Ausgold Limited Overview
Ausgold Limited is a Perth-based gold developer whose value rests almost entirely on the 100%-owned Katanning Gold Project in the south-west Yilgarn Craton of Western Australia, about 275km south-east of Perth. KGP hosts a 2.44Moz JORC Mineral Resource (68.6Mt at 1.11g/t Au, 63% Measured) and a 1.33Moz Ore Reserve (37.4Mt at 1.11g/t, 83% Proved). The December 2025 DFS Update outlines a 10.3-year open-pit, free-milling operation producing 1.22Moz recovered, averaging 143koz a year over the first four years, at a life-of-mine AISC of A$2,252/oz. Pre-production capital is A$354m. At a A$4,300/oz base case the study shows a post-tax NPV5 of A$1.03bn and an IRR of 52.4%. Ausgold holds roughly 3,000km² of surrounding tenure, has no revenue and no debt, and was advancing toward a final investment decision in late 2026. It has now agreed to be acquired by OceanaGold for scrip (with a capped cash election), implying A$776m.
Company's own description
In its FY2026 Annual Report, Ausgold describes its principal activities as developing its wholly owned Katanning Gold Project and exploring for gold and other precious metals. In public messaging it has repeatedly set out the ambition of becoming Australia's next mid-tier gold producer, and its LinkedIn description positions KGP as a long-life, low-risk operation in the south-west Yilgarn. The FY2026 Chairman's Letter describes the year as the move from project evaluation to active pre-development, with FID targeted by the end of calendar 2026.
Independent characterisation
Ausgold is a single-asset, pre-revenue gold developer at the late-feasibility, early-works stage. The investment case has three parts:
-
A large, shallow, free-milling, bulk-tonnage deposit in a Tier-1 jurisdiction. A 17km mineralised trend, about 10km of which is modelled resource, spread across three zones: Northern (Datatine), Central (Jackson, Olympia, White Dam, Jinkas, Jinkas South — about 90% or 2.19Moz of the resource) and Southern (Dingo, Lukin).
-
Unusually well-advanced enabling infrastructure for a pre-FID project. This includes freehold land ownership over the development footprint, granted Mining Leases over all areas needed for development (as of the FY2026 Annual Report), a 250-room workforce village under construction, early works agreements with an EPC contractor (Lycopodium) and a build-own-operate power provider (CrossBoundary Energy), and good road and regional-town access — 3.5 hours' drive from Perth, near the Katanning regional hub.
-
District-scale exploration optionality. Roughly 3,000km² of the Katanning Greenstone Belt and adjacent trends (Stanley Thrust, Yandina Thrust), including the Nanicup Bridge satellite prospect 40km south-east of KGP and underground potential at Datatine.
The company's position in the value chain is upstream exploration and mine development. It has no customers today. Once in production, revenue would come from selling doré or refined bullion to a refinery or bullion bank at spot (the DFS assumes 99.9% payable and a 2.5% WA state royalty). There is no subscription, licensing or service revenue. The end-market is the global gold market (investment, central bank, jewellery and industrial demand), which prices in US dollars; Ausgold's costs are in Australian dollars, so it carries natural AUD-gold price leverage.
Revenue model mix
| Revenue type | Current (FY2026) | Future (post-production, per DFS) |
|---|---|---|
| Product sales (gold) | Nil | ~100% of revenue; LOM net revenue A$5,104m at A$4,300/oz (Dec-25 DFS Update) |
| Services | Nil | Nil |
| Subscription / licensing | Nil | Nil |
| Other income | Interest income A$2.52m (FY2026); minor government grants/EIS co-funding | Interest income |
Key operating parameters (December 2025 DFS Update)
| Parameter | Value |
|---|---|
| Mining method | Conventional open pit (drill, blast, load and haul) |
| Ore processed (LOM) | 37.6Mt at 1.11g/t Au |
| Implied throughput | ~3.6–3.7Mtpa (DFS based on an initial 3.6Mtpa plant; future expansion to 5–5.5Mtpa flagged in October 2024) |
| Strip ratio | 7.02 (waste:ore) |
| Metallurgical recovery | 90.4% |
| Recovered gold (LOM) | 1,219,511oz |
| Mine life (gold production) | 10.3 years |
| Average production, years 1–4 | 143koz per year |
| C1 cash cost (LOM) | A$2,051/oz |
| AISC (LOM / years 1–4) | A$2,252/oz / A$2,157/oz |
| Pre-production capex | A$354m (incl. contingency) |
| Power | Hybrid gas + solar + battery storage, build-own-operate (CrossBoundary Energy) |
| Workforce accommodation | 250-room village in Katanning town, 40km bus commute |
Strategy
Stated strategy (FY2026 Annual Report, paraphrased)
Accelerated, parallel development: advance engineering, infrastructure, permitting and procurement before FID to reduce execution risk and shorten the time from FID to first gold.
De-risk through enabling infrastructure: secure land, accommodation, power and EPC capability ahead of the investment decision.
Keep growing the resource: continue in-fill and extensional drilling to expand and upgrade the 2.44Moz resource, convert Resources to Reserves, test underground potential (Datatine, Jinkas Deeps) and define satellite deposits (Nanicup Bridge).
Social licence: build partnerships with the Shire of Katanning, Traditional Owners (WKSNAC) and the Great Southern community; local employment and procurement.
Ambition: become Australia's next significant long-life gold producer (repeatedly described as a "mid-tier" producer).
Strategic initiatives — last 24 months
| Initiative | Date | Detail | Status |
|---|---|---|---|
| DFS (Jun 2025) and DFS Update (Dec 2025) | Jun & Dec 2025 | Feasibility-level definition of a 10.3-year, 1.22Moz operation | Complete |
| Land acquisition programme | Aug–Oct 2025 | ~860ha (A$35m), 240ha (A$3m), 348ha | Complete except A$20m second instalment (due by 26 Aug 2026 or FID) |
| Drilling campaign | Sep 2025 → | Started at 44,000m, expanded to 54,000m; 56,115m (373 holes) done by 30 Jun 2026; 25,000m RC grade-control-style infill at 20m × 20m over the first two years of mine life | Ongoing |
| Workforce Accommodation Village | Nov 2025 lease; Apr 2026 contract | 250 rooms, A$30.1m, ADD Business Group fixed price; reverts to Shire at end of mine life | Construction; first stage November 2026 |
| EPC early works | Jun-26 quarter | Lycopodium — detailed engineering, execution planning, vendor data | Ongoing |
| Hybrid power BOO | Jun-26 quarter | CrossBoundary Energy — gas/solar/BESS; long-lead deposits | Ongoing |
| Permitting via WA Priority Approvals Program | Nov 2025 → | EPA (ARI with public review), EPBC (Preliminary Documentation), Works Approval (DWER), MDCP (DMPE) | In progress; ERD publicly released July 2026 |
| Traditional Owner agreement | FY2026 | Binding Consultation and Cooperation Agreement with WKSNAC | Executed |
| Revegetation | Winter 2026 | Initial 30ha, mostly done by Katanning Landcare | Under way |
| Debt financing | 2025–26 | Debt financing discussions disclosed; no facility signed | Superseded by OceanaGold scheme |
| Sale of company | 17 Aug 2026 | Scheme with OceanaGold | Pending (vote late November 2026) |
Medium-term targets and guidance
| Target | Latest guidance | Prior guidance | Source |
|---|---|---|---|
| FID | By end of CY2026 | Mid-CY2026 (Jan 2026); mid-2026 (Sep 2025) | Jun-26 quarterly; Dec-25 quarterly |
| Construction start | Early CY2027 | — | FY2026 Annual Report |
| First gold | Mid-CY2028 | End-2027 (H1 FY26 investor material); late CY2027 (June 2025 DFS context) | Jun-26 quarterly; Quartr |
| Production years 1–4 | ~143koz per year | 140koz (Jun-25 DFS) | DFS Update |
| AISC LOM | A$2,252/oz | A$2,265/oz | DFS Update |
| ESG / emissions targets | — | — | — |
There is no formal earnings or revenue guidance; the company is pre-production. If the scheme is implemented, future development decisions pass to OceanaGold.
Products & Services
Ausgold sells no products or services. Its "portfolio" is a set of mineral assets at different stages, catalogued below as the equivalent of product lines.
Katanning Gold Project (flagship, 100%)
| Attribute | Detail |
|---|---|
| Description | Open-pit, free-milling gold project on a 17km mineralised trend within the Katanning Greenstone Belt, ~40km north-east of Katanning |
| Mineral Resource (Dec-2025, unchanged from Jun-2025) | Measured 41.6Mt @ 1.14g/t (1.531Moz); Indicated 21.2Mt @ 1.02g/t (0.693Moz); Inferred 5.9Mt @ 1.16g/t (0.219Moz); Total 68.6Mt @ 1.11g/t for 2.443Moz |
| Ore Reserve (Dec-2025) | Central Zone: Proved 29.1Mt @ 1.14g/t (1,070.0koz), Probable 5.4Mt @ 0.96g/t (168.7koz). South Zone: Proved 1.2Mt @ 0.97g/t (36.5koz), Probable 1.7Mt @ 1.01g/t (54.6koz). Total 37.4Mt @ 1.11g/t for 1,329.7koz |
| Competent Persons | MRE: Dr Michael Cunningham (SRK), Daniel Guibal (Condor Consulting), Graham Conner (Ausgold). Reserves: Jake Fitzsimons (Orelogy) |
| Price assumptions | Resource pit shell A$4,500/oz; Reserves A$3,000/oz; revenue base case A$4,300/oz (US$2,795/oz at AUD/USD 0.65) |
| Target customer | Refiners / bullion purchasers (offtake not yet contracted) |
| Latest "version" | DFS Update, 16 December 2025 |
| Pricing model | Spot gold price, 99.9% payable, less 2.5% WA royalty |
| Zone | Deposits | Notes |
|---|---|---|
| Northern | Datatine | Some of the highest grades at KGP; deep diamond hole BSDD062 hit 9.5m @ 2.44g/t from 512m (~500m down-plunge); underground studies (stope optimisation) under way |
| Central | Jackson, Olympia, White Dam, Jinkas, Jinkas South | ~90% (2.19Moz) of resource; the Jinkas–White Dam synformal structure is the main value driver; EIS-funded deep drilling tests up to 700m down-plunge |
| Southern | Dingo, Lukin | 91koz Reserve; extension intercepts incl. 20m @ 1.20g/t from 180m (BSRC1880); 240ha land buffer bought to allow Dingo growth |
KGP deposits by zone
Katanning Regional — Nanicup Bridge
About 40km south-east of KGP with direct road access. 66 RC holes (5,955m) on 50m × 100m spacing confirmed multiple thick lodes over at least 1km of strike, striking north-south and dipping ~30° east, open from surface, with a supergene blanket locally above 2g/t. Best results include 42m @ 0.55g/t from 102m (NBRC030) and 19m @ 0.90g/t from 24m (NBRC027). The stated aim is a maiden Mineral Resource and a satellite feed source (FY2026 Annual Report).
Kraken (formerly Kulin Gold Project)
On the Yandina Thrust, which also hosts the Griffins Find and Tampia gold mines. It is a large geophysical anomaly with gold-in-soil anomalism above 100ppb along its southern strike (E70/6757). Drilled during the 9,000m regional RC programme; results pending at the FY2026 report date.
Moulyinning
Regional prospect with a large-scale anomaly. Drilled in the regional programme; results pending at the FY2026 report date.
Stanley Gold Project (80% farm-in)
At the northern end of the Stanley Thrust, a regional fault more than 100km long, about 25km east of KGP, with a coherent gold-in-soil anomaly (>10ppb) along much of its length. New EL applications cover the Nyabing Prospect (E70/6749) and the Mineral Hill Prospect (E70/6754).
Other regional holdings
Woodanilling (100%), Calyerup Creek (100%), Duggan Prospect (E70/6758), and Lake Magenta (100%, farmed out to Serena Minerals: 51% for A$500k over 24 months, then a further 34% for A$250k over 12 months). In FY2026 about 690km² of non-prospective tenure was surrendered.
Legacy assets (historical)
Cracow (gold, Queensland), Yamarna (Ni-Cu-Co, WA) and Doolgunna Station (Cu-Au, WA) appear in aggregator profiles but not in the 30 June 2026 tenement schedule. Their current status — relinquished or sold — and the dates are not publicly disclosed in the sources reviewed.
Financial Narrative
Income statement
Source: FY2026 Annual Report, Remuneration Report five-year performance table; KMP totals from the FY2026 Remuneration Report. Diluted EPS is N/A (anti-dilutive). Operating income, EBITDA and gross/operating/EBITDA/net margins are not meaningful at nil revenue; EBITDA is not reported. Revenue CAGR: not meaningful.
Commentary. Losses rose steadily from A$2.6m (FY2022) to A$10.7m (FY2025) as the company moved from exploration to PFS, DFS and pre-development, built a development team, and booked larger share-based payments after the 2024 board renewal. The FY2026 loss fell 9.6% to A$9.7m despite much higher activity. Two things explain this. First, interest income jumped to A$2.52m on the larger cash balance after the A$125m of FY2026 raisings. Second, Ausgold capitalises most project spending — land, PP&E and evaluation — on the balance sheet rather than expensing it. Share-based payments were about A$3.6m in FY2026 (Quartr summary of the FY2026 result); KMP option and rights expense alone was A$2.85m. The 1.99c loss per share reflects a weighted average of roughly 488m shares.
Balance sheet
Sources: FY2026 Annual Report (cash, both years); Appendix 5B reports (no loan facilities). Borrowings shown as nil per Appendix 5B section 7 (no loan, credit standby or other facilities); a small lease or hire-purchase liability exists (FY2026 repayments of borrowings A$23k). Goodwill assumed nil as there have been no business combinations; not separately verified.
Quarterly cash trajectory (A$m)
Source: Appendix 5B reports for Dec-2025 and Jun-2026; Quartr summary of the Mar-2026 quarterly.
Commentary. The balance sheet changed completely in FY2026. Cash went from A$12.0m to A$87.4m on A$125.15m of gross equity raised (A$35m in July 2025; A$80m placement plus A$10m SPP in November–December 2025, Tranche 2 settling in January 2026) and A$3.9m of option exercises. Land and village spending were capitalised. One known liability stands out: the A$20m second instalment of the 860ha land purchase, payable at the earlier of FID or 26 August 2026 — after the FY2026 balance date. The September 2026 quarterly, which would confirm payment, had not been reviewed at the cut-off. OceanaGold has also agreed to provide an A$20m bridge loan in November 2026 for working capital before completion (Mining Technology, 17 August 2026), so Ausgold's first debt is likely to be intra-transaction.
Cash flow statement
Source: Appendix 5B for the quarter ended 30 June 2026 (year-to-date column = FY2026).
FY2026 quarterly cash flows (A$m)
Sources: Dec-2025 and Jun-2026 Appendix 5Bs; Mar-2026 figures via Quartr. Q1 values derived as H1 year-to-date minus Q2. In Q2 FY26, net equity inflow is placement and SPP proceeds net of costs, excluding A$2.0m from option exercises.
Commentary. Spending on exploration and evaluation sped up sharply through FY2026, rising almost fivefold from Q1 to Q4 as the 54,000m drill programme, EPC early works, environmental studies and village construction ramped up. The Q4 run-rate of about A$10.5m in net "relevant outgoings" gave 8.4 quarters of funding on the Appendix 5B measure. That measure leaves out the A$20m land instalment, the A$30.1m village EPC contract (paid progressively) and long-lead deposits, so the real runway before FID was much shorter. This is a key reason a corporate transaction or major financing was needed by late 2026.
Ratios
Current ratio, asset turnover and cash conversion cycle are not meaningful (no revenue, no inventory, no receivables beyond GST). Net debt is negative (net cash) in all periods reviewed; interest coverage is not applicable as there is no interest-bearing debt.
Forward project economics — the relevant "financials"
Source: December 2025 quarterly, summarising the 16 December 2025 DFS Update; base case A$4,300/oz, AUD/USD 0.65, 5% real discount rate, 30% tax.
Commentary. The DFS Update added 82koz of LOM production and about A$75m of NPV, almost entirely by mining Central Zone ore that the June 2025 plan had left out because of the eastern boundary of ML70/211, and by moving waste dumps closer to cut haulage. The longer payback (17 vs 13 months) reflects the profile and phasing changes, not weaker economics. At the A$6,400/oz spot price prevailing in December 2025, post-tax NPV5 rises to A$2.30bn and IRR to 92%. That leverage is the core of both the bull case and OceanaGold's interest. At base case, life-of-mine revenue averages roughly A$495m a year — about 64x Ausgold's FY2026 cash operating overhead.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansFinancial Detail
Key Financials and Per-Share Data
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Revenue (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Interest income (AUD Mn) | 0.002 | 0.05 | 0.15 | 0.61 | 2.52 |
Gross profit (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Net loss before tax (AUD Mn) | -2.59 | -5.23 | -8.34 | -10.75 | -9.72 |
Income tax (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Net loss after tax (AUD Mn) | -2.59 | -5.23 | -8.34 | -10.75 | -9.72 |
Basic loss per share (A cents) | -1.5 | -2.5 | -3.6 | -3.1 | -1.99 |
Dividends per share (A cents) | 0 | 0 | 0 | 0 | 0 |
KMP remuneration expense (AUD Mn) | — | — | — | 3.50 | 4.57 |
Key Financials and Share Count (m)
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Cash & equivalents (AUD Mn) | — | — | — | 12.03 | 87.36 |
Total borrowings (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Net cash (AUD Mn) | — | — | — | 12.03 | 87.36 |
Goodwill & intangibles (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Shares on issue (m) | — | — | — | — | 547.86 |
Key Financials and Share Count (m) (Jun-2025–Jun-2026)
| Metric | Jun-2025 | Sep-2025 | Dec-2025 | Mar-2026 | Jun-2026 |
|---|---|---|---|---|---|
Cash at quarter end (AUD Mn) | 12.03 | 23.44 | 75.60 | 97.87 | 87.36 |
Shares on issue at quarter end (m) | — | — | 508.64 | — | 547.86 |
Cash Flow
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Net operating cash flow (AUD Mn) | — | — | — | — | -1.65 |
Payments for PP&E incl. land (AUD Mn) | — | — | — | — | -22.34 |
Payments for exploration & evaluation (AUD Mn) | — | — | — | — | -23.63 |
Net investing cash flow (AUD Mn) | — | — | — | — | -46.04 |
Free cash flow (operating + investing) (AUD Mn) | — | — | — | — | -47.69 |
Gross equity raised (AUD Mn) | — | — | — | — | 125.15 |
Option exercise proceeds (AUD Mn) | — | — | — | — | 3.93 |
Equity issue costs (AUD Mn) | — | — | — | — | -6.04 |
Net financing cash flow (AUD Mn) | — | — | — | — | 123.02 |
Dividends paid (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Share buybacks (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Balance Sheet
| Metric | Q1 FY26 (Sep-25) | Q2 FY26 (Dec-25) | Q3 FY26 (Mar-26) | Q4 FY26 (Jun-26) |
|---|---|---|---|---|
Exploration & evaluation outflow (AUD Mn) | 2.52 | 3.32 | 5.62 | 12.17 |
Staff costs (AUD Mn) | 1.13 | 0.97 | 0.43 | 0.40 |
Admin & corporate costs (AUD Mn) | 1.52 | 0.89 | 1.15 | 0.38 |
Net equity inflow (AUD Mn) | — | 57.99 | 28.42 | 0 |
Financial Analysis
| Ratio | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Debt / equity (x) | 0 | 0 | 0 | 0 | 0 |
Net debt / EBITDA (x) | 0 | 0 | 0 | 0 | 0 |
Financial Analysis — Mine life
| Metric | Jun-25 DFS (LOM) | Dec-25 DFS Update (LOM) |
|---|---|---|
Mine life (years) | 9.7 | 10.3 |
Ore Reserve (Moz) | 1.253 | 1.330 |
Ore mined / processed (Mt) | 35.34 | 37.65 |
Waste mined (Mt) | 242.1 | 264.4 |
Strip ratio (x) | 6.85 | 7.02 |
Head grade (g/t) | 1.11 | 1.11 |
Recovery (%) | 90.4 | 90.4 |
Gold recovered (koz) | 1,137 | 1,220 |
Net revenue (AUD Mn) | 4,759 | 5,104 |
Operating costs (AUD Mn) | 2,345 | 2,501 |
Sustaining capital incl. closure (AUD Mn) | 125 | 131 |
Pre-production capital (AUD Mn) | 355 | 354 |
Pre-tax free cash flow (AUD Mn) | 1,934 | 2,118 |
Tax paid (AUD Mn) | 565 | 618 |
Post-tax free cash flow (AUD Mn) | 1,369 | 1,500 |
C1 cash cost (A$/oz) | 2,062 | 2,051 |
AISC (A$/oz) | 2,265 | 2,252 |
Payback (months) | 13 | 17 |
Post-tax NPV5 (AUD Mn) | 954 | 1,028 |
Post-tax NPV5 (USD Mn) | 620 | 668 |
Post-tax IRR (%) | 53.2 | 52.4 |
Results by Region
| Region | FY2024 | FY2025 | FY2026 |
|---|---|---|---|
Australia — operating revenue (AUD Mn) | 0 | 0 | 0 |
Australia — interest income (AUD Mn) | 0.15 | 0.61 | 2.52 |
Rest of world — revenue (AUD Mn) | 0 | 0 | 0 |
Share Price and Margin Analysis (%)
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Share price at start of FY (AUD) | 0.43 | 0.46 | 0.46 | 0.36 | 0.64 |
Share price at end of FY (AUD) | 0.46 | 0.46 | 0.36 | 0.64 | 0.79 |
FY share price change (%) | 7.0 | 0.0 | -21.7 | 77.8 | 23.4 |
Capital Markets
| Metric | At A$1.065 (pre-bid) | At A$1.36 (scheme implied) |
|---|---|---|
Equity value (AUD Mn) | ~583 (basic) | ~776 (fully diluted) |
Less cash at 30 Jun 2026 (AUD Mn) | 87 | 87 |
Enterprise value (AUD Mn) | ~496 | ~689 |
EV / Resource oz (A$/oz) | ~203 | ~282 |
EV / Reserve oz (A$/oz) | ~373 | ~518 |
Price / post-tax NPV5 at A$4,300/oz (x) | ~0.57 | ~0.75 |
Price / post-tax NPV5 at A$6,400/oz (x) | ~0.25 | ~0.34 |
P/E, EV/EBITDA, EV/Sales | n/m (loss-making, pre-revenue) | n/m |
P/B | — | Not calculated |
Analyst Ratings & Targets
| Broker / source | Date | Rating | Target / valuation |
|---|---|---|---|
Bell Potter | 19 Aug 2026 | Speculative Hold (downgraded) | A$1.50 (10% premium to the initial offer, recognising AUC is in play) |
Canaccord Genuity | Mid-2026 (pre-bid) | Positive | Implied ~A$3.45 (a 238% return from A$1.02, per Motley Fool) |
Euroz Hartleys (Mike Millikan) | 2025 | Supportive commentary | — |
TipRanks aggregate | Late 2025 | Buy | A$2.05 (aggregator) |
Simply Wall St | 2026 | — | Covered by 2 analysts |
“—” = not publicly disclosed.
Capital Markets — Dividend history
| Item | Detail |
|---|---|
Dividend history | None ever paid |
Dividend policy | None (pre-production) |
Credit ratings (Moody's / S&P / Fitch) | Not rated |
Debt maturity profile | No debt at 30 June 2026; A$20m OGC bridge loan expected November 2026 |
Share Price & Returns
| Date | Type | Amount (AUD Mn) | Price (AUD) |
|---|---|---|---|
Jul 2024 | Institutional placement | ~38 | — |
Jul 2025 | Placement | 35 | — |
Nov 2025 – Jan 2026 | Placement (two tranches) | 80 | 0.80 |
Dec 2025 | Share Purchase Plan | 10 | 0.80 |
Analyst Conclusions
Management guidance (standalone, pre-scheme)
FID by the end of CY2026, construction from early CY2027, first gold by mid-CY2028. About 143koz a year in years 1–4 at an AISC of about A$2,157/oz. A Mineral Resource update incorporating the 2025–26 drilling is pending. This guidance is now effectively subordinate to the scheme timetable: Scheme Booklet late October 2026, scheme meeting late November 2026, implementation December 2026.
Consensus
No formal consensus forecasts are available (pre-revenue). Broker valuations have converged on the deal terms (Bell Potter A$1.50).
Bull case
-
Strong gold price and positive reconciliation. With spot gold well above the A$4,300/oz base case (A$6,400/oz cited in December 2025, NPV5 A$2.30bn) and in-fill drilling beating model grades more than 80% of the time, intrinsic value may be well above A$776m. Taking OGC scrip keeps holders exposed to that upside.
-
Possible competing bid. KGP is permitted-pathway, land-secured and contractor-ready — rare among WA developers. A acquisitive mid-tier could top OGC's offer before the late-November meeting, subject to the A$7.76m break fee and OGC's matching right.
-
Resource growth. Open-pit extensions, Datatine and Jinkas underground potential, and the Nanicup Bridge satellite could extend mine life well beyond 10.3 years or support a 5Mtpa expansion.
Bear case
-
Scrip and gold-price risk. The consideration is a fixed 0.03365 OGC shares, so a weaker gold price or OGC-specific issues reduce the value received. The cash alternative is capped at A$194m (25%).
-
Scheme failure leaves an unfunded developer. If the deal fails, Ausgold faces a ~A$270m+ funding gap, a delayed FID and permitting still open (EPA/EPBC), plus about A$7.76m of possible break-fee exposure in defined circumstances. The share price would probably fall back toward pre-bid levels (A$0.85–1.07).
-
Execution and cost risk standalone. A low-grade (1.11g/t), 7.0-strip open pit in an inflationary WA cost environment, with private-land compensation still unresolved (Plaint 751289, about 80koz) and a history of schedule slippage.
Key catalysts and monitorables (next 12 months)
| Timing | Catalyst |
|---|---|
| Mid/late Oct 2026 | September 2026 quarterly (cash; confirmation of the A$20m land payment) |
| Late Oct 2026 | Scheme Booklet and Independent Expert's Report (value range vs A$1.36) |
| Oct–Nov 2026 | First court hearing; FIRB and competition clearances; TSX approval |
| Nov 2026 | Village first stage handover; A$20m OGC bridge loan drawdown |
| Late Nov 2026 | Scheme meeting (75% of votes cast and majority by number); cash election deadline five business days earlier |
| Dec 2026 | Second court hearing; implementation; delisting |
| Late 2026 | EPA recommendation and Ministerial approval; EPBC decision; Works Approval |
| H1 2027 | FID (by OGC if acquired); construction start; MRE update |
| Ongoing | Any superior proposal; gold price; OGC share price |
Analyst verdict
Ausgold has done what few junior developers manage: it has turned a long-studied, low-grade, bulk-tonnage deposit in WA farmland into a construction-ready project. Between August 2025 and August 2026 it bought out the land dispute that had constrained the Reserve, raised A$125m, increased the Reserve to 1.33Moz (83% Proved), lifted post-tax NPV5 above A$1bn at a conservative A$4,300/oz, and committed EPC, power and accommodation partners ahead of FID. The board — Roxgold, Resolute/CGA, Newmont/Fortuna and Dundee alumni — ran a classic "de-risk then monetise" playbook.
The OceanaGold scheme crystallises that work at a 28–44% premium, and on our calculations at about A$518 per Reserve ounce and about 0.75x base-case NPV. For a single-asset developer facing a A$270m+ funding gap, permitting that has not yet concluded, and the usual 15–30% cost-overrun risk in WA construction, that price is fair rather than generous. The discount to NPV approximates the dilution and execution risk a standalone build would carry. The scrip-heavy structure is the key nuance: holders swap single-asset execution risk for a diversified four-mine producer, while keeping gold-price exposure, which is attractive if one is bullish on gold.
Our base expectation is that the scheme proceeds. Dundee's 7.7% support, a unanimous board, a credible acquirer and break-fee protection all point that way. The main swing factors are the Independent Expert's valuation range and whether a rival WA mid-tier steps in before the late-November meeting. Absent a superior proposal, AUC is best viewed as merger arbitrage against OGC, with standalone fundamentals as a downside reference near A$0.85–1.07. For long-term holders, the more interesting question shifts to whether OceanaGold delivers KGP on budget, on time, and with the resource growth the 2025–26 drilling suggests.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansExecutive Leadership
Board of Directors
| Name | Role | Appointed | Background | Education | Committees | Shareholding (AR, 20 Aug 2026) |
|---|---|---|---|---|---|---|
John Dorward | Executive Chairman | 16 May 2024 | Former President, CEO and Director of Roxgold Inc. (TSX) — built the Yaramoko underground mine in Burkina Faso and acquired Séguéla from Newcrest; former VP Business Development at Fronteer Gold (sold to Newmont for US$2.3bn); earlier at Leviathan Resources, MPI Mines and Bankwest project finance. Current boards: Roxmore Resources, Surge Copper. Recent former: Contact Gold, Taura Gold, Robex Resources. | BCom (Hons), GradDip Applied Finance & Investment, GradDip Chartered Secretaries, CFA | — | 5,833,233 shares; 833,334 options; 3,568,250 performance rights |
Adrian Goldstone | Non-Executive Director | 16 May 2024 | Managing Director – Technical, Dundee Corporation (substantial shareholder); former EVP Sustainable Development, Dundee Precious Metals; earlier Cyprus Minerals and Amax Gold. Current boards: Saturn Metals, Viva Gold. | MSc (Hons) | Chair Audit; member Risk and Remuneration & Nominations | 1,030,000 shares; 500,000 rights |
Mark Turner | Non-Executive Director | 16 April 2024 | Mining engineer with 35+ years: Newcrest; Resolute (GM Operations for 10 years); COO of CGA Mining (Masbate, Philippines, sold to B2Gold for C$1.1bn); current COO of RTG Mining | BEng Mining (Hons), FAusIMM | Chair Risk; member Audit and Remuneration & Nominations | 808,146 shares; 500,000 rights |
Paul Weedon | Non-Executive Director | 8 November 2024 | SVP Exploration, Fortuna Mining; former Exploration Director (Australia and Ghana) at Newmont — led the team that found the +2Moz Apensu deposit; former AngloGold Ashanti roles | BSc Geology (Hons), MAIG | Chair Remuneration & Nominations; member Audit and Risk | 199,878 shares; 872,354 rights |
Executive Leadership Team
| Name | Role | Since | Background |
|---|---|---|---|
Ben Stockdale | CEO and Co-Company Secretary | CFO from 1 Aug 2024; CEO from 14 May 2026 | 25+ years in resources finance and commercial roles, including debt and equity project financings, M&A, and metals and concentrate marketing |
Mark Mitchell | Chief Operating Officer | 1 Feb 2025 | KMP; prior roles not detailed in the sources reviewed |
Tammie Dixon | Chief Financial Officer | Announced 21 Jul 2026 | Prior roles not detailed in the sources reviewed |
Reece Olney | General Manager Operations | May 2026 | 30+ years; GM Operations at several Mount Gibson Iron mines; most recently GM of Fenix Resources' Weld Range project |
John Sofield | Project Director | 9 Jun 2026 | 25+ years; project delivery roles at South32, SO4 Potash, Covalent Lithium, FMG and BCI Mardie; most recently Commissioning Manager at BP Kwinana |
Sophia Huang | Co-Company Secretary | 9 Oct 2025 | Lawyer and governance professional, Vistra Australia |
Graham Conner | Geology / Competent Person (exploration) | — | MAIG; responsible for exploration data integrity |
Directors' Remuneration
| Name | Cash salary & fees | Annual leave | Other | Long service leave | Superannuation | Options & rights | Total |
|---|---|---|---|---|---|---|---|
J Dorward | 421,000 | 20,496 | 4,833 | 6,377 | 30,000 | 1,275,075 | 1,757,781 |
A Goldstone | 54,911 | 0 | 4,833 | 0 | 6,589 | 157,815 | 224,148 |
M Turner | 58,205 | 0 | 4,833 | 0 | 3,295 | 157,815 | 224,148 |
P Weedon | 54,911 | 0 | 4,833 | 0 | 6,589 | 242,603 | 308,936 |
B Stockdale | 473,646 | 9,780 | 4,834 | 9,511 | 30,000 | 572,537 | 1,100,308 |
M Mitchell | 460,000 | 6,450 | 4,834 | 6,927 | 30,000 | 443,313 | 951,524 |
Total | 1,522,673 | 36,726 | 29,000 | 22,815 | 106,473 | 2,849,158 | 4,566,845 |
Governance Overview
| Item | Assessment |
|---|---|
Board size | 4 (1 executive, 3 non-executive) |
Independence | Three NEDs nominally independent; Goldstone is an executive of Dundee Corporation (~7.7% holder), which on ASX Principles criteria weakens his independence. Effective independent majority is therefore arguable. |
Chair/CEO separation | Roles separated since 14 May 2026 (Stockdale CEO), but the Chair is executive; Dorward was expected to move to a non-executive role toward the end of 2026 (June 2026 quarterly). |
Committees | Audit (Chair: Goldstone), Risk (Chair: Turner), Remuneration & Nominations (Chair: Weedon); Audit & Risk split on 25 March 2026 |
FY2026 attendance | 100% for all directors (6 board meetings) |
Gender diversity | Board 0% female; female executives include CFO Tammie Dixon and Co-Company Secretary Sophia Huang |
Governance statement | 2026 Corporate Governance Statement published 1 September 2026 |
Board & Management Changes
| Date | Change | Context |
|---|---|---|
8 Nov 2024 | MD Matthew Greentree resigns; Paul Weedon joins board | Transition to a development-focused board under Dorward |
1 Feb 2025 | Mark Mitchell appointed COO | Build-out of the development team |
8 Oct 2025 | Company Secretary / Commercial Manager Denis Rakich resigns | Replaced by co-secretaries Stockdale and Huang (9 Oct 2025) |
14 May 2026 | Stockdale becomes CEO; Olney becomes GM Operations | Pre-FID team build |
9 Jun 2026 | John Sofield appointed Project Director | Construction readiness |
21 Jul 2026 | Tammie Dixon appointed CFO | Backfills Stockdale |
Major Shareholders
| Holder | Shares | % of issued capital | Source / date |
|---|---|---|---|
Dundee Corporation (incl. Dundee Resources) | 42,467,969 | ~7.7% | OceanaGold/Ausgold scheme release, 17 Aug 2026 |
Unnamed new substantial holder | — | ≥5% | — |
Directors (aggregate) | ~7.9m | ~1.4% | Mining Technology, 17 Aug 2026; FY2026 Annual Report |
Competitive Landscape
Key Competitors
| Company | Ticker | Category | Relative positioning vs Ausgold (qualitative) |
|---|---|---|---|
OceanaGold | TSX/NYSE: OGC | Acquirer; multi-mine producer | Four operating mines; US$655m cash and US$200m undrawn credit at the time of the deal; pro-forma market cap ~US$6.9bn. Will own KGP if the scheme completes. |
Capricorn Metals | ASX: CMM | WA producer and developer | Analysts (Euroz Hartleys via Resources Rising Stars) compared Ausgold to Capricorn's Karlawinda circa 2020, describing Katanning as larger, higher grade and better served by infrastructure |
Genesis Minerals | ASX: GMD | WA mid-tier producer | Consolidator of WA gold assets; potential competing acquirer |
Ramelius Resources | ASX: RMS | WA mid-tier producer | Acquisitive mid-tier; potential competing acquirer |
Vault Minerals | ASX: VAU | Multi-asset producer | Mid-tier peer |
Westgold Resources | ASX: WGX | WA producer | Mid-tier peer |
Regis Resources | ASX: RRL | Producer (incl. Duketon) | Mid-tier peer |
Northern Star Resources | ASX: NST | Major producer | Potential acquirer of large WA development assets |
Newmont (Boddington) | NYSE: NEM | Major; operates Boddington in the SW Yilgarn | Same craton; underlines the region's endowment |
Saturn Metals | ASX: STN | WA developer (Apollo Hill) | Developer peer; Goldstone also sits on its board |
Ora Banda Mining | ASX: OBM | WA producer | Smaller producer peer |
Bellevue Gold | ASX: BGL | WA producer | Recent WA build case study |
Peer Comparison FY2026
| Metric | Ausgold (AUC) | OceanaGold (OGC) | Peer developer median |
|---|---|---|---|
Revenue growth | n/m | — | n/m |
Margins | n/m | — | n/m |
R&D intensity | Nil (E&E A$23.6m FY2026) | — | n/m |
Reserve | 1.33Moz | — | — |
Pre-production capex | A$354m | — | — |
Balance sheet | A$87.4m cash, no debt (Jun-26) | US$655m cash, US$200m undrawn (Aug-26) | — |
Recent Developments
--