Frontier Energy Limited Overview
Key identifiers
| Item | Detail | Source |
|---|---|---|
| Current legal name | Frontier Energy Limited | FY2025 Annual Report |
| Former names | Superior Lake Resources Limited (2018–2022); Ishine International Resources Limited (to 2018) | Business News company profile; Stockhead |
| ABN | 64 139 522 553 | FY2025 Annual Report |
| Incorporation | 2009, Australia (company limited by shares, incorporated and domiciled in Australia) | FY2025 Annual Report; Simply Wall St |
| Original listing | ASX, December 2009 (as Ishine International Resources) | financialfilings.com listing record |
| Registered office / HQ | Level 20, 140 St Georges Terrace, Perth WA 6000, Australia | FY2025 Annual Report |
| Primary listing | Australian Securities Exchange, code FHE (fully paid ordinary shares) | FY2025 Annual Report |
| Secondary quotation | OTCQB (US), code FRHYF (debuted on OTCQX in August 2022; later announcements reference OTCQB) | Business News; ASX announcements 2023–2026 |
| ISIN | AU0000207912 (per third-party filings index; not confirmed against an issuer document) | financialfilings.com |
| CUSIP | Not publicly disclosed (Australian issuer) | — |
| Fiscal year end | 31 December | FY2025 Annual Report |
| Employees | Not publicly disclosed. Group operates with a small executive team; office space, administration, accounting, corporate and project personnel are supplied by Matador Capital Pty Ltd (a Davey-related party) under shared-services agreements | FY2025 Annual Report, Remuneration Report |
| Employee trend (3-year) | Not publicly disclosed. Employee benefits and consultancy expense was A$1.03m in FY2024 and A$1.11m in FY2025, of which A$1.09m in FY2025 was directors' salaries and consulting fees | FY2025 Annual Report, Note 6 |
| Auditor | Ernst & Young, Perth (lead partner Pierre Dreyer for FY2025); auditor changed in March 2022 at re-admission | FY2025 Annual Report; ASX "Change of auditors" 3 March 2022 |
| Share registry | Automic Group, Sydney | FY2025 Annual Report |
| Website | https://frontierhe.com (legacy superiorlake.com.au no longer the company site) | FY2025 Annual Report |
| Shares on issue | 546,572,215 at 31 December 2025; plus 16,000,000 issued January 2026 and approximately 550,000,000 issued July 2026 under the A$110m raise; derived minimum of approximately 1.11 billion shares at October 2026 | FY2025 Annual Report Note 16; pv-tech via Kalkine |
| Market capitalisation | Approximately A$234m (derived: ~1.11bn shares × A$0.21 share price on 1 September 2026). Third-party data sites show stale figures between A$121m and A$129m that pre-date the July 2026 share issue | Derived; Kalkine 1 September 2026 |
Frontier Energy is a single-asset, pre-revenue renewable-energy developer that has just crossed into construction. Its core asset is the Waroona Renewable Energy Project, about 120km south of Perth, where Stage One combines roughly 132MW of solar (120MWdc in earlier disclosures) with an 81.5MW, 6.9-hour battery, at a capital cost of about A$310m plus A$22m contingency. The project sits within 500 metres of Western Power's 330kV Landwehr Terminal, on one of the least constrained corridors of Western Australia's South West Interconnected System. Revenue visibility comes primarily from 88.06MW of Reserve Capacity credits worth about A$32m a year, plus a Capacity Investment Scheme underwriting that extends a revenue floor to 2042. Funding is a completed A$110m equity raise and up to A$280m of credit-approved debt from Natixis and SMBC. First generation is targeted for 2028. The company's mining heritage — the Superior Lake zinc project in Ontario — was sold in 2026.
Company's own description
The FY2025 Annual Report describes the principal activity as the development of a large-scale integrated renewable energy facility, and states that the Group will continue to pursue a strategy to create a significant vertically integrated renewable energy company in Western Australia. The report presents the Waroona Project as sited on 303 hectares of freehold land, with a further 527 hectares of adjoining freehold controlled by the company, close to the Landwehr Terminal, the Dampier to Bunbury Natural Gas Pipeline, roads, ports and a skilled Peel-region workforce.
Independent characterisation
Frontier is best understood as an infrastructure development company in the final pre-operational phase. It has no operating revenue; its income statement consists of interest, rent, option fees and corporate costs, while nearly all spending on the project is capitalised to "Solar Project in progress" (A$61.6m at 31 December 2025). Its value proposition rests on four elements:
-
Grid access. An executed Electricity Transfer Access Contract with Western Power and proximity to a 330kV terminal — scarce assets in a constrained grid.
-
Contracted capacity revenue. WA's Wholesale Electricity Market (WEM) includes a capacity market. Stage One has been assigned 88.06MW of peak capacity credits at a fixed A$360,700/MW for five years from the 2027–28 capacity year, producing roughly A$32m a year, which the company says is about half of forecast Stage One revenue (FY2025 Annual Report). Crux Investor's September 2026 interview characterises the capacity mechanism as underpinning a much larger share of the revenue base; the two characterisations differ and are noted here as a discrepancy.
-
Government revenue underwriting. Selection under the federal Capacity Investment Scheme (CIS) Tender 6 in May 2026, which management says provides minimum revenue protection to 2042, with 50% upside sharing above a ceiling. The CIS contract was described as imminent but not yet executed in mid-September 2026.
-
Landbank and expansion. About 830 hectares of freehold at Waroona, a fully approved Stage Two (≈130MW solar / 80MW battery), and an option over the Bristol Springs land.
Business and revenue model
| Revenue stream (planned) | Description | Status / magnitude | Source |
|---|---|---|---|
| Reserve Capacity credits | Fixed payments for capacity availability under WA's Reserve Capacity Mechanism | 88.06MW peak credits; A$360,700/MW; ≈A$32m p.a. fixed for five years from 2027–28 | FY2025 Annual Report |
| Energy sales | Wholesale energy sales, especially battery-shifted sales into the 4pm–10pm peak | Aurora-modelled ≈A$40.5m p.a. average over first five years | Crux Investor, 17 September 2026 |
| Large-scale Generation Certificates (LGCs) and balancing | Environmental certificates and balancing-market payments | ≈A$4m p.a. modelled (carbon credits and balancing) | Crux Investor |
| Essential system services | Frequency Co-optimised Essential System Services (FCESS) | Not quantified | FY2025 Annual Report |
| CIS underwriting | Revenue floor and ceiling with the Commonwealth to 2042 | Selected May 2026; contract terms confidential | Kalkine; Crux Investor |
The model is entirely a merchant-plus-capacity utility model. There are no product, subscription or licensing revenues. The company is not vertically integrated into retail; customers are the WEM (via AEMO settlement) and, prospectively, bilateral offtakers such as data-centre operators.
Value chain position and end-markets
Frontier sits in the generation and storage segment of the electricity value chain. It owns the land and project, procures equipment directly from tier-one manufacturers (LONGi, Trina Solar, SMA, Nextracker), "free-issues" that equipment to its EPC contractor Monford, and relies on Western Power for transmission connection. Its end-market is the SWIS, which serves about 1.2 million customers (FY2025 Annual Report). Customer types are the market operator (capacity and energy settlement), potential corporate PPA counterparties, and the Commonwealth (CIS).
Strategy
Stated strategy
The FY2025 Annual Report states the Group's intent to create a "significant vertically integrated renewable energy company in Western Australia." In practice, the strategy has three layers: (1) build and commission Stage One on time and budget; (2) monetise the landbank and grid capacity through Stage Two and later stages; and (3) diversify offtake toward long-term contracts, including data-centre demand.
Strategic initiatives in the last 24 months
| Initiative | Timing | Detail | Source |
|---|---|---|---|
| Updated Stage One DFS | December 2024 / January 2025 | Lower capex, updated price forecasts; battery extended to 6.9 hours | FY2025 Annual Report |
| Strategic partnering process | H1 2025 | Multiple non-binding indicative offers received; process ultimately superseded by direct equity/debt funding | FY2025 Annual Report |
| Early works EPC contract | H1 2025 | Monford Group: design, surveys, geotechnical and drainage work | FY2025 Annual Report |
| Fixed-price capacity credit strategy | July–October 2025 | Applied as a fixed-price facility; 88.06MW assigned | FY2025 Annual Report |
| CIS strategy | March 2025 – May 2026 | Withdrew from Tender 2 to apply under Tender 6; selected May 2026 | FY2025 Annual Report; Kalkine |
| Free-issue procurement model | 2025–2026 | Direct purchase from LONGi, Trina, SMA, Nextracker; free-issued to Monford | Crux Investor |
| Board renewal | February 2026 | Executive Chairman with project-finance track record | ASX 24 February 2026 |
| Non-core divestment | Q2 2026 | Pick Lake/Superior Lake sold for ~A$2.25m | June 2026 Quarterly |
| Stage Two grid process | October 2026 | Ready to Progress status under Western Power Critical Projects Framework | Discovery Alert |
| Data-centre offtake exploration | 2,026 | Discussions with data-centre operators; substation sized with headroom to roughly triple capacity | Crux Investor |
ESG commitments
The company's sustainability report emphasises heritage protection (Noongar Standard Heritage Agreement with Gnaala Karla Booja Aboriginal Corporation), local procurement and employment commitments made in its CIS Tender 6 application, and BESS fire-safety design. No quantified emissions targets for the company itself are disclosed.
Medium-term targets and guidance
| Item | Target | Source |
|---|---|---|
| Financial close (debt) | October–November 2026 | Crux Investor |
| First debt drawdown | Q1 2027 | Crux Investor |
| Cold commissioning | Late 2027 | Crux Investor |
| First revenue | 2,028 | Crux Investor; Kalkine |
| Average annual revenue, first five years | ~A$72.5m (Aurora model) | Crux Investor |
| Average annual EBITDA, first five years | ~A$62.5m (86% margin) | Crux Investor |
| Post-tax project IRR | ~20%; payback ~6 years | Crux Investor |
| Average free cash flow after debt service and tax, first five years | ~A$35m p.a. | Crux Investor |
| Earlier guidance (August 2024) | Stage One EBITDA A$68m p.a. first five years; capex A$304m; equity IRR 22% | Quartr summary of 2024 presentation |
Products & Services
Frontier has no commercial products. Its "portfolio" consists of development projects. Each is catalogued below.
Renewable energy segment
| Attribute | Detail | Source |
|---|---|---|
| Location | Shire of Waroona, ~120km south of Perth, 8km from Waroona town | FY2025 Annual Report |
| Land | 303ha freehold (Stage One area) within ~830ha total controlled | FY2025 Annual Report; Crux Investor |
| Solar | 132MW (2026 releases); 120MWdc in FY2025 Annual Report (likely AC/DC or design change — not reconciled) | Kalkine; FY2025 Annual Report |
| Battery | 81.5MW, ~6.9-hour duration (≈560MWh, derived); earlier design was 80MW/360MWh four-hour | FY2025 Annual Report; pv magazine 2024 |
| Capex | ~A$310m plus A$22m contingency (2026); A$304m in February 2024 DFS | Crux Investor; pv magazine |
| Equipment | LONGi Solar (~200,000 panels, 30-year warranty); Trina Solar (156 BESS containers, 20-year warranty); SMA (26 power conversion units); Nextracker (1,885 trackers) | Crux Investor |
| EPC | Monford Group, fixed price, free-issue model | Crux Investor; June 2026 Quarterly |
| Substation | Global Power Solutions | Crux Investor |
| Grid connection | Western Power; underground 330kV cable to Landwehr Terminal (procurement and design cost A$5.4m as of mid-2025) | Crux Investor; June 2025 quarterly |
| Generation | ~258GWh in year one (2024 DFS) | 2024 half-year report |
| Capacity credits | 88.06MW peak and 81.5MW flexible credits for 2027–28; A$360,700/MW | FY2025 Annual Report |
| Revenue support | CIS Tender 6 selection, revenue floor to 2042 | June 2026 Quarterly |
| Timeline | Mobilisation September 2026; piling December 2026; panels January 2027; cold commissioning late 2027; first revenue 2028 | Crux Investor; Discovery Alert |
| Pricing model | Capacity payments plus wholesale energy, LGCs, FCESS | FY2025 Annual Report |
Waroona Renewable Energy Project — Stage One (flagship)
Waroona Stage Two
Approximately 130MW solar and 80MW battery, with development approval and environmental assessment complete. Western Power deemed the connection application "Ready to Progress" under its Critical Projects Framework on 15 October 2026. Frontier says Stage One's substation and cable to Landwehr (over A$30m combined) can be reused, reducing cost and time. Stage Two still requires its own revenue-certainty mechanism (capacity credits, CIS or PPA). Sources: Discovery Alert; Crux Investor.
Longer-range Waroona staging (as described by third-party summary of company materials)
A four-stage concept totalling up to 1GW of solar and 660MW of storage by 2031: Stage Three (200MWdc solar / 140MW BESS) and Stage Four (560MWdc solar / 300–360MW BESS). Source: roic.ai company description; not confirmed in the FY2025 Annual Report.
Bristol Springs Project
A utility-scale renewable project adjacent to Waroona — originally the 114MWdc Bristol Springs Solar project acquired in 2022. Frontier holds a five-year sole option to buy the land for a fixed A$5.0m; option fees of A$3.04m had been paid by FY2025, with a further A$1.5m paid in January 2026. Biodiversity surveys over 525ha were completed in 2025. Source: FY2025 Annual Report Notes 12 and subsequent events.
Peaking Plant Project (dormant)
A A$0.65m carrying value for a "Peaking Plant Project in progress" remains on the balance sheet, a legacy of Waroona Energy's proposed 120MW dual-fuel (hydrogen-capable) peaking plant. No expenditure was capitalised in FY2025. Source: FY2025 Annual Report Note 12; power-technology.com.
Green hydrogen / hydrogen refuelling (discontinued)
Plans for a 36.6MW alkaline electrolyser and a hydrogen refuelling station (2022–2023) were abandoned when strategy shifted in December 2023. The hydrogen project-in-progress was fully impaired in FY2024. Source: FY2025 Annual Report Notes 12 and LTI table; FY2022 Annual Report.
Mineral exploration segment (divested)
Superior Lake Zinc and Copper Project, Ontario, Canada — ~200km east of Thunder Bay, comprising Pick Lake and Winston Lake deposits over ~175km². The 2019 BFS outlined a 325,000tpa operation producing ~38,000t zinc a year. An option to Panther Metals (June 2025, A$2.75m) lapsed in October 2025; the asset was fully impaired at FY2025 and sold in Q2 2026 for about A$2.25m. Sources: Mining.com; FY2025 Annual Report; June 2026 Quarterly.
Financial Narrative
All figures A$ millions unless stated, years ending 31 December. Revenue from ordinary activities was nil throughout, so margin-based metrics are not meaningful.
Income statement
Sources: FY2025 Annual Report (income statement and Remuneration Report five-year table); Appendix 4E FY2023.
H1 2026 interim: Net income of A$75,896 for the half-year to 30 June 2026, including A$2.27m net profit from discontinued operations (Superior Lake sale), implying a continuing-operations loss of about A$2.19m (derived). Basic EPS 0.01 cents. Net tangible assets per share 17.4 cents (15.8 cents at the prior comparative). Source: Appendix 4D H1 2026; Quartr.
EBITDA: Not reported by the company. A derived FY2025 EBITDA before impairment and share-based payments would be roughly -A$2.05m (net loss -5.168, add back impairment 1.355, share-based payments 1.745, depreciation/amortisation 0.016, finance costs 0.011), but this is an analytical construct, not a company figure.
Revenue CAGR: Not meaningful (nil revenue).
Balance sheet
Sources: FY2025 Annual Report (balance sheet, Notes 12–16, statement of changes in equity for 1 January 2024 opening balances); Appendix 4E FY2023 (NTA per share). Working capital and net debt derived.
30 June 2026 interim: Cash A$7.97m; total assets A$96.59m. Source: H1 2026 report summary (Quartr). These pre-date settlement of most of the A$110m equity raise (settled around 15–21 July 2026).
Note: FY2025 trade and other payables of A$5.58m include a A$4.0m advance from Grant Davey for his share placement (subsequently converted to equity in January 2026), which inflates liabilities and depresses working capital at year-end.
Cash flow
Source: FY2025 Annual Report, cash flow statement.
Ratios
ROIC, net debt/EBITDA, interest coverage and cash conversion cycle are not meaningful for a pre-revenue company with negative EBITDA and no operating working-capital cycle.
Commentary on trends and drivers
FY2021–FY2022 (restructuring and relisting). Losses of A$2.6m and A$5.3m reflected the shell-like transition after the Superior Lake sale and the costs of re-admission, Bristol Springs acquisition and hydrogen studies. The company was suspended for the first two months of 2022.
FY2023 (accounting gain). The reported profit stems from the deconsolidation and re-acquisition accounting for Waroona Energy. Operationally, the year established the current asset base: the Waroona merger lifted equity to A$83.4m by year-end and delivered the second grid connection and the Waroona land.
FY2024 (impairment year). The A$18.1m loss was dominated by the A$14.9m Superior Lake write-down plus A$0.38m impairment of the hydrogen project. Cash rose to A$14.3m due to the A$16.75m Tranche 1 placement. The Tranche 2 placement of approximately A$23.2m, which required shareholder approval, does not appear in the FY2024 share register reconciliation, indicating it did not proceed (the register shows only the 3 September 2024 issue of 67.0m shares). The most likely reason is that capacity credits were not allocated in the 2024 cycle, which undermined the Infradebt financing; the company has not been found to state this link explicitly in the material reviewed.
FY2025 (capital-light holding pattern, then pivot to funding). The loss narrowed to A$5.2m. Spending shifted to capitalised development (A$8.8m added to Solar Project in progress) and a A$7.9m refundable Reserve Capacity Security. Cash fell to A$5.6m. Liquidity was bridged with two short-term facilities (an A$8m secured loan from Rockford Equity costing A$0.57m in charges, and an A$6m loan from a Davey entity), both repaid in December 2025, and an A$11.5m placement. Share-based payments more than quadrupled to A$1.75m as equity incentives were reset.
2026 (inflection). The A$110m equity raise and A$280m credit-approved debt transform the balance sheet. After financial close (targeted October–November 2026) and first drawdown (Q1 2027), the company will carry substantial project debt geared at about 65%, with an 18-year notional amortisation, changing the risk profile from equity-funded developer to leveraged infrastructure owner.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansFinancial Detail
Segment revenue (AUD Mn)
| Segment revenue (AUD Mn) | FY2023 | FY2024 | FY2025 |
|---|---|---|---|
Renewable energy revenue (AUD Mn) | 0 | 0 | 0 |
Mineral exploration revenue (AUD Mn) | 0 | 0 | 0 |
Total revenue from ordinary activities (AUD Mn) | 0 | 0 | 0 |
Results by Segment and Segment Assets & Liabilities
| Segment metric (AUD Mn) | FY2024 | FY2025 |
|---|---|---|
Renewable energy operating loss (AUD Mn) | -3.349 | -2.691 |
Renewable energy impairment (AUD Mn) | -0.381 | 0 |
Mineral exploration operating result (AUD Mn) | 0.506 | 0.212 |
Mineral exploration impairment (AUD Mn) | -14.899 | -1.355 |
Corporate operating loss (AUD Mn) | — | -1.334 |
Group net loss before tax (AUD Mn) | -18.123 | -5.168 |
Renewable energy total assets (AUD Mn) | 81.798 | 90.266 |
Mineral exploration total assets (AUD Mn) | 1.610 | 0.004 |
Corporate total assets (AUD Mn) | — | 0.164 |
Renewable energy total liabilities (AUD Mn) | 1.839 | 5.428 |
Mineral exploration total liabilities (AUD Mn) | 0.297 | 0.004 |
Corporate total liabilities (AUD Mn) | — | 0.207 |
Group Entities
| Entity | Jurisdiction | Role | Source |
|---|---|---|---|
Frontier Energy Limited | Australia | Listed parent, head of tax-consolidated group | FY2025 Annual Report |
Bristol Springs Solar Pty Ltd | Australia | Bristol Springs project / land option | FY2025 Annual Report Note 2(k) |
Superior Mining Pty Ltd | Australia | Legacy holding company from Superior Lake era | FY2025 Annual Report Note 2(k) |
Superior Energy Pty Ltd | Australia | Wholly owned subsidiary (function not described) | FY2025 Annual Report Note 2(k) |
Waroona Energy Inc. (WHE) | British Columbia, Canada (functional currency C$) | Former TSX-V company; holds Waroona project interests | FY2025 Annual Report Note 2(d) |
Pick Lake Mining Limited (PLM) | Nova Scotia, Canada | Held Superior Lake Zinc Project; project sold 2026 | FY2025 Annual Report; CROPS release |
Income Statement and Per-Share Data
| Metric | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|---|
Revenue from ordinary activities (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Other income (AUD Mn) | — | — | — | 0.797 | 0.667 |
Corporate expenses (AUD Mn) | — | — | — | 1.948 | 1.593 |
Employee benefits and consultancy (AUD Mn) | — | — | — | 1.032 | 1.110 |
Share-based payments expense (AUD Mn) | — | — | — | 0.396 | 1.745 |
Impairment expense (AUD Mn) | — | — | — | 15.280 | 1.355 |
Net profit/(loss) before tax (AUD Mn) | — | — | — | -18.123 | -5.168 |
Net profit/(loss) attributable to owners, per five-year table (AUD Mn) | -2.591 | -5.343 | 2.760 | -17.994 | -5.207 |
Basic EPS (A$ cents) | -1.51 | -2.13 | 0.68 | -3.87 | -1.00 |
Diluted EPS (A$ cents) | — | — | — | -3.87 | -1.00 |
Dividends per share (A$ cents) | 0 | 0 | 0 | 0 | 0 |
Balance Sheet and Per-Share Data
| Metric | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|
Total assets (AUD Mn) | — | — | 83.408 | 90.435 |
Cash at banks (AUD Mn) | — | 11.574 | 14.335 | 5.588 |
Property plant and equipment incl. projects (AUD Mn) | — | — | 66.120 | 76.468 |
Solar project in progress (AUD Mn) | — | — | 52.793 | 61.568 |
Land incl. option fees (AUD Mn) | — | — | 12.671 | 14.245 |
Exploration and evaluation assets (AUD Mn) | — | 16.103 | 1.367 | 0 |
Other financial assets incl. reserve capacity security (AUD Mn) | — | — | 0.079 | 8.015 |
Goodwill and intangibles (AUD Mn) | — | — | 0 | 0 |
Short-term debt (AUD Mn) | — | — | 0.058 | 0 |
Long-term debt (AUD Mn) | — | — | 0 | 0 |
Net debt (AUD Mn, negative = net cash) | — | — | -14.277 | -5.588 |
Total liabilities (AUD Mn) | — | — | 2.136 | 5.639 |
Total equity (AUD Mn) | — | 83.441 | 81.272 | 84.796 |
Working capital (AUD Mn) | — | — | 13.690 | 0.313 |
Net tangible assets per share (A$ cents) | 9.09 | 18.71 | — | — |
Cash Flow
| Metric | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|---|
Net operating cash flow (AUD Mn) | — | — | — | -2.766 | -2.212 |
Purchases of PP&E / capex (AUD Mn) | — | — | — | -10.372 | -9.769 |
Free cash flow (AUD Mn, OCF less capex, derived) | — | — | — | -13.138 | -11.981 |
Reserve capacity security deposit paid (AUD Mn) | — | — | — | 0 | -7.941 |
Net investing cash flow (AUD Mn) | — | — | — | -10.072 | -17.491 |
Proceeds from share issues (AUD Mn) | — | — | — | 16.754 | 7.500 |
Loan proceeds (AUD Mn) | — | — | — | 5.221 | 14.000 |
Loan repayments (AUD Mn) | — | — | — | -5.164 | -14.058 |
Net financing cash flow (AUD Mn) | — | — | — | 15.588 | 10.951 |
Dividends paid (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Share buybacks (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Returns & Leverage Ratios (%) and Financial Ratios (x)
| Ratio | FY2024 | FY2025 |
|---|---|---|
Return on equity (%, net loss / average equity, derived) | -22.0 | -6.2 |
Return on assets (%, net loss / average assets, derived) | — | -5.9 |
Current ratio (x, derived) | 7.41 | 1.06 |
Debt to equity (x) | 0.00 | 0.00 |
Asset turnover (x) | 0 | 0 |
Region revenue (AUD Mn)
| Region revenue (AUD Mn) | FY2023 | FY2024 | FY2025 |
|---|---|---|---|
Australia revenue (AUD Mn) | 0 | 0 | 0 |
Canada revenue (AUD Mn) | 0 | 0 | 0 |
Region total assets (AUD Mn)
| Region total assets (AUD Mn) | FY2024 | FY2025 |
|---|---|---|
Australia: renewable energy and corporate (AUD Mn) | 81.798 | 90.430 |
Canada: mineral exploration (AUD Mn) | 1.610 | 0.004 |
Share Price
| Metric | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|
Year-end share price (AUD) | 0.450 | 0.365 | 0.120 | 0.240 |
Capital Markets
| Measure | Value | Source |
|---|---|---|
Recent price | A$0.21 (1 September 2026); A$0.20–0.22 range in August–September 2026 | Kalkine |
52-week range | A$0.18 – A$0.37 | stocklight.com |
Equity raise price | A$0.20 (June 2026) | pv-tech via Kalkine |
1-year performance | Not reliably determinable from available data; TradingView showed +7.3% over an undated trailing year | TradingView |
3-year performance | Approximately -42% from A$0.365 (end-2023) to A$0.21 (derived) | Derived |
5-year performance | Not meaningful (suspension through early 2022); +62% from the A$0.13 re-admission raise price (derived) | Derived |
Beta | 0.41 (third-party) | TradingView |
All-time high | A$10.675 (August 2010, Ishine era, adjusted basis per provider) | TradingView |
Valuation Snapshot
| Multiple | Value | Basis |
|---|---|---|
P/B | ~1.2x (derived: A$0.21 / 17.4c NTA per share at 30 June 2026, pre-raise basis) | Appendix 4D H1 2026 |
Market cap / forecast Stage One EBITDA | ~3.7x (derived: ~A$234m / A$62.5m modelled average EBITDA; excludes project debt and pre-revenue time value) | Crux Investor; derived |
Capital Markets — Moody's
| Item | Status |
|---|---|
Moody's | Not rated |
S&P | Not rated |
Fitch | Not rated |
Prospective project debt | Up to A$280m (A$250m construction/term; A$13m bank guarantee; A$17m DSRF); ~65% gearing; 18-year notional amortisation; financial close targeted October–November 2026; first drawdown Q1 2027 |
Share Price & Returns
| Date | Event | Shares (M) | Price (AUD) | Gross proceeds (AUD Mn) | Source |
|---|---|---|---|---|---|
March 2022 | Re-admission raise | 61.5 | 0.13 | 8.0 | SmallCaps |
December 2023 | Waroona acquisition (scrip) | — | — | — | Stockwatch |
September 2024 | Tranche 1 placement | 67.0 | 0.25 | 16.75 | FY2025 Annual Report |
December 2025 | Placement Tranche 1 | 30.0 | 0.25 | 7.5 | FY2025 Annual Report |
January 2026 | Director placement | 16.0 | 0.25 | 4.0 | FY2025 Annual Report |
July 2026 | Major equity raise | 550.0 | 0.20 | 110.0 | Kalkine |
Analyst Conclusions
Management guidance
Management guides to financial close in October–November 2026, first debt drawdown in Q1 2027, panel deliveries from January 2027, cold commissioning in late 2027 and first revenue in 2028. Lender-commissioned Aurora modelling points to average Stage One revenue of ~A$72.5m and EBITDA of ~A$62.5m a year over the first five years, a ~20% post-tax IRR and ~A$35m a year of free cash flow after debt service and tax. Stage Two is being progressed through the Western Power connection process, contingent on securing its own revenue mechanism.
Consensus
No published consensus earnings forecasts are available. Third-party price targets of A$0.34–0.39 imply 60–85% upside from A$0.21 (derived), but the number and identity of contributing analysts is not disclosed.
Bull case
-
Revenue visibility is unusually strong for a developer. Fixed capacity payments of ~A$32m a year from 2027–28 plus a CIS floor to 2042 underpin bankability, as demonstrated by the Natixis/SMBC credit approval.
-
Cost risk is largely capped. With fixed-price, free-issue equipment and EPC contracts signed before financial close and a A$22m contingency, the classic capex overrun risk is materially reduced.
-
Expansion is cheap and approved. Stage Two reuses more than A$30m of connection infrastructure, already has development approval and has priority grid status; a second stage of similar size could roughly double the asset base at lower incremental cost.
Bear case
-
Execution and timeline slippage. Commercial operation targets have moved from 2H 2026 (2024 guidance) to October 2027 (2025) to 2028 revenue (2026). Capacity obligations for 2027–28 and the A$7.94m security create a hard performance test.
-
Merchant revenue compression. Battery saturation already cut average peak prices by about 21% in 2025; nearly half of modelled revenue is energy sales exposed to this trend, and capacity pricing steps down after five years.
-
Governance and dilution. Heavy reliance on a dominant shareholder's related entities, an executive chair, minimal committee structures and a doubling of the share count at a discounted price may cap the valuation multiple investors are willing to pay.
Key catalysts and monitorables (next 12 months)
| Catalyst | Expected timing | What to watch |
|---|---|---|
| Debt financial close | October–November 2026 | Final terms vs credit-approved package; syndication |
| CIS contract execution | Near term (pending September 2026) | Floor and ceiling levels, if disclosed |
| First tracker deliveries | November 2026 | Supply-chain execution |
| Solar piling start | December 2026 | Construction progress |
| First panel deliveries | January 2027 | Logistics |
| First debt drawdown | Q1 2027 | Conditions precedent satisfied |
| FY2026 Annual Report | ~February 2027 | Capitalised costs vs budget; contingency usage |
| Stage Two access offer and revenue mechanism | 2,027 | Capacity credits, CIS round or PPA (possibly data-centre) |
| Western Power connection works | Ongoing | Critical path to energisation |
| WA capacity price for subsequent years | Annual AEMO cycle | Market tightness signal |
Concluding analyst verdict
Frontier Energy is no longer the company named in the request. Superior Lake Resources, a high-grade zinc story that could not fund its Ontario mine, has become a Western Australian solar-and-storage developer, and as of October 2026 it has finally moved from studies to construction. The decisive developments came in rapid succession during 2025–2026: a capacity credit allocation at a sharply higher price, selection under the Capacity Investment Scheme, an A$110m equity raise, up to A$280m of credit-approved bank debt from two global lenders, fixed-price contracts for the main equipment and EPC scope, and mobilisation to site. That sequence resolves the funding risk that defined the company's prior history of bridge loans, related-party advances and abandoned financing routes.
The investment question has therefore shifted from "will it be built?" to "will it be built on time, and how much will the merchant tail be worth?" The fixed-price structure and contingency give reasonable comfort on cost, but the company has a record of timetable slippage and has never built an asset. Revenue quality is good for the first five years, yet battery proliferation in the SWIS is already compressing the peak spreads on which nearly half of modelled revenue depends.
On the numbers available, the equity trades at roughly 1.2x book and under 4x modelled average Stage One EBITDA before accounting for project debt and the two-year wait. That gap reflects genuine execution, dilution and governance discounts rather than obvious mispricing, but it leaves room for re-rating if construction proceeds to plan and Stage Two secures revenue support. The stock is best viewed as a construction-phase infrastructure option on Western Australia's coal exit. Financial close and the first construction milestones over the next six months are the critical tests.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansExecutive Leadership
Board of Directors
| Name | Role | Appointed | Background | Source |
|---|---|---|---|---|
Jamie Cullen | Executive Chairman | 2 March 2026 | CEO of Pacific Energy for a decade, growing it to ~1GW of contracted remote power; led its 2019 sale to QIC (EV A$535m) and a A$2bn refinancing in 2025; former MD of Resource Equipment Ltd and PCH Group; chartered accountant, BCom | ASX announcement 24 February 2026 |
Guy Chalkley | Non-Executive Director (Chairman 17 February 2025 – 2 March 2026) | 17 February 2025 | CEO of Endeavour Energy (NSW distribution); former CEO and CFO of Western Power; FCCA, MAICD; board member, Energy Networks Australia | FY2025 Annual Report |
Grant Davey | Non-Executive Director (Executive Director 2025–2026; Executive Chairman 2022–2025) | 27 February 2018 | ~30 years in mining development and operations; involved in Panda Hill niobium, Cape Ray gold and acquisition of Kayelekera uranium mine from Paladin; former director of Lotus Resources and Waroona Energy; director of Earth's Energy | FY2025 Annual Report |
Dixie Marshall | Non-Executive Director | 1 December 2021 | ~40 years in strategic communications and government relations; six years as Director of Strategic Communications in the WA Premier's Office; Chair of GRA Partners; Deputy Chair, WA Football Commission | FY2025 Annual Report |
Amanda Reid | Non-Executive Director; Chair of Sustainability Committee | 8 August 2022 | Government relations and corporate communications; former Partner at GRA Partners; former senior adviser to WA governments | FY2025 Annual Report |
Executive Leadership Team
| Name | Role | Tenure | Background | Source |
|---|---|---|---|---|
Adam Kiley | Chief Executive Officer | Since 19 December 2023 | ~20 years in resources and energy, equity capital markets and debt advisory; former MD and CEO of Waroona Energy Inc. | FY2025 Annual Report |
Chris Bath | Chief Financial Officer (Executive Director until 2 March 2026) | Director from 1 December 2021 | Chartered accountant, 25+ years in energy and resources in Australia and South-East Asia; director of Equus Energy | FY2025 Annual Report; ASX 24 February 2026 |
Warren King | Chief Operating Officer | Since 19 December 2023 | Background not detailed in reviewed sources | FY2025 Annual Report |
Stuart McKenzie | Company Secretary | Since 18 March 2024 | 30+ years in commercial roles; company secretary for Anvil Mining, Lotus Resources, Ok Tedi Mining and others; former EY and HSBC; LLB, BEc | FY2025 Annual Report |
Directors' Remuneration
| Name | Salary and fees | Annual leave | Superannuation | Share-based payments | Non-cash | Total | % performance related |
|---|---|---|---|---|---|---|---|
Guy Chalkley | 113,082 | 0 | 13,328 | 149,815 | 0 | 276,225 | 0 |
Grant Davey | 270,000 | 0 | 0 | 356,727 | 0 | 626,727 | 57 |
Chris Bath | 180,000 | 0 | 0 | 226,612 | 3,541 | 410,153 | 55 |
Dixie Marshall | 67,114 | 0 | 7,886 | 0 | 0 | 75,000 | 0 |
Amanda Reid | 67,114 | 0 | 7,886 | 0 | 0 | 75,000 | 0 |
Adam Kiley | 320,000 | 41,846 | 37,600 | 310,478 | 4,773 | 714,697 | 43 |
Warren King | 223,500 | 0 | 0 | 280,133 | 0 | 503,633 | 56 |
Total | 1,240,810 | 41,846 | 66,700 | 1,323,765 | 8,314 | 2,681,435 | — |
Board & Management Changes
| Date | Change | Context |
|---|---|---|
19 December 2023 | Kiley appointed CEO, King COO | Post-Waroona merger integration |
18 March 2024 | McKenzie appointed Company Secretary | — |
19 August 2024 | Mark McGowan AC announced as incoming Chairman | Profile-raising appointment |
3 December 2024 | McGowan appointment cancelled | No start date could be agreed |
17 February 2025 | Chalkley Chairman; Davey to Executive Director | Adding utility-sector expertise |
2 March 2026 | Cullen Executive Chairman; Chalkley and Davey to NED; Bath leaves board, remains CFO | Transition to financing and construction |
Major Shareholders
| Holder | Interest | Date / basis | Source |
|---|---|---|---|
Grant Davey (indirect) | 69,104,214 shares and 12,117,575 options | At date of FY2025 Annual Report (February 2026) | FY2025 Annual Report |
Grant Davey | ~6.3% of issued capital (pre-July 2026 raise) | Director interest notices, 2026 | stocklight.com |
Adam Kiley | 10,376,487 shares | 31 December 2025 | FY2025 Annual Report |
Chris Bath (indirect) | 3,977,735 shares and 2,769,475 options | February 2026 | FY2025 Annual Report |
Jamie Cullen | On-market purchases including A$215,000 and A$81,446 tranches; ~0.11% | 2026 | stocklight.com |
Institutional investors (aggregate) | Rose from ~10% to ~30% of register after the A$110m raise | September 2026 | Crux Investor |
An unnamed substantial holder | Ceased to be substantial | 21 January 2026 | InvestSMART announcement list |
Competitive Landscape
Key Competitors
| Competitor / comparator | Category | Relevance to Frontier | Comparative revenue | Positioning vs Frontier |
|---|---|---|---|---|
Synergy (WA Government-owned) | Incumbent generator-retailer | Dominant SWIS generator and retailer; building large state-owned batteries; managing coal exit by 2029 | Not compiled | Vastly larger; also a potential offtaker |
Alinta Energy | Private generator-retailer | Major WA gas and renewables generator | Not compiled | Larger, integrated; competes for capacity credits |
Neoen | Global IPP | Developer of large WA batteries (Collie) | Not compiled | Larger, global balance sheet |
Cunderdin solar/BESS project owner | IPP | Only new renewable generation facility added to SWIS in 2025 (128MW solar, 55MW 4-hour BESS) | Not compiled | Closest physical analogue to Waroona Stage One |
Pacific Energy (QIC-owned) | Remote/off-grid power | Cullen's former company; WA energy specialist | Not compiled | Different market (remote) but competes for talent and capital |
Standalone battery developers in the SWIS (various) | Storage IPPs | Rapid battery additions depressed 2025 peak prices from A$152 to A$120/MWh | Not compiled | Direct competitors for peak-period arbitrage revenue |
Gas peakers (various owners) | Thermal | Supply ~29% of SWIS electricity in 2025 | Not compiled | Compete for capacity credits |
AGL Energy / Origin Energy | ASX-listed gentailers | East-coast focused; valuation reference for ASX energy | Not compiled | Not direct SWIS competitors |
Genex Power (acquired by J-Power, 2024) | Former ASX renewable developer | Valuation reference for listed developers | Not compiled | Precedent for take-private of ASX developers |
Other CIS Tender 6 WA winners (not named in sources) | Developers | Compete for same policy support pool | Not compiled | Similar stage |
Peer Comparison FY2025
| Attribute | Frontier Energy | Typical incumbent gentailer | Typical global IPP in WA |
|---|---|---|---|
Revenue (latest FY) | Nil (FY2025) | Not compiled | Not compiled |
Revenue growth | Not meaningful | Not compiled | Not compiled |
Forecast EBITDA margin | ~86% at Stage One (Aurora model) | Not compiled | Not compiled |
R&D intensity | Nil disclosed | Not compiled | Not compiled |
Assets in operation in SWIS | None (first in 2028) | Multiple GW | Hundreds of MW |
Balance sheet | ~A$110m equity raised; A$280m project debt pending financial close | Investment grade or state-backed | Global corporate balance sheets |