust, Mumbai Port Trust), toll-paying road users, shipping lines and cargo owners (port SPVs), power off-takers.
End-markets: Indian transport infrastructure (highways, bridges, ports) and, historically, renewable/hydro power.
Current asset base (as disclosed in Q1 FY2027 results)
| Asset / SPV | Relationship today | Status (per company disclosure) |
|---|---|---|
| Vizag Seaport Pvt Ltd (VSPL) | Associate (company holds ~23.56%) | Operating multi-cargo terminal at Visakhapatnam inner harbour; equity-accounted; associate profit share INR 2.03 crore in Q1 FY2027 |
| Indira Container Terminal Pvt Ltd (ICTPL) | Beneficial interest in 16.29% of equity; control transferred to new management in FY2025 after lender OTS | Funded exposure INR 48.33 crore; INR 35 crore bank guarantee still outstanding in favour of lenders |
| Sidhi Singrauli Road Project Ltd (SSRPL) | Subsidiary | One-time settlement with MPRDC/MoRTH and lenders completed in Q1 FY2026; lenders issued no-dues certificate releasing company's guarantee |
| Patna Highway Projects Ltd (PHPL) | Control lost (CIRP; Silver Point resolution plan approved) | Supreme Court civil appeals admitted 26 Sep 2025; INR 1,190.24 crore guarantee invocation by Phoenix ARC contested |
| Rajahmundry Godavari Bridge Ltd (RGBL) | Control lost (CIRP) | Exposure written off; INR 697.10 crore guarantee invocation booked as current liability; further INR 98.11 crore non-funded exposure; DRT recovery stayed 7 Jul 2026 |
| Pravara Renewable Energy Ltd (PREL) | Wholly owned subsidiary, but company asserts loss of control under Ind AS 110 | Admitted to CIRP 6 Jan 2023; plant reportedly auctioned by lenders (DRT order 27 Feb 2025); INR 191.67 crore non-funded exposure |
| Sikkim Hydro Power Ventures Ltd (SHPVL) | Subsidiary | Development ceased; accounts not on going-concern basis; INR 18.84 crore impairment in Q1 FY2027; sale to Statkraft called off Apr 2024 |
| Tidong Hydro Power Ltd | Subsidiary | Status not detailed in recent filings |
| Cochin Bridge Infrastructure Co Ltd | Subsidiary | Legacy New Mattancherry Bridge SPV; current status not detailed |
| Birmitrapur Barkote Highway, Yamunanagar Panchkula Highway, Vijayawada Gundugolanu Road Project, Tada Infrastructure Development, Segue, Chitoor, Earthlink, Gammon Logistics, Gammon Projects Developers, GREIPL, Gammon Road Infrastructure, Gammon Seaport Infrastructure | Subsidiaries / step-down subsidiaries | Largely dormant or in dispute; 14 subsidiaries' results unreviewed, reporting combined total assets of INR 26.32 crore and revenue of INR 0.02 crore in Q1 FY2027 |
| GIPL–GECPL JV | Joint venture | Immaterial; share of loss INR 0.10 crore in Q1 FY2027 |
Source: Q1 FY2027 results notes 4–7 and auditor's Annexure A (13 Aug 2026).
Strategy
Stated strategy
The company does not publish investor presentations, investor-day materials or medium-term targets. The FY2022 annual report's Whole-Time Director's message spoke of working to keep assets operating through a difficult period and seeking additional funding and diversified opportunities (annual report extract, BSE). In practice, the observable strategy since 2021 has had four themes:
-
Asset monetisation to raise liquidity — VSPL 33% stake sale (2021); attempted Sikkim Hydro sale to Statkraft (2022, abandoned 2024).
-
Lender settlements to extinguish guarantees — ICTPL OTS (FY2025); SSRPL OTS (FY2026), which released the company from all SSRPL-related guarantees.
-
Litigation to recover value and resist guarantee invocations — Supreme Court appeals over PHPL; Section 65 IBC application alleging fraudulent/malicious initiation of PHPL CIRP; defence against Phoenix ARC (PHPL guarantee) and against Canara Bank/Bank of Baroda/United Bank DRT recovery (RGBL guarantee); DRT/DRAT proceedings over PREL.
-
Arbitration claims against concession authorities — e.g., ICTPL arbitration claims (management asserts recoverability), Patna Buxar Highway award (linked to VSPL loan settlement).
Initiatives in the last 24 months (Oct 2024 – Oct 2026)
| Initiative | Date | Description | Status |
|---|---|---|---|
| ICTPL OTS and change of control | FY2025 (lender assignment Sept 2024) | Lender debt assigned (Ambica Capital Markets / successor lender); company transferred shareholding, retaining 16.29% beneficial interest | Completed; INR 35 crore BG release pending |
| SSRPL OTS | Q1 FY2026 | INR 275 crore paid by authority directly to lenders; no-dues certificate releases company | Completed |
| VSPL loan settlement | Q4 FY2025 | VSPL's restructured loan to AJR linked to Patna Buxar Highway award; principal waived under final settlement terms, with balance payable on receipt of award by 30 Sep 2025 or arbitral realisation | Per CARE (VSPL), Feb 2026 |
| PHPL Supreme Court appeals | Admitted 26 Sep 2025 | Seeks to overturn Silver Point resolution plan | Pending |
| Defence of Phoenix ARC petition | Won at NCLT 4 Jul 2025 | NCLAT appeal by Phoenix ARC pending | Pending |
| RGBL DRT stay | 7 Jul 2026 | Stay on recovery proceedings pending miscellaneous applications | Next hearing 18 Sep 2026; written submissions by 13 Oct 2026 |
| Governance repair | 2,026 | CS appointed; internal auditor appointed; KMP authorisations under Reg. 30(5) | Ongoing |
Medium-term targets / guidance
None published. No ESG commitments, cost programmes with quantified targets, or new business launches have been disclosed.
Products & Services
The company does not sell products. Its "portfolio" is a set of concession assets and SPV interests. Pricing models for concessions are set by concession agreements (toll notifications, annuity schedules, port tariff/revenue-share), none of which are currently generating consolidated revenue. Each asset is catalogued individually below.
Ports
| Asset | Description & capabilities | Counterparty / customer | Start / concession | Current status |
|---|---|---|---|---|
| Vizag Seaport Pvt Ltd (VSPL) | Multi-cargo terminal at the inner harbour of Visakhapatnam Port; two multipurpose berths, aggregate design capacity 7.7 MTPA, arrival draft 16.5 m; handles all cargo except petroleum products; revenue share with port trust on berth hire and wharfage reported at 17.11% | Visakhapatnam Port Authority; bulk/break-bulk shippers | Concession Nov 2001 for 30 years (to Nov 2031); commercial operations 2004 | Associate. Ownership: Shripriya Ports 49.70%, AJR Infra 23.56%, Lastin Holdings 26.24% (CARE on VSPL, Feb 2026). VSPL also holds a restructured loan to AJR Infra linked to a Patna Buxar Highway arbitral award |
| Indira Container Terminal Pvt Ltd (ICTPL) | Offshore container berths project at Mumbai Port plus management of Ballard Pier station container terminal | Mumbai Port Authority | 2000s | Control transferred FY2025 under OTS; company retains beneficial interest in 16.29%; INR 35 crore bank guarantee outstanding |
| Blue Water Iron Ore Terminal Pvt Ltd (erstwhile Bedi Seaport) | Dedicated iron ore berth at Paradip Port, Odisha (31% stake as of 2009) | Paradip Port | 2,009 | Current status not disclosed in sources reviewed |
| Gammon Seaport Infrastructure Ltd | Port holding SPV | — | — | Subsidiary; activity not disclosed |
Roads and bridges
| Asset | Description | Concession grantor | Status |
|---|---|---|---|
| Sidhi Singrauli Road Project Ltd (SSRPL) | Highway project in Madhya Pradesh | MPRDC / MoRTH | OTS completed Q1 FY2026; INR 275 crore paid to lenders; company's guarantees released |
| Patna Highway Projects Ltd (PHPL) | Highway project in Bihar | NHAI (understood) | CIRP; Silver Point resolution plan approved May 2022; Supreme Court appeal pending |
| Rajahmundry Godavari Bridge Ltd (RGBL) | Road-cum-bridge over Godavari at Rajahmundry, Andhra Pradesh; tolling had commenced | Andhra Pradesh authorities | CIRP; control lost; exposure written off |
| Vijayawada Gundugolanu Road Project Pvt Ltd | Four-lane toll road; tolling from 1 Sep 2014 | NHAI | Subsidiary; current status not detailed |
| Birmitrapur Barkote Highway Pvt Ltd | Highway project in Odisha | NHAI (understood) | Subsidiary; status not detailed |
| Yamunanagar Panchkula Highway Pvt Ltd | Highway project in Haryana | NHAI (understood) | Subsidiary; status not detailed |
| Cochin Bridge Infrastructure Co Ltd | New Mattancherry Bridge, Kochi, Kerala | Kerala authorities | Subsidiary; legacy asset |
| Patna Buxar Highway Ltd | Highway project in Bihar; holds an arbitral award assigned to VSPL loan settlement | NHAI (understood) | Referenced as a subsidiary in CARE VSPL release (Feb 2026); not in Q1 FY2027 consolidation list |
| Exited roads (FY2016) | Andhra Expressway (Rajahmundry–Dharmavaram, INR 256 crore), Rajahmundry Expressway (Dharmavaram–Tuni, INR 248 crore), Gorakhpur bypass, Kosi Bridge, Mumbai Nasik Expressway | NHAI / states | Ceased to be subsidiaries in FY2016 |
| Gammon Road Infrastructure Ltd | Road holding SPV | — | Subsidiary; activity not disclosed |
Power and energy
| Asset | Description | Status |
|---|---|---|
| Pravara Renewable Energy Ltd (PREL) | 30 MW bagasse-based cogeneration plant on BOOT basis with Padmashri Dr. Vithalrao Vikhe Patil Sahakari Sakhar Karkhana; 25-year concession from COD | CIRP admitted Jan 2023; plant in possession of Karkhana/DRT receiver; plant reportedly auctioned by lenders; SPV auditors disclaimed opinion for FY2024 and FY2025 |
| Sikkim Hydro Power Ventures Ltd | Hydro project in Sikkim | Development ceased; accounts on non-going-concern basis; INR 18.84 crore impairment Q1 FY2027 |
| Tidong Hydro Power Ltd | Hydro project in Himachal Pradesh (Tidong) | Subsidiary; current status not disclosed |
| Youngthang Power Ventures | Hydro SPV (2009) | Status not disclosed |
| Punjab / Haryana Biomass Power | 12 MW biomass plant, Bhagaura, Patiala (commissioned Jun 2010); 50% of Punjab Biomass Power reported sold | Exited |
| Gammon Renewable Energy Infrastructure Projects Ltd | Renewable holding SPV | Subsidiary; activity not disclosed |
Other / urban / logistics
| Asset | Status |
|---|---|
| Gammon Logistics Ltd | Subsidiary; activity not disclosed |
| Gammon Projects Developers Ltd | Subsidiary; activity not disclosed |
| Tada Infrastructure Development Co Ltd; Segue Infrastructure Projects; Chitoor Infrastructure Co; Earthlink Infrastructure Projects | SEZ/urban land SPVs (Andhra Pradesh, formerly Satyavedu/Tada); status not disclosed |
| Gammon Metro Transport Ltd (erstwhile Gammon L&T Infra MRTS) | Historical; status not disclosed |
| Amritsar project (with Emaar-MGF and GE Infrastructure) | Historical 2008 consortium; outcome not disclosed |
Services
| Service line | Description | Status |
|---|---|---|
| Project development | Bidding, structuring and financing of PPP concessions | Dormant; no new bids disclosed |
| Project advisory | Advisory services to SPVs | Dormant |
| Sector-specific O&M | Toll and port O&M | No consolidated revenue since Q3 FY2025 |
Financial Narrative
Basis: Consolidated figures are from the Screener/C-MOTS standardised database, cross-checked against company filings where available. C-MOTS includes exceptional items within "other income", so PBT and net profit are post-exceptional. Standalone figures are also shown because the consolidated perimeter has shrunk dramatically as SPVs were deconsolidated. Blank cells denote not meaningful (n/m) or not disclosed.
Income statement — consolidated (INR crore)
Gross profit is not reported by the company (no cost-of-sales line under Ind AS presentation used). Sources: Screener consolidated P&L; FY2026 EPS of INR 11.80 and FY2025 EPS of INR 5.96 confirmed in company results (Q1 FY2027 and Q3 FY2026 consolidated statements). Company-reported FY2026 consolidated profit attributable to owners: INR 1,110.03 crore (INR 1,11,003.31 lakh), including exceptional income of INR 1,110.98 crore from the SSRPL settlement.
Margins and growth — consolidated
Revenue CAGR FY2021–FY2025 (INR 242 crore to INR 35 crore): approximately -38.3% per year (Screener reports -37.6% five-year). FY2026 CAGR is not meaningful (revenue nil). Net margins are not meaningful given exceptional items that are multiples of revenue.
Income statement — standalone (INR crore)
Sources: Screener standalone P&L; company FY2026 standalone audited figures (total income INR 24.01 crore, all other income; exceptional income INR 313.19 crore; PBT INR 314.15 crore; PAT INR 314.48 crore; EPS INR 3.34) per Q1 FY2027 results comparatives. FY2025 standalone loss of INR 111.72 crore (INR 11,172.09 lakh) confirmed in Q3 FY2026 results.
Source conflict flagged: ScanX (31 May 2026) reported FY2026 net profit as "INR 31.42 crore" and FY2025 loss as "INR 9.68 crore". The company's statement is in lakh (INR 31,448.36 lakh = INR 314.48 crore; FY2025 PBT INR 9,677.57 lakh = INR 96.78 crore). The ScanX figures appear to be a lakh-to-crore conversion error by a factor of ten.
Balance sheet — consolidated (INR crore, 31 March)
Sources: Screener consolidated balance sheet. FY2026 other equity of INR -1,043.88 crore confirmed by company (INR -1,04,388.33 lakh; Q1 FY2027 consolidated statement). Cash and equivalents, short/long-term debt split, goodwill/intangibles and working capital are not separately available in the sources reviewed and are therefore not publicly disclosed (in sources reviewed). Net debt cannot be computed precisely without cash; with borrowings of only INR 8 crore at FY2026, net debt is immaterial relative to the true economic leverage, which sits in "other liabilities" (invoked guarantees, dues to subsidiaries and SPV lenders) and in off-balance-sheet contingent guarantees.
Working capital proxy: Consolidated current liabilities exceeded current assets by INR 985.51 crore at 30 June 2026; standalone by INR 1,131.30 crore (Q1 FY2027 results, note 6). At 31 December 2025 the standalone gap was INR 1,101.62 crore (Q3 FY2026 results).
Balance sheet — standalone (INR crore, 31 March)
Source: Screener standalone balance sheet; FY2026 other equity INR -1,209.35 crore confirmed by company (INR -1,20,934.97 lakh).
Cash flow — consolidated (INR crore)
Capex is not separately disclosed in sources reviewed; Screener's FCF is effectively CFO (minimal capex). Source: Screener consolidated cash flows.
Cash flow — standalone (INR crore)
Source: Screener standalone cash flows. H1 FY2026 standalone operating cash outflow was INR 26.18 crore (company H1 FY2026 cash flow statement).
Ratios — consolidated
ROE, ROCE, debt/equity and net debt/EBITDA are not meaningful because equity is negative and EBITDA is negative or nil. Current ratio is below 1x in all periods (consolidated current liabilities exceed current assets by ~INR 986 crore at June 2026) but exact ratios are not disclosed in sources reviewed. ROA in FY2025–FY2026 is inflated by one-off settlement gains on a collapsing asset base. Sources: Screener ratios (debtor days, CCC); other ratios computed from Screener data.
Commentary on trends, inflections and drivers
FY2022–FY2023: impairment wave. Consolidated losses of INR 957 crore (FY2022) and INR 1,605 crore (FY2023) were driven not by operations but by write-downs: "other income" of INR -695 crore and INR -1,260 crore respectively reflects impairments and losses on loss of control of SPVs (PHPL after the May 2022 resolution-plan approval; RGBL; PREL's CIRP admission in January 2023). Standalone, the company wrote down investments from INR 1,153.83 crore (FY2021) to INR 497.44 crore (FY2023), sending standalone net worth negative in FY2023. Finance costs remained around INR 260–280 crore because SPV debt was still consolidated.
FY2024: residual operations, continuing interest burden. Revenue fell to INR 61 crore as the operating SPV perimeter shrank. Consolidated loss narrowed to INR 231 crore, but standalone took a further INR 204 crore of negative other income, chiefly in Q4 FY2024 (standalone Q4 loss of INR 224.35 crore).
FY2025: first settlement gains. Consolidated exceptional income of INR 801.35 crore (company filings; INR 801.21 crore recognised in Q2 FY2025) turned the year to a INR 541 crore consolidated profit. The FY2025 settlement/deconsolidation activity included the ICTPL one-time settlement and transfer of control; the precise itemisation of the INR 801 crore was not available in the sources reviewed. Standalone recorded an exceptional loss of INR 56.86 crore in Q2 FY2025 and an FY2025 loss of INR 111.72 crore. Consolidated finance cost fell to INR 211 crore and debt to INR 6 crore as SPV debt left the balance sheet.
FY2026: SSRPL settlement. The SSRPL one-time settlement — INR 275 crore paid to lenders against dues of approximately INR 1,104.62 crore, with the lenders issuing a no-dues certificate releasing the company from all corporate guarantees — produced consolidated exceptional income of INR 1,110.98 crore and standalone exceptional income of INR 313.19 crore (reversal of a INR 308.92 crore provision against receivables from SSRPL, plus INR 4.27 crore of unamortised guarantee commission). Excluding exceptional items, FY2026 consolidated pre-tax result was a loss of INR 0.42 crore and standalone a pre-exceptional profit of INR 0.96 crore. Consolidated net worth improved from INR -1,966 crore to INR -855 crore.
Q1 FY2027: reversion to underlying run-rate. With no revenue and no settlement gains, the standalone loss was INR 1.32 crore and the consolidated loss INR 18.89 crore, the latter including an INR 18.84 crore impairment of Sikkim Hydro PP&E. This is the clearest guide to the "steady state": a holding company costing roughly INR 5–6 crore a quarter to run (employee costs INR 0.64 crore, finance costs INR 1.01 crore, other expenses INR 4.68 crore standalone), partly offset by other income.
Quality-of-earnings conclusion. Every profitable year since FY2021 owes its profit to non-recurring settlement accounting. The recurring business generates negative cash flow. Reported EPS (INR 11.80 consolidated FY2026) has no predictive value.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansFinancial Detail
Revenue by Segment and Revenue by Segment (%)
| Metric | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|
Infrastructure / Construction & Engineering revenue — Screener (INR Cr) | 91 | 61 | 35 | 0 |
Construction & Engineering revenue — Zonebourse (INR Cr) | 53.1 | 59.8 | 34.7 | — |
Segment share of total revenue (%) | 100 | 100 | 100 | 100 |
YoY growth, Screener basis (%) | -48.9 | -33.0 | -42.6 | -100 |
Results by Segment and Segment Margins & Growth (%)
| Metric | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|
Segment EBITDA, excl. other income (INR Cr) | -10 | 6 | -16 | -20 |
Segment pre-tax income incl. exceptional items (INR Cr) | -1,601 | -229 | 557 | 1,111 |
Segment EBITDA margin (%) | -11 | 11 | -46 | — |
Income Statement and Per-Share Data
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Revenue from operations (INR Cr) | 178 | 91 | 61 | 35 | 0 |
Operating expenses (INR Cr) | 102 | 101 | 55 | 51 | 20 |
EBITDA excl. other income (INR Cr) | 76 | -10 | 6 | -16 | -20 |
Other income incl. exceptional items (INR Cr) | -695 | -1,260 | 81 | 802 | 1,135 |
Finance costs (INR Cr) | 261 | 281 | 279 | 211 | 4 |
Depreciation & amortisation (INR Cr) | 71 | 51 | 38 | 18 | 0 |
Operating income, EBITDA less D&A (INR Cr) | 5 | -61 | -32 | -34 | -20 |
Pre-tax income (INR Cr) | -951 | -1,601 | -229 | 557 | 1,111 |
Net income (INR Cr) | -957 | -1,605 | -231 | 541 | 1,111 |
EPS basic/diluted (INR) | -9.80 | -16.62 | -2.00 | 5.96 | 11.80 |
Dividend per share (INR) | 0 | 0 | 0 | 0 | 0 |
Margin Analysis (%)
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
EBITDA margin (%) | 42.7 | -11.0 | 9.8 | -45.7 | — |
Operating margin (%) | 2.8 | -67.0 | -52.5 | -97.1 | — |
Revenue growth YoY (%) | -26.4 | -48.9 | -33.0 | -42.6 | -100 |
Income Statement and Per-Share Data — Revenue from operations
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Revenue from operations (INR Cr) | 0 | 0 | 0 | 0 | 0 |
Total expenses excl. finance and D&A (INR Cr) | 5.38 | 5.66 | 26.67 | 33.96 | 19.45 |
Other income incl. exceptional items (INR Cr) | -550.72 | -1,265.34 | -204.09 | -56.60 | 337.21 |
Finance costs (INR Cr) | 0.07 | 7.74 | 9.06 | 6.18 | 3.59 |
Pre-tax income (INR Cr) | -556.22 | -1,278.77 | -239.85 | -96.77 | 314.15 |
Net income (INR Cr) | -556.75 | -1,279.40 | -240.87 | -111.72 | 314.48 |
EPS basic/diluted (INR) | -5.91 | -13.58 | -2.56 | -1.19 | 3.34 |
Balance Sheet
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Total assets (INR Cr) | 2,483 | 1,305 | 1,037 | 215 | 173 |
Fixed assets, net (INR Cr) | 722 | 565 | 489 | 20 | 20 |
Capital work in progress (INR Cr) | 159 | 67 | 67 | 0 | 0 |
Investments (INR Cr) | 602 | 319 | 114 | 45 | 86 |
Other assets incl. cash and receivables (INR Cr) | 1,000 | 354 | 366 | 151 | 68 |
Equity share capital (INR Cr) | 189 | 189 | 189 | 189 | 189 |
Reserves / other equity (INR Cr) | -924 | -2,528 | -2,716 | -2,155 | -1,044 |
Total equity (INR Cr) | -735 | -2,339 | -2,527 | -1,966 | -855 |
Borrowings, total (INR Cr) | 20 | 174 | 207 | 6 | 8 |
Other liabilities (INR Cr) | 3,198 | 3,470 | 3,356 | 2,175 | 1,020 |
Balance Sheet — Total assets
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Total assets (INR Cr) | 1,891.09 | 642.34 | 417.86 | 179.70 | 135.06 |
Investments (INR Cr) | 950.15 | 497.44 | 288.86 | 48.18 | 88.26 |
Other assets (INR Cr) | 940.85 | 144.83 | 128.95 | 131.49 | 46.79 |
Reserves / other equity (INR Cr) | 108.16 | -1,171.22 | -1,412.10 | -1,523.83 | -1,209.35 |
Total equity (INR Cr) | 297.34 | -982.04 | -1,222.92 | -1,334.65 | -1,020.17 |
Borrowings (INR Cr) | 108.32 | 46.51 | 61.49 | 6.95 | 8.07 |
Other liabilities (INR Cr) | 1,485.43 | 1,577.87 | 1,579.29 | 1,507.40 | 1,147.16 |
Cash Flow
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Operating cash flow (INR Cr) | 53 | 79 | 28 | -78 | -34 |
Investing cash flow (INR Cr) | 18 | -26 | -25 | 116 | 33 |
Financing cash flow (INR Cr) | -87 | -51 | -6 | -39 | 1 |
Net change in cash (INR Cr) | -16 | 2 | -2 | -1 | 0 |
Free cash flow, Screener definition (INR Cr) | 54 | 80 | 27 | -78 | -34 |
Dividends paid (INR Cr) | 0 | 0 | 0 | 0 | 0 |
Buybacks (INR Cr) | 0 | 0 | 0 | 0 | 0 |
Cash Flow — Operating cash flow
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Operating cash flow (INR Cr) | 4.25 | 5.62 | -19.31 | -121.37 | -31.85 |
Investing cash flow (INR Cr) | 19.96 | -29.78 | 8.02 | 142.75 | 30.67 |
Financing cash flow (INR Cr) | -24.91 | 25.07 | 9.89 | -21.37 | 1.18 |
Net change in cash (INR Cr) | -0.70 | 0.90 | -1.41 | 0.01 | 0.00 |
Returns & Leverage Ratios (%) and Financial Ratios (x)
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
ROA, net income / average total assets (%) | -30.6 | -84.7 | -19.7 | 86.4 | 572.7 |
Interest coverage, EBITDA / finance cost (x) | 0.29 | -0.04 | 0.02 | -0.08 | -5.00 |
Asset turnover, revenue / average assets (x) | 0.057 | 0.048 | 0.052 | 0.056 | 0 |
Debtor days | 97 | 182 | 220 | 217 | — |
Cash conversion cycle (days) | -5,905 | -409 | 220 | 217 | — |
Revenue by Region and Revenue by Region (%)
| Region | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
India revenue (INR Cr) | 178 | 91 | 61 | 35 | 0 |
Outside India revenue (INR Cr) | 0 | 0 | 0 | 0 | 0 |
India share of total (%) | 100 | 100 | 100 | 100 | 100 |
India revenue growth YoY (%) | -26.4 | -48.9 | -33.0 | -42.6 | -100 |
Capital Markets
| Item | Detail | Source |
|---|---|---|
Last traded price | INR 0.70 (3 Oct 2023) | Screener; IndMoney |
52-week range before suspension | INR 0.50 – INR 1.75 | IndMoney |
Last-day volume | 16.69 lakh shares | IndMoney |
Price change in 6 months before suspension | -26.3% | IndMoney |
1-year return | n/m (suspended) | Screener |
3-year price CAGR | 0% (suspended) | Screener |
5-year price CAGR | -14% | Screener |
10-year price CAGR | -18% | Screener |
Data conflict | Investing.com shows INR 0.75 on 4 Aug 2026 with previous close INR 0.70; this is inconsistent with the continuing suspension and is treated as stale/erroneous data | Investing.com |
Margin Analysis (%) and Operating Metrics (count)
| Holder | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Promoter holding (%) | 20.60 | 20.60 | 20.60 | 10.72 | 10.72 |
FII holding (%) | 10.21 | 10.21 | 10.21 | 1.09 | 1.09 |
DII holding (%) | 7.17 | 17.96 | 7.18 | 17.05 | 7.18 |
Public holding (%) | 62.02 | 51.24 | 62.01 | 71.14 | 81.01 |
Number of shareholders (count) | 127,800 | 120,873 | 119,117 | 119,040 | 118,998 |
Per-Share Data
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Consolidated EPS (INR) | -9.80 | -16.62 | -2.00 | 5.96 | 11.80 |
Standalone EPS (INR) | -5.91 | -13.58 | -2.56 | -1.19 | 3.34 |
Consolidated book value per share (INR) | -7.77 | -24.73 | -26.72 | -20.79 | -9.04 |
Dividend per share (INR) | 0 | 0 | 0 | 0 | 0 |
Valuation Multiple Details
| Valuation multiple (at INR 0.70) | Value | Comment |
|---|---|---|
P/E on FY2026 consolidated EPS | ~0.06x | Meaningless — exceptional-driven |
P/E on FY2026 standalone EPS | ~0.21x | Meaningless — exceptional-driven |
P/E on TTM consolidated EPS (INR -0.11) | n/m | Loss-making |
P/B | n/m | Negative book value |
EV/EBITDA | n/m | Negative EBITDA |
EV/Sales | n/m | Zero revenue |
Credit Ratings
| Agency | Instrument | Rating | Date |
|---|---|---|---|
CARE Ratings | LT bank facilities — cash credit, INR 25 crore | CARE D; Issuer Not Cooperating | 24 Jul 2026 (reaffirmed) |
CARE Ratings | ST bank facilities — bank guarantee, INR 35 crore | CARE D; Issuer Not Cooperating | 24 Jul 2026 (reaffirmed) |
Moody's / S&P / Fitch | — | Not rated | — |
Analyst Conclusions
Management guidance
None. Management states in each filing that it is confident the going-concern assumption and carrying values are appropriate, while acknowledging that planned resolutions have been pending a long time (Q1 FY2027 note 6). There is no revenue, profit or deleveraging guidance.
Consensus expectations
No consensus exists. The rational base case is a quarterly standalone cash burn in the low single-digit INR crore range, with periodic large non-cash swings from litigation and settlement outcomes.
Bull-case arguments
-
The guarantee overhang is shrinking. SSRPL's OTS removed one entire guarantee chain and generated INR 1,110.98 crore of consolidated exceptional income; consolidated net worth improved by over INR 1,100 crore in FY2026. If the Phoenix ARC appeal fails at NCLAT, the single largest exposure (INR 1,190.24 crore) falls away.
-
Legal asymmetry on PHPL. The Supreme Court admitted both appeals and directed expedition (26 Sep 2025). Because the company's PHPL funded exposure (INR 212.95 crore) is already fully provided, any favourable outcome is pure upside.
-
Hidden residual assets. A 23.56% stake in an operating port to 2031, a 16.29% beneficial interest in ICTPL with INR 48.33 crore funded exposure management considers recoverable, and arbitration awards (e.g., Patna Buxar) could exceed the ~INR 66 crore market value implied at the last traded price.
Bear-case arguments
-
Liabilities still overwhelm assets. Consolidated total assets were INR 173 crore at March 2026 against negative equity of INR 855 crore, a INR 986 crore working-capital gap and ~INR 1,515 crore of contested non-funded exposures. Even a string of wins leaves equity deeply negative.
-
No operating engine. Q1 FY2027 shows the steady state: zero revenue, a standalone loss and an impairment (Sikkim Hydro). Every "profit" in FY2025–FY2026 came from one-off settlements.
-
Governance and listing risk. Months-late results, a period without a compliance officer, rating-agency non-cooperation and a three-year trading suspension raise the probability of compulsory delisting, under which minority holders typically recover little.
Catalysts and monitorables (next 12 months)
| Catalyst | Expected window | Impact |
|---|---|---|
| NCLAT hearing on Phoenix ARC appeal (CA (AT)(Ins) 1083/2025) | Not notified | Binary: INR 1,190 crore exposure |
| Supreme Court hearing on PHPL appeals | Not notified (expedition directed) | Potential recovery |
| RGBL DRT miscellaneous applications decision (after 13 Oct 2026 submissions) | Q3–Q4 FY2027 | Could unwind or crystallise INR 697 crore booked liability and stay |
| PREL DRT Delhi final order (OA 69) and DRT Mumbai auction IA | H2 FY2027 | INR 191.67 crore non-funded exposure |
| NCLT Delhi Section 65 IA-4455/2024 | Ongoing | Potential leverage in PHPL dispute |
| ICTPL BG replacement | Not scheduled | Removes INR 35 crore contingent |
| Timeliness of Q2 FY2027 (due mid-Nov 2026) and Q3 FY2027 results | Nov 2026 / Feb 2027 | Test of governance repair; prerequisite for revocation of suspension |
| Exchange action on suspension (revocation vs. delisting) | Unknown | Determines whether equity value is accessible at all |
| CARE rating review | ~mid-2027 | Cooperation with CARE would signal improved disclosure |
Concluding analyst verdict
AJR Infra and Tolling is best understood not as an infrastructure company but as a distressed litigation and liability-management shell carrying the remnants of Gammon Infrastructure Projects' once ambitious PPP portfolio. The headline numbers mislead in both directions. FY2026's INR 1,110 crore consolidated profit and INR 11.80 EPS are artefacts of the SSRPL settlement, not evidence of earning power; the Q1 FY2027 loss on zero revenue is the true run-rate. Equally, the deeply negative net worth overstates certainty of loss, because a significant share of the liability stack is contested and has been moving in the company's favour: the SSRPL guarantee is gone, the NCLT has dismissed Phoenix ARC's INR 1,190 crore claim, the Supreme Court has admitted the PHPL appeals, and DRT has stayed RGBL recovery.
The investment problem is access and governance rather than arithmetic. Shares have not traded since October 2023, the company sits in the exchanges' non-compliance series, its rating agency reports non-cooperation, and FY2026 quarterly disclosures arrived months late. Until the company demonstrates sustained compliance — timely quarterly filings, a functioning compliance office and engagement with CARE — the equity is effectively untradeable and exposed to delisting. The promoter's fully pledged 10.72% stake and its own default status mean there is no sponsor to backstop a revival.
For creditors and claimants, the next twelve months are pivotal: the Phoenix ARC appeal and the RGBL DRT proceedings alone could swing the liability base by roughly INR 1,900 crore. For equity holders, even the best realistic outcome — winning most cases and monetising the VSPL and ICTPL interests — would likely leave the company a small, asset-light shell with negative or marginal net worth and no business model. The verdict is avoid / not investable: monitor only as a special-situations litigation story, with any reconsideration contingent on revocation of the trading suspension and a decisive NCLAT ruling against Phoenix ARC.
Source register
| Source | Use |
|---|---|
| AJR Infra Q1 FY2027 results and board outcome, 13 Aug 2026 (NSE archive) | Financials, notes on all SPVs, litigation, KMP, auditors, consolidation list |
| AJR Infra Q1/Q2/Q3 FY2026 results, approved 24 Feb 2026 (NSE archive) | FY2026 interim figures, SSRPL exceptional items, cash flows |
| AJR Infra Q2 FY2025 results, 14 Nov 2024 | FY2025 exceptional items |
| Auditor's report on FY2025 standalone statements (IIFL reproduction) | Going-concern and SSRPL OTS status at Mar 2025 |
| Reg. 30 letters: 9 Jan 2023 (PREL CIRP), 30 Mar 2024, 16 Apr 2024 (Statkraft called off), 30 Sep 2024 (ICTPL), 31 Dec 2024, 12 Feb 2025 (Mali reappointment), 26 Jun 2025, 25 Sep 2025, 29 Dec 2025 (Chaganti resignation), 24 Mar 2026 | Governance and corporate events |
| CARE Ratings press releases: 1 Mar 2023; 24 Jul 2026; Vizag Seaport 12 Feb 2026 | Ratings, company profile, VSPL ownership |
| NCLAT order, 16 May 2023 (IBBI) | RGBL appeals withdrawn |
| Screener.in (C-MOTS data), standalone and consolidated pages | Multi-year P&L, balance sheet, cash flow, ratios, shareholding, announcements |
| IIFL, Goodreturns, ICICI Direct, PL India company histories | Historical milestones |
| PortNews (Reuters), Construction World, TXF News, Venture Intelligence | VSPL transactions |
| Morningstar, Zonebourse, Investing.com, Simply Wall St, IndMoney, ScanX, Multibagg, HDFC Securities | Employees, segment data, management, price data, news summaries (discrepancies flagged where found) |
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansExecutive Leadership
Executive Leadership Team
| Name | Title | Tenure | Background | Age |
|---|---|---|---|---|
Mineel Madhukar Mali (DIN 06641595) | Whole-Time Director (de facto chief executive) | WTD since 1 Apr 2021; reappointed for 3 years from 1 Apr 2025 (board, 12 Feb 2025) | Commerce graduate from Mumbai; described in FY2022 annual report as having over three decades of professional experience | ~61 (Simply Wall St) |
Vinay Sharma | Chief Financial Officer | — | — | — |
Amatulla Akil Chunawala (ACS 80050) | Company Secretary & Compliance Officer | Appointed June 2026 | Expertise in securities law, Companies Act and corporate compliance | — |
“—” = not publicly disclosed.
Board of Directors
| Name | Category | Notes |
|---|---|---|
Mineel Mali | Executive, Whole-Time Director | Signs all results; board's sole executive member |
Subhrarabinda Birabar | Non-Executive (described variously as independent in FY2022 annual report and as additional non-executive non-independent director by Simply Wall St) | Post-graduate in logistics; reappointed (retire-by-rotation) at 25th AGM, 29 Sep 2026; co-signed FY2025 audited results in WTD's absence |
Mahendra Kumar Agrawala | Independent Director | Reappointed as additional director (independent) effective 31 Oct 2023 after first five-year term |
Srinivasu Chaganti (DIN 06387528) | Non-Executive Director | Resigned 29 Dec 2025, citing personal reasons |
Other independent directors | Independent | The FY2022 annual report listed five independent/non-executive seats in addition to the WTD; names and current tenure of remaining members not confirmed in sources reviewed |
Board & Management Changes
| Date | Change |
|---|---|
1 Apr 2021 | Mineel Mali appointed WTD |
31 Oct 2023 | M.K. Agrawala reappointed independent director |
12 Feb 2025 | Mali reappointed WTD for 3 years from 1 Apr 2025 |
30 May 2025 | FY2025 results signed by authorised non-executive directors (incl. Birabar) due to WTD's absence; company later clarified this to NSE |
29 Dec 2025 | Chaganti resigns |
Dec 2025 | "Change in Management" Reg. 30 disclosure filed |
Jun 2026 | Chunawala appointed CS & Compliance Officer |
29 Sep 2026 | Birabar reappointed at AGM |
Major Shareholders
| Holder category | % (Sep 2026) |
|---|---|
Promoter — Gammon India Ltd (100% pledged/encumbered) | 10.72 |
Foreign institutional investors | 1.09 |
Domestic institutional investors (incl. banks) | 7.18 |
Public / non-institutional | 81.01 |
Number of shareholders | 118,969 |
Competitive Landscape
Competitors by Segment
| Segment | Competitor | Relative positioning vs AJR Infra |
|---|---|---|
Roads – BOT/HAM/toll | IRB Infrastructure Developers | Large toll-road developer with InvIT-based capital recycling; scale and balance sheet far beyond AJR |
Roads – BOT/HAM | Ashoka Buildcon | Integrated EPC + developer; asset monetisation executed successfully |
Roads – HAM/EPC | Dilip Buildcon | EPC-led developer; asset sales to Shrem InvIT |
Roads – HAM/EPC | PNC Infratech | HAM portfolio with asset sales; investment-grade-type profile relative to AJR |
Roads – BOT | Sadbhav Infrastructure Project / Sadbhav Engineering | Peer that also suffered heavy stress from BOT leverage; partial analogue |
Roads – BOT | IL&FS Transportation Networks | Collapsed developer; closest analogue for systemic BOT failure |
Roads/infra | Reliance Infrastructure | Settled toll-road SPV debts (e.g., JR Toll Road, INR 273 crore, 2025) via parent support |
Ports | Adani Ports & SEZ | Dominant private port operator; once reported as suitor for VSPL stake |
Ports | JSW Infrastructure | Fast-growing private port operator |
Ports (Vizag) | Visakha Container Terminal / other Vizag berth operators | Direct local competitors for VSPL cargo |
EPC parent peer | Hindustan Construction Co (HCC) | Legacy EPC-developer that also shed BOT assets under stress |
Hydro / renewables | Statkraft (as investor), NHPC, SJVN, Greenko | Well-capitalised developers; Statkraft walked away from Sikkim Hydro |
Competitor Detail
| Metric | AJR Infra (FY2026, consolidated) |
|---|---|
Revenue (INR Cr) | 0 |
Revenue growth YoY (%) | -100 |
EBITDA margin (%) | n/m |
Net worth (INR Cr) | -855 |
Credit rating | CARE D (INC) |
Recent Developments
Entries before April 2025 are included where needed for context.
Outcomes of the 17 Aug, 31 Aug, 18 Sep and 22 Sep 2026 hearings were not available in sources reviewed.