Horizon Gold Limited Overview
Horizon Gold is a Perth-based, single-asset gold developer. Its sole asset is the 100%-owned Gum Creek Gold Project in the Mid-West/Murchison region of Western Australia, a brownfields camp that produced more than 1.1Moz of gold before closing in 2005, when the gold price was about A$560/oz. Horizon was spun out of Panoramic Resources in 2016 and has been controlled by Zeta Resources since 2020. Over the past five years it has grown the Mineral Resource from 1.36Moz to 2.30Moz (37.97Mt at 1.89g/t). In July 2026 it completed a Definitive Feasibility Study for a 2.4Mtpa open-pit, free-milling operation producing 880koz over ten years. The study shows a pre-tax NPV5 of A$1.31B, a pre-tax IRR of 53.1% and pre-production capex of A$350M at A$5,500/oz. With A$24M cash, no debt and a Final Investment Decision targeted for Q2 2027, Horizon is moving from explorer to developer. The company trades at a deep discount to its study NPV, reflecting financing, permitting and free-float constraints.
Company's own description
The company describes itself as an exploration company focused on exploration and development activities at its 100%-owned Gum Creek Gold Project in the Mid-West Region of Western Australia (company profile, as carried on Market Index and ASX filings). Following the July 2026 DFS, management now presents the business as an execution-ready gold developer with a defined pathway to production (FY2026 results materials, 22 Sep 2026).
Independent characterisation
Horizon is a pre-revenue, single-asset, single-commodity (gold) developer with a secondary base-metal option (the Altair zinc-copper-silver VMS deposit). It does not sell products or services. Its value lies in:
-
In-ground resources: 2.30Moz Au, of which about 63% was Indicated as of the 2023/2025 estimates.
-
A maiden Probable Ore Reserve: 728koz.
-
A DFS-defined development project: NPV and IRR as above.
-
Exploration upside: a large, contiguous landholding covering most of the Gum Creek greenstone belt, described as about 620km² in 2021 and as an 80km belt in 2026 presentations.
Business model and revenue model
| Element | Current state (FY2026) | Planned state (post-FID) |
|---|---|---|
| Revenue model | No operating revenue. FY2026 income of A$513k was mainly interest | Sale of gold doré to a refiner (e.g. the Perth Mint or similar), spot-linked, possibly with a hedge book required by lenders |
| Product / service / subscription / licensing mix | 0% / 0% / 0% / 0% (pre-revenue) | ~100% commodity product sales (gold); possible base-metal by-product only if Altair is developed (not in DFS) |
| Value-chain position | Upstream exploration and project development | Upstream mine owner-operator (owner-miner or contract mining, to be decided at FID), with an on-site 2.4Mtpa CIL/CIP-type processing plant |
| Customer types | — | Refiners and bullion buyers |
| End-markets | — | Global gold market (investment, central bank, jewellery and industrial demand), priced in US$ and converted to A$ |
| Funding model | Equity (placements and entitlement offers), historically supported by Zeta; short-term Zeta loan facility in FY2025 | Debt plus equity project finance (Orimco appointed adviser, Jul 2026); toll treatment or a JV identified as lower-capex early-production alternatives outside the DFS |
Asset summary — Gum Creek Gold Project
| Attribute | Detail | Source |
|---|---|---|
| Location | Mid-West/Murchison region, WA; about 640km NE of Perth; near Sandstone, about 100km SE of Meekatharra | Kalkine; The West Australian / Bulls N' Bears |
| Ownership | 100% (via Gum Creek Gold Mines Pty Ltd) | Interim report, Mar 2026 |
| Tenure | Existing resources sit on granted Mining Leases | Annual report FY2020 |
| Historic production | More than 1.1Moz to 2005; 37 open pits and 3 underground mines on the belt | Gold Industry Group; Stockhead; ASX quarterly |
| Mineral Resource | 37.97Mt at 1.89g/t Au for 2.30Moz (4 Nov 2025) | ASX, 4 Nov 2025 |
| Ore Reserve | 728koz Probable (maiden, Jul 2026) | DFS, 22 Jul 2026 |
| Base-metal resource | Altair VMS: 7.0Mt at 1.8% Zn, 0.5% Cu, 5.0g/t Ag (2.9% ZnEq), Inferred | Kalkine (company-sourced) |
| Metallurgy | Predominantly free milling; DFS total recovery 91.5%; Wilsons is refractory | DFS; 2018 RIU presentation |
Strategy
Stated strategy themes (paraphrased from the FY2025 and FY2026 annual reports, the Mar 2026 raise and the DFS):
-
Become a stand-alone gold producer at Gum Creek.
-
Deliver a simple, free-milling, open-pit first stage, as a technically de-risked base case.
-
Grow resources through cost-effective exploration across an underexplored brownfields belt, prioritising high-grade extensions beneath historic pits (Omega, Kingfisher, Swan-Swift, Wedge).
-
Use the elevated A$ gold price environment to fund development.
Medium-term guidance and timeline: FID in Q2 2027; early works, approvals and team build-out during 2027; plant construction from Q4 2027 over about 12 months; first gold in H2 2028 (DFS; FY2026 results materials).
Products & Services
Horizon has no commercial products. Its "portfolio" is its deposits and prospects. Each is catalogued below with the most recent disclosed parameters.
Planned "product": gold doré from a 2.4Mtpa processing plant, expandable to 3.0Mtpa. Average production is 98koz/yr in years 1–5, 88koz/yr over the life of mine, and 114koz peak in year 2 (DFS, Jul 2026).
Product Portfolio
| Deposit / prospect | Type | Latest disclosed data | Role | Source / date |
|---|---|---|---|---|
Swan / Swift (open cut) | Free milling, Gidgee Shear Zone | 2021 MRE: 4.16Mt at 2.41g/t for 323koz (since re-modelled in 2023/2025 updates); 22m at 3.18g/t from 2m | DFS mining area; adjacent to the old Gidgee Mill site | ASX Feb 2021; Bulls N' Bears 2026 |
Swan / Swift (underground) | Free milling, high grade | 2021 MRE: 0.70Mt at 6.71g/t for 150koz; 1.5g/t cut-off in the 2025 MRE | Outside DFS; upside | ASX Feb 2021, Nov 2025 |
Kingfisher (open cut) | Free milling | Open-cut MRE 1.22Mt at 2.01g/t; Aug 2026 RC intercept 23m at 5.26g/t from 188m (20 RC holes, 3,273m) | DFS plus resource growth; MRE update due late 2026 | ASX, 3 Aug 2026 |
Kingfisher (underground) | Free milling | 4m at 11.35g/t incl. 1m at 42.2g/t; 5m at 2.42g/t from 338m | Underground option | ASX Feb and Apr 2026 |
Omega | High-grade beneath workings | Mineralisation extended more than 120m down plunge; 14m at 2.87g/t; 8m at 4.60g/t from 342m | Underground target | ASX, 29 Apr 2026 |
Howards | Free milling, bulk | Jul 2013 estimate about 5.97Mt at 1.06g/t (204koz); 28m at 3.88g/t reported in 2026 | Major DFS mining area | RIU presentation 2018; Bulls N' Bears 2026 |
Wilsons (UG) | Refractory | About 400koz at 4.31g/t (2026); 2013: 2.27Mt at 5.37g/t for 391.5koz | Outside DFS; requires a refractory circuit or third-party treatment | SmallCaps 2026; RIU 2018 |
Hawk | Free milling | 12m at 2.30g/t from 140m incl. 6m at 4.26g/t | MRE update due late 2026 | Kalkine, Aug 2026 |
Eagle / Eagle South | Free milling | Mineralisation extended 300m south | Resource expansion | ASX, 9 Jun 2026 |
Goldfinch | Free milling, shallow | 11m at 3.18g/t | Maiden MRE pending | ASX, Jun 2026 |
Robin | Free milling, shallow | 7m at 2.46g/t | Exploration | Bulls N' Bears 2026 |
Shrike South | Free milling | Included among significant intercepts (Jun 2026) | Exploration | ASX, 9 Jun 2026 |
Wedge | High grade | "Spectacular" high-grade intercept (historic announcement) | UG target | ASX references |
Heron South | Free milling | Resource-extension target | Exploration | RIU 2018 |
Altair | VMS Zn-Cu-Ag | 7.0Mt at 1.8% Zn, 0.5% Cu, 5.0g/t Ag (2.9% ZnEq) Inferred | Non-core optionality | Kalkine 2026 |
Other MRE deposits | Mixed | Kingston Town, Think Big (Wyooda), Toedter, Specimen Well, Kearrys, Hyperno-Reliance, Melbourne Bitter, Deep South (named in the Nov 2025 MRE) | Feed optionality | ASX, 4 Nov 2025 |
Financial Narrative
All figures are A$ millions unless stated. FY2024 to FY2026 come from annual-report summaries (Quartr, citing FY2025 and FY2026 annual reports).
Income statement
Gross profit, operating income, EBITDA, pre-tax income margins and revenue CAGR are not applicable (pre-revenue). Pre-tax income is approximately equal to net loss, since no material tax expense is disclosed. The FY2026 EPS of about -1.2 cents is per Market Index.
Commentary. Losses are small because Horizon capitalises most exploration and evaluation spending onto the balance sheet. That is why net assets grew to A$72M while the P&L loss was only A$2M. The FY2025 improvement (a loss of A$0.97M against A$1.71M) reflected cost control and investment income. The FY2025 comprehensive profit was driven by the revaluation of the Alto Metals stake, which was later sold for about A$5M. The FY2026 loss doubled as the company built a development team (a new CEO), ran study overheads and issued share-based payments (3.5M performance rights to the CEO), partly offset by interest on the larger cash balance.
Balance sheet
FY2024 net equity is implied at about A$31.9M, since FY2025 equity of A$33.53M was a 5% increase; this is derived rather than reported. Total assets and working capital were not separately disclosed in the sources reviewed. The FY2025 year-end debt position is described as nil drawn, with a A$1.5M undrawn facility. No borrowings are disclosed at FY2026, so net debt was about -A$24.05M (a net cash position).
Commentary. The balance sheet changed completely in FY2026. Cash rose about 48-fold, from A$0.5M to A$24.05M, after A$39.7M of equity raisings: the A$12M in Jul–Sep 2025 and A$30.2M in Mar–Apr 2026, less costs and timing differences. Equity more than doubled. The company states it is funded through to FID (ASX, 4 Mar 2026).
Cash flow
Source: Appendix 5B, 30 Jul 2026.
Commentary. The run-rate investment of about A$5.4M per quarter (exploration plus PP&E) against A$24M of cash implies roughly four to five quarters of runway at the current four-rig intensity. That is consistent with the Q2 2027 FID timetable, but it leaves little buffer for pre-FID early works without new funding. Free cash flow is structurally negative until production.
Ratios
Price/book is computed as market cap divided by net assets: A$84M / A$33.53M for FY2025 and A$204.5M / A$72.14M for FY2026. FY2026 book value per share is per Market Index. ROE, ROA, ROIC, interest coverage, net debt/EBITDA, asset turnover and the cash conversion cycle are not meaningful (negative earnings, no EBITDA, no revenue). The current ratio was not disclosed but is clearly well above 1x at FY2026, given A$24M cash and the absence of debt.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansFinancial Detail
Balance Sheet and Per-Share Data
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Operating revenue (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Other income, interest (AUD Mn) | — | — | — | — | 0.513 |
Net loss after tax (AUD Mn) | — | — | -1.705 | -0.972 | -2.02 |
Gain on revaluation of equity instruments, OCI (AUD Mn) | — | — | — | 2.489 | — |
Total comprehensive result (AUD Mn) | — | — | — | 1.517 | — |
EPS basic (A$ per share) | — | — | — | — | -0.012 |
Dividends per share (AUD) | 0 | 0 | 0 | 0 | 0 |
Balance Sheet
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Cash and equivalents (AUD Mn) | — | — | — | 0.503 | 24.05 |
Net assets / total equity (AUD Mn) | — | — | — | 33.53 | 72.14 |
Total borrowings (AUD Mn) | — | — | — | 0 | 0 |
Undrawn Zeta loan facility (AUD Mn) | — | — | — | 1.5 | — |
Goodwill and intangibles (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Balance Sheet — Equity capital raised
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Equity capital raised (AUD Mn) | — | — | — | — | 39.7 |
Dividends paid (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Buybacks (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Metric (Q4 FY2026, quarter to 30 Jun 2026) | Q4FY2026 | — | — | — | — |
Net operating cash flow (AUD Mn) | -0.358 | — | — | — | — |
Payments for property, plant and equipment (AUD Mn) | -0.766 | — | — | — | — |
Exploration and evaluation expenditure (AUD Mn) | -4.635 | — | — | — | — |
Proceeds from issue of equity (AUD Mn) | 10.178 | — | — | — | — |
Closing cash (AUD Mn) | 24.045 | — | — | — | — |
Financial Ratios (x) and Per-Share Data
| Ratio | FY2025 | FY2026 |
|---|---|---|
Debt / equity (x) | 0 | 0 |
Price / book (x) | 2.51 | 2.83 |
Book value per share (AUD) | — | 0.37 |
Geographic Revenue
| Region | FY2024 | FY2025 | FY2026 |
|---|---|---|---|
Australia — operating revenue (AUD Mn) | 0 | 0 | 0 |
Rest of world — operating revenue (AUD Mn) | 0 | 0 | 0 |
Share Price and Market Valuation
| Metric | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|---|
Share price at 30 June (AUD) | 0.44 | 0.35 | 0.36 | 0.30 | 0.58 | 1.05 |
Market capitalisation at 30 June (AUD Mn) | — | — | — | — | 84 | 204.5 |
Return period (to 30 Jun 2026)
| Return period (to 30 Jun 2026) | % |
|---|---|
1-year (from A$0.58) | 81 |
3-year (from A$0.36) | 192 |
5-year (from A$0.44) | 139 |
Valuation Snapshot
| Metric | Value | Basis |
|---|---|---|
Enterprise value (AUD Mn) | 180.5 | A$204.5M market cap minus A$24.05M cash, no debt |
EV per resource ounce (A$/oz) | 78 | 180.5 / 2.30Moz |
EV per reserve ounce (A$/oz) | 248 | 180.5 / 0.728Moz |
P / NAV (pre-tax DFS NPV5) (x) | 0.16 | — |
P / B (x) | 2.83 | 204.5 / 72.14 |
Capital Markets
| Item | Status |
|---|---|
Analyst consensus | No major broker coverage (Market Index) |
Dividend history / policy | No dividends ever paid; none expected before production |
Credit ratings (Moody's / S&P / Fitch) | Not rated |
Debt maturity profile | No debt outstanding at FY2026 |
Equity issuance history | Rights issues at A$0.30 (2020), A$0.35 (2021), A$0.35 (2022), A$0.30 (2023), A$0.48 (2025), A$1.20 (2026) |
Analyst Conclusions
Management guidance
-
FID targeted for Q2 2027.
-
Approvals, early works and team build-out during 2027.
-
Plant construction from Q4 2027 (about 12 months).
-
First gold in H2 2028.
-
MRE updates for Kingfisher, Hawk and Swan, plus a maiden Goldfinch MRE, later in 2026.
-
Project finance through a debt and equity combination.
Consensus: none available.
Bull case
-
Deep NAV discount. At about 0.16x pre-tax NPV and about A$78/oz EV per resource ounce, the market values Gum Creek well below the DFS. A credible financing package typically drives developer re-rating.
-
Growth beyond the DFS. About 816koz of underground ounces (416koz free milling plus 400koz Wilsons) sit outside the mine plan. Post-DFS intercepts such as 23m at 5.26g/t at Kingfisher point to mine-life extension and a 3.0Mtpa expansion (+25%).
-
Strategic scarcity. Gum Creek is one of WA's larger undeveloped, permitted-tenure gold camps in a consolidating district, which supports takeover optionality.
Bear case
-
Funding gap. Capex of A$350M against a A$204M market cap and A$24M cash means heavy dilution, restrictive debt (hedging) or a control transaction on terms set by Zeta.
-
Price-deck dependence. At A$4,000/oz the pre-tax NPV falls to A$335M (IRR 19.5%). Much of the DFS value reflects today's elevated price.
-
Execution risk. A small team with a new CEO must deliver a new plant amid WA cost inflation, with a Probable-only reserve covering about 32% of the resource.
Catalysts and monitorables (next 12 months)
| Timing | Catalyst |
|---|---|
| 19 Oct 2026 | September-quarter report (cash burn, drilling) |
| Q4 2026 | MRE updates (Kingfisher, Hawk, Swan; Goldfinch maiden) |
| Late 2026 – 2027 | Lender term sheets and mandates via Orimco; possible offtake or streaming |
| 2,027 | Mining proposal and works approvals; EPC selection |
| Q2 2027 | FID |
| Ongoing | A$ gold price; Zeta's funding intentions; any district M&A |
Analyst verdict
Horizon Gold has crossed the most important threshold a junior gold company can cross. It has converted a long-dormant, historically productive camp into a bankable-grade development project. The July 2026 DFS is the inflection point. It shows a simple, free-milling, 2.4Mtpa open-pit operation producing 98koz a year in its first five years at an AISC of about A$3,000/oz. At the study's A$5,500/oz deck, that yields a pre-tax NPV5 of A$1.31B and an IRR of 53%, with payback in under two years. The resource base has grown about 70% in five years, and the newest drilling, especially at Kingfisher and Omega, sits largely outside the mine plan. That suggests the DFS is a floor rather than a ceiling.
The market's scepticism is nonetheless rational. The equity is worth roughly one-sixth of the study's pre-tax NPV because three hurdles remain. The first is funding A$350M from a A$24M cash base. The second is building a greenfield plant in Australia's most inflation-prone mining jurisdiction with a newly assembled team. The third is navigating a register controlled about 65% by Zeta Resources, which limits liquidity and makes minority outcomes depend on the controlling holder's preferences. Gold-price sensitivity amplifies all three: a return to A$4,000/oz would remove about three-quarters of the pre-tax value.
On balance, Horizon offers asymmetric exposure to the WA developer re-rating cycle for investors who accept financing and governance risk. The decisive monitorables are the quality of the debt package (gearing, hedging requirements, any streaming), the scale of resource growth in the late-2026 MRE updates, and whether approvals keep FID on schedule for Q2 2027. A credible financing announcement would likely narrow the NAV discount sharply. A slip in FID, or dilutive funding at depressed prices, would extend the "show-me" phase.
All figures are from public sources as cited. Known discrepancies: some secondary sources (e.g. Kalkine, Mar 2026) still quote the superseded 1.39Moz resource; the current figure is 2.30Moz (4 Nov 2025). Leigh Ryan is described as moving to GM Exploration (ASX, 30 Jan 2026), while the interim report records him as resigning as a director on the same date; both are consistent with ceasing board membership while remaining an employee.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansExecutive Leadership
Executive Leadership Team
| Name | Role | Tenure / notes | Background (as disclosed) | Shares held (latest notice) |
|---|---|---|---|---|
Scott Williamson | CEO and Managing Director | From 2 Feb 2026 | Mining engineer with 20+ years of experience; prior roles at Blackstone Minerals and Resolute Mining | None disclosed (performance rights only) |
Peter Sullivan | Non-executive Chairman | Executive Chairman until 2 Feb 2026, then Non-executive; long-standing director associated with the Zeta Resources/ICM group | Not detailed in sources reviewed | 5,263,901 indirect |
James (Jamie) Sullivan | Non-executive Director | Director since at least 2020 | Not detailed in sources reviewed | 92,711 direct; 2,437,653 indirect |
Peter Venn | Non-executive Director | Director since at least 2018 | Not detailed in sources reviewed | 585,691 indirect |
Leigh Ryan | General Manager – Exploration (former MD) | MD c. 2020 to 2 Feb 2026; interim report records him as resigned as a director on 2 Feb 2026 | Geologist; led resource growth from 1.36Moz to 2.30Moz | Small holdings (rights-issue participation) |
Trevor O'Connor | CFO / Company Secretary (named as contact on announcements) | Long association, dating back to Panoramic-era management | Former Panoramic CFO (from 2003) | — |
“—” = not publicly disclosed.
Directors' Remuneration
| Executive | Salary (AUD) | Equity | Source |
|---|---|---|---|
Scott Williamson (CEO/MD) | 300000 plus superannuation | 3,500,000 performance rights (LTI) | ASX, 30 Jan 2026 |
Major Shareholders
| Holder | Shares | % | Date | Source |
|---|---|---|---|---|
Zeta Resources Limited | 120,532,502 | 64.69 | 12 Mar 2026 notice | Market Index |
L1 Capital Pty Ltd | 12,840,403 | 6.59 | 20 Aug 2026 notice | Market Index |
Hardrock Capital Pty Ltd (two accounts) | 5,013,240 | about 2.95 | Sep 2025 top-20 | Market Index (Morningstar) |
Clearpool Capital Holdings | 2,083,333 | 1.23 | Sep 2025 | Market Index |
Peter Sullivan (indirect) | 5,263,901 | about 2.7 | Apr 2026 | Market Index |
Jamie Sullivan (direct and indirect) | 2,530,364 | about 1.3 | Apr 2026 | Market Index |
Competitive Landscape
Key Competitors
| Peer | Relevance to Horizon | Relative positioning |
|---|---|---|
Ramelius Resources (ASX: RMS) | Mid-tier WA producer; Mt Magnet hub in the Murchison | Producer with mills; potential acquirer or toll-treatment counterparty |
Westgold Resources (ASX: WGX) | Murchison producer (Meekatharra/Cue hubs) | Regional mill owner; consolidator |
Genesis Minerals (ASX: GMD) | WA producer (Leonora), former developer re-rated on consolidation | Valuation benchmark for developer-to-producer transitions |
Capricorn Metals (ASX: CMM) | Mid-West producer (Karlawinda), growing Mt Gibson | Benchmark for single-asset WA developers |
Brightstar Resources (ASX: BTR) | Sandstone-district neighbour and consolidator | Closest geographic competitor for regional ounces |
Aurumin (ASX: AUN) | Sandstone-district holder | Regional consolidation context |
New Murchison Gold (ASX: NMG) | Near-term Mid-West developer | Competes for development capital |
Meeka Metals (ASX: MEK) | Murchison developer (Murchison Gold Project) | Peer developer |
Antipa Minerals (ASX: AZY) | 2.5Moz WA developer/explorer; raised A$40M in Jul 2025 | Resource-size peer for valuation |
Ora Banda Mining (ASX: OBM) | WA restart story | Restart benchmark |
Competitor Detail
| Metric | Horizon Gold (FY2026 / DFS) |
|---|---|
Revenue (AUD Mn) | 0 |
Resource (Moz) | 2.30 |
Reserve (Moz) | 0.728 |
Planned production, first 5 years (koz/yr) | 98 |
AISC, DFS (A$/oz) | 2,995 |
Pre-production capex (AUD Mn) | 350 |
Market cap at 30 Jun 2026 (AUD Mn) | 204.5 |