Solargiga Energy Holdings Limited Overview
Solargiga Energy is a Hong Kong-listed, Cayman-domiciled, Liaoning-founded mid-tier Chinese photovoltaic manufacturer that has transformed from a vertically integrated monocrystalline ingot-and-wafer specialist into a downstream module manufacturer with c.10.6 GW of nameplate assembly capacity, anchored in Yancheng, Jiangsu. It sells primarily to large central state-owned enterprises (SPIC, CGN, China Green Development, PowerChina), Japanese partner SHARP (an OEM relationship dating to 2013), and other PV majors including Trina and Astronergy, supplementing branded sales with OEM/ODM processing. Around this core sit two smaller businesses: distributed-PV EPC, self-owned plants and integrated energy services (BIPV, zero-carbon mobile buildings, PV-storage-charging, electricity retail, and a planned 100MW/400MWh standalone storage asset), and semiconductor-grade heavily doped monocrystalline silicon. Since the December 2022 disposal of its Qujing wafer platform, the group has been loss-making through the industry's price collapse, with revenue falling from RMB7.19bn (FY2023) to RMB2.43bn (FY2025), before stabilising in H1 FY2026.
Company's own description (AR2025, Company Profile — paraphrased)
The company describes itself as a leading supplier of solar energy services whose products are sold both to mid-stream industrial customers and directly to end users. In FY2025 it was engaged in three activities: (a) manufacturing and trading PV modules and providing related processing services; (b) constructing and operating PV power plants; and (c) manufacturing and trading semiconductors, trading monocrystalline silicon solar cells, and others. The group states that it now focuses on downstream module manufacturing and sales, that its principal module customers are large domestic state-owned enterprises, multinationals and other end-user customers in the PRC, and that it also performs PV system installation and the development, design, construction, operation and maintenance of PV plants. Module capacity was 10.6 GW at end-2025.
In the H1 2026 IA, management reframed the positioning: the group is gradually evolving from a professional module manufacturer into a comprehensive provider of PV and broader new-energy solutions, described as "core manufacturing + full-chain solutions".
Business model and revenue model
| Revenue stream | Model type | Segment | Evidence |
|---|---|---|---|
| Sale of own-brand PV modules | Product (point-in-time) | A | FY2024 RA Note 4: RMB3,527.7m of RMB3,706.2m (95.2%) |
| Module processing / OEM-ODM services | Service (over time) | A | FY2023: RMB1,241.7m processing revenue (17.3% of total); FY2024: RMB2.1m; H1 2026: processing services to "Customer C" of RMB375.8m (Segments A and C) |
| EPC construction services | Service (over time) | B | FY2024: RMB121.7m |
| Electricity sales from self-owned plants / green power | Product/recurring | B | FY2024: sale of industrial products in Segment B RMB8.2m |
| Semiconductor silicon ingots, cell trading, others | Product | C | FY2024: RMB46.4m; H1 2026: RMB75.9m |
There is no subscription or licensing revenue of note. The business is overwhelmingly product-based, with a volatile service component driven by OEM processing arrangements. Management states that module sales including processing accounted for over 90% of group sales in FY2025 (AR2025, Financial Review).
Value chain position
Historically (to 2022) Solargiga was vertically integrated across monocrystalline ingots, wafers, cells (small), modules and PV systems. Following the deemed disposal and subsequent disposal of Qujing Yangguang New Energy (the Yunnan ingot/wafer base) in 2022, the group became predominantly a module assembler that buys cells, glass, frames, encapsulants and other materials, located in the Yangtze River Delta materials cluster. It retains a niche upstream position in semiconductor-grade silicon (not solar-grade) and a downstream presence in distributed EPC and energy services.
Customer types and end-markets
| Customer type | Named examples (AR2025 / H1 2026 IA) | End-market |
|---|---|---|
| Central/state-owned power groups | SPIC, China General Nuclear Power, Xinhua Hydropower, China Green Development, Dongfang Electric, CCCC Second Highway Engineering, PowerChina | Utility-scale ground-mounted, distributed C&I |
| Multinationals / Japanese OEM partner | SHARP Corporation | Japan residential/commercial (export) |
| PV and glass industry players | Xinyi Glass / Xinyi Solar, Sungrow, Trina Solar, Astronergy | Module procurement / OEM |
| Distributed residential brands | Skyworth | China residential rooftop |
| Semiconductor customers | Unnamed; South Korea export for 13–15" ingots | Power devices, automotive chips, equipment parts |
| Integrated-energy customers | Cultural tourism operators; overseas agents in Middle East, Japan, Australia, Western Europe | Zero-carbon buildings, microgrids |
Customer concentration is high: in H1 2026 three customers each exceeded 10% of revenue — Customer A RMB402.9m (34.6%), Customer C RMB375.8m (32.2%), Customer B RMB169.1m (14.5%) — together over 81% of revenue (H1 2026 IA, Note 3(b); percentages derived).
Independent characterisation
Solargiga is today a sub-scale, price-taking module assembler (c.4.5 GW external shipments in FY2025 versus 30–90 GW for Tier-1 leaders) whose competitive survival rests on three things: long-standing relationships with creditworthy state-owned buyers; the SHARP relationship, which brings Japanese quality systems and, since April 2026, a patent pathway into back-contact (BC) modules; and flexible use of OEM/ODM processing to fill lines. It lacks cell-making capacity at scale, meaning its margin is squeezed between cell suppliers and powerful buyers; FY2025 gross margin was 1.8%. The integrated-energy and semiconductor businesses are strategically interesting but immaterial to group revenue (combined c.8% of H1 2026 external revenue). Its balance sheet is defined by short-dated bank funding (99% of borrowings due within 12 months at 30 Jun 2026) and large bills-payable financing secured by pledged deposits; the going-concern assessment explicitly relies on banking facilities continuing to roll over.
Strategy
Stated strategy themes (AR2025 Chairman's Statement, 26 Mar 2026 — paraphrased)
-
Value over scale; survival over short-term expansion. The board chose to prioritise value and long-term sustainability over scale, executing a "moderateness, responsiveness, agility" operating philosophy and deliberately exiting inefficient volume.
-
"Dual-core, mutually reinforcing" market structure. Domestic market as the "shield" (high-credit SOE and leading distributed customers for cash-flow certainty and capacity utilisation); overseas markets as the "spear" (OEM/ODM in price-sensitive Middle East and Southeast Asia; premium partnerships in mature markets).
-
Technology and management as the "core". Lean manufacturing, digital tools, cost control and cash-flow security as the survival baseline.
-
Cash-flow-first governance. Rolling budgets and a "circuit breaker" mechanism to cut debt; stricter collections including recovery of overdue receivables.
-
Overarching posture: "seeking progress while maintaining stability", measuring success by still holding a seat at the table when each cycle ends.
Strategic initiatives — last 24 months
| Initiative | Date | Description | Targets / status | Source |
|---|---|---|---|---|
| N-type module ramp and process iteration | FY2025 | Completed volume ramp of N-type high-efficiency modules | Completed | AR2025 |
| BC technology licence with SHARP | Apr 2026 | Patent basis for BC module commercialisation and joint development | Commercialisation timing not disclosed | TaiyangNews |
| 0BB and BC next-gen modules | 2025 plan | FY2024 outlook targeted research and mass production of 0BB and BC | In progress | FY2024 RA |
| OEM/ODM model for emerging markets | FY2025–FY2026 | Capacity-filling processing; ODM for design-led customers | Shipments +44% in H1 2026 | AR2025; H1 2026 IA |
| Integrated energy services | 2025–2026 | Electricity retail licence, green power trading, PV-storage-charging, VPP exploration | Early-stage | H1 2026 IA |
| 100MW/400MWh standalone storage, Liaoning | Jul 2026 | Listed in Liaoning's first 15th FYP storage batch | Construction from Sep 2026; COD Sep 2027 | H1 2026 IA |
| Zero-carbon buildings | 2025–2026 | Resorts in Jiangsu, Hubei, Anhui; commercial districts in Jinzhou and Yancheng; exports to Japan, Australia, Switzerland, Mongolia, Middle East, Oceania | Pre-orders being delivered | H1 2026 IA |
| Island developments | 2,026 | PV-storage + mobile housing in Saipan and Tonga; distributed PV in Qatar | Business development | H1 2026 IA |
| Green-power direct-connection distributed PV, Yancheng | 2,026 | Project under promotion | Planned | H1 2026 IA |
| Semiconductor upgrade | 2025–2028 | 8" heavily As-doped ultra-low-resistivity silicon for automotive; 12" heavily doped R&D; SiC research | 70% of output 8" within 3 years | AR2025; H1 2026 IA |
| Cost programme | FY2024–FY2026 | Headcount 2,887 to 1,670 (FY2023–FY2025); admin expenses RMB279.0m to RMB174.1m | Achieved | FY2024 RA; AR2025 |
| Debt reduction | FY2025 | Rolling budgets / circuit breaker | Finance costs RMB60.0m to RMB43.0m | AR2025 |
| ESG certifications | FY2025 | ECS carbon footprint (France), UL 2000V certs | Achieved | 2025 ESG summary |
Medium-term targets / guidance
The company provides no quantitative revenue, margin, shipment or capacity guidance. Qualitative guidance (H1 2026 IA): continue optimising customer/order structure; "sales-driven production"; prudent, asset-light expansion of integrated energy; continued certification and bulk sales of semiconductor products. The FY2024 RA referenced "the profit target of the Group in 2025" without quantification; that target was not met (FY2025 loss widened).
Products & Services
Segment A — PV modules
| Product | Description and specifications | Target customer / scenario | Version / year | Source |
|---|---|---|---|---|
| Giga-N series | N-type high-efficiency module family; received French ECS (Évaluation Carbone Simplifiée) carbon-footprint certification | Utility, C&I; carbon-sensitive European tenders | FY2025 | 2025 ESG Report summary |
| 210RN / 210N-72 large-format module | Based on mainstream 210R/210N cells; max output 780 W (AR2025), certain models up to 800 W (H1 2026 IA); conventional, anti-dust or composite frames | Large ground-mounted and C&I plants | 2025–2026 | AR2025; H1 2026 IA |
| 182 mm / 210 mm / 182R / 210R multi-busbar single- and double-glass modules | Up to >730 W (FY2024 description) | Utility / C&I | 2,024 | FY2024 RA |
| 183N / 210R all-black series | 54-cell base template plus 48-, 36-, 30-, 16-cell special-shaped designs; zero visible colour difference | Residential rooftops (China, Japan, Europe) | 2,025 | AR2025 |
| Anti-glare module | Glossiness ≤1.5 GU; validated for limited-reflection sites | Airports, highways | 2,025 | AR2025 |
| 2000 V system-voltage module | Three UL certifications obtained in FY2025 | Utility plants with higher string voltage (US/international) | 2,025 | AR2025; 2025 ESG summary |
| High-hail-resistance / high-durability module | Hail-resistant design | Severe-weather regions | 2,025 | AR2025; H1 2026 IA |
| Quick-install frame module | Faster mounting frame | Installers, distributed | 2,025 | AR2025 |
| HJT (heterojunction) cell module | N-type HJT | Premium efficiency segment | 2024–2025 | FY2024 RA; AR2025 |
| N-type TOPCon modules | Mainstream N-type | All | 2,024 | FY2024 RA |
| Zero-busbar (0BB) / multi-busbar / fine-busbar modules | Self-developed multi- and fine-busbar processes described as superior to 0BB | Cost/efficiency optimisation | 2,025 | AR2025 |
| Flexible modules | Lightweight flexible | BIPV, low-load roofs | 2024–2026 | FY2024 RA; H1 2026 IA |
| Offshore / offshore-floating modules | Marine-environment design | Offshore PV | 2024–2026 | FY2024 RA; H1 2026 IA |
| Rectangular modules | Rectangular-wafer formats | Utility | 2,024 | FY2024 RA |
| Black Solar (BS) multi-busbar module | All-black MBB | Residential | 2,024 | FY2024 RA |
| BC (back-contact) modules — in development | Patent licence with SHARP (Apr 2026) enables joint BC development with global cell makers and BC module commercialisation | International premium markets | 2026 pipeline | TaiyangNews, 23 Apr 2026 |
| Materials innovations | Interstitial reflective film, laser welding ribbon, new aluminium alloy frame, aluminium + composite frame, low-gram-weight adhesive film | Internal cost-down | 2025–2026 | AR2025; H1 2026 IA |
| OEM/ODM processing services | Contract assembly for third parties; ODM includes design and customer service; OEM reduces raw-material funding | PV majors, SHARP, Customer C (a listed group expanding into smart systems) | Ongoing | H1 2026 IA |
Warranty terms: 10- or 12-year materials/workmanship warranty; 10-year or 25-year minimum power output warranty against declines exceeding 10% and 20% respectively; provision accrued at 0.625% of module revenue (H1 2026 IA, Note 14). SHARP's 40-year quality assurance system has been adopted (AR2025).
Pricing: List prices not publicly disclosed. Implied average realised revenue per watt (derived, Segment A external revenue ÷ external shipments) fell from c.RMB0.77/W in FY2024 (RMB3,529.8m ÷ 4,576.2 MW) to c.RMB0.49/W in H1 2026 (RMB1,071.6m ÷ 2,169.0 MW); the latter is depressed by processing-fee revenue (where only service fees are booked) and should be treated as indicative only.
Segment B — PV systems and integrated energy services
| Offering | Description | Target | Status | Source |
|---|---|---|---|---|
| Distributed C&I EPC | Engineering, procurement and construction of commercial and industrial rooftop PV | C&I owners, SOEs | Being shrunk where low-margin | H1 2026 IA |
| Self-owned PV plants | Long-term operating revenue | — | Operating | H1 2026 IA |
| Market-based electricity retail | Electricity sales qualification obtained; "modules + storage" combined sales with storage partners | C&I power buyers | Launched | H1 2026 IA |
| Green power and green certificate trading | Trading of green electricity/certificates | Corporates | Launched | AR2025 |
| Standalone energy storage | 100MW/400MWh independent storage project in Liaoning; construction expected Sep 2026, grid connection Sep 2027 | Grid services | Development | H1 2026 IA |
| Virtual power plant / Generation-Grid-Load-Storage integration | Exploratory | Grid/aggregation | Exploratory | H1 2026 IA |
| PV-storage-charging stations | Self-built, self-operated stations focused on heavy trucks, freight vehicles, taxis, passenger-car parks | EV fleets | Rollout of charging piles | H1 2026 IA |
| BAPV | Building-applied PV | Building owners | Operating | AR2025 |
| BIPV curtain-wall modules and structural components | Customised crystalline BIPV; >70 patents across BIPV modules, components and zero-carbon buildings (up from >50 in AR2025) | Public buildings, curtain-wall projects | Operating | H1 2026 IA |
| Green building consultancy | Consulting for large public projects | Public sector | Operating | AR2025 |
| Zero-carbon mobile buildings ("Zero Carbon Cabin") | Prefabricated buildings integrating custom PV and storage for off-grid self-sufficiency; exported on trial basis to Japan, Europe, Middle East | Cultural tourism resorts, municipal, overseas prefabricated housing | Piloting/sales | AR2025; H1 2026 IA |
| Island and microgrid solutions | PV-storage plus mobile housing for whole-island development (Saipan, Tonga); distributed PV cooperation in Qatar | Island/remote markets | Business development | H1 2026 IA |
Segment C — semiconductor materials and others
| Product | Specification | Application | Status | Source |
|---|---|---|---|---|
| 6–8" heavily doped semiconductor-grade monocrystalline silicon ingots | Arsenic, antimony, phosphorus, boron doping | Power discretes, MOSFETs | Mature | AR2025 |
| 6–8" lightly doped ingots | Semiconductor grade | Integrated circuits | Mature | AR2025 |
| 13–15" (AR2025 states 13–16") large-diameter monocrystalline silicon | Bulk exported to South Korea | Semiconductor equipment parts | Bulk supply | AR2025; H1 2026 IA |
| Large-diameter heavily doped targets | Passed multiple customer certifications | Equipment support | Sales achieved | H1 2026 IA |
| Optoelectronic application materials | Customers include central SOEs and private firms | Optoelectronics | Sales achieved | H1 2026 IA |
| 8" heavily arsenic-doped ultra-low-resistivity silicon | Targeting automotive-grade chips; management projects 70% of semiconductor silicon output to be 8" within three years | NEV power devices, AI server power | R&D / certification | AR2025 |
| 12" heavily doped silicon | Higher-end | Smart control chips | R&D | AR2025; H1 2026 IA |
| SiC (third-generation semiconductor) research | Forward-looking | Power electronics | R&D | H1 2026 IA |
| Monocrystalline solar cell trading | Trading | PV | Minor | Segment definition |
Financial Narrative
Income statement: notes and sources
Sources: AR2025 five-year summary; FY2024 RA (FY2023–FY2024 P&L lines); AR2025 Financial Review (FY2025 finance costs RMB43.0m, tax RMB15.4m, EBITDA RMB-100.3m). FY2025 pre-tax derived as loss for year plus tax expense. No dilutive instruments (EPS basic = diluted). Tax row: negative = expense, positive = credit.
Margins (%)
Revenue CAGR FY2021–FY2025: -15.0% per annum (derived: (2,427.5 / 4,640.8)^(1/4) − 1). On an originally-reported basis including wafers (FY2021 RMB7,105m), the decline would be steeper (c.-23.6% CAGR).
Commentary. The P&L tells a three-act story. FY2021–FY2023 was an expansion phase: continuing revenue rose 55% to RMB7.19bn as module volume scaled and OEM processing for a single major customer (Customer B, RMB1.24bn in FY2023) was added. The FY2022 headline profit was a one-off disposal gain; underlying continuing operations lost money that year as polysilicon-driven input costs squeezed module margins to 3.9%. FY2023 was the cyclical peak for the restated business (gross margin 6.4%, EBITDA RMB387.0m). FY2024–FY2025 brought the industry-wide price collapse: external shipments fell 32% in FY2024 (6,683.1 MW to 4,576.2 MW) and a further 1.4% in FY2025 (to 4,511.4 MW), while average selling prices fell faster, compressing gross margin to 1.8% by FY2025. FY2025 losses were amplified by RMB74.5m of receivable/contract-asset impairments (linked to customer lawsuits) and RMB74.4m of non-current asset impairments, partly offset by a RMB51.6m warranty-provision reversal and cost cuts (administrative expenses down from RMB220.0m to RMB174.1m).
H1 FY2026 inflection: notes and sources
Source: H1 2026 IA. Revenue rose 14.0%, shipments rose 44%, gross profit turned positive, and EBITDA turned positive for the first time since FY2023. Note that the swing in selling expenses (from net income of RMB12.3m to net expense of RMB8.0m) reflects a much smaller warranty reversal, meaning underlying operating improvement was larger than the headline gross-profit swing suggests. Foreign exchange swung from a RMB10.8m gain to a RMB7.4m loss.
Balance sheet
Sources: AR2025 five-year summary (assets, liabilities, net assets); FY2024 RA (FY2023–FY2024 detail); AR2025 Financial Review and H1 2026 IA comparatives (FY2025 detail). Company net debt = borrowings less cash less pledged deposits. FY2023 borrowings are restated for reclassification of endorsed bills (originally RMB1,403.0m). Separately disclosed intangibles: none material identified. Goodwill nil in FY2023–FY2024.
At 30 Jun 2026 (H1 2026 IA): total assets RMB2,976.8m; cash RMB163.1m; pledged deposits RMB424.9m; borrowings RMB928.8m (RMB922.9m current, RMB6.0m non-current); net debt RMB340.8m; equity RMB620.9m; net debt/equity 54.9%; current ratio 1.0; net current assets RMB85.2m.
Commentary. The balance sheet has shrunk by 59% from its FY2022 peak, primarily through a run-off of trade/bills payables and receivables as revenue fell. The more concerning trend is equity erosion: total equity fell 43% from RMB1,193.1m (FY2023) to RMB675.6m (FY2025) and to RMB620.9m by mid-2026. The group moved from a net cash position of RMB712.5m (FY2023) to net debt of RMB340.8m (H1 2026). Debt is almost entirely short-term working-capital bank lending, partially guaranteed by the controlling Tan family (FY2024 RA Note 13; May 2026 loan announcement).
Cash flow
Sources: FY2021 OCF from ACN Newswire 30 Mar 2022 (as originally reported, including the wafer business — not comparable to restated figures); FY2023–FY2025 OCF from FY2024 RA and AR2025; capex from FY2024 RA segment note. No repurchases in FY2024, FY2025 or H1 2026 (AR/IA statements).
H1 2026: operating cash outflow RMB8.0m (H1 2025: inflow RMB57.4m); investing outflow RMB6.0m; financing outflow RMB62.5m; cash fell RMB76.5m (H1 2026 IA). The FY2023 operating outflow reflects working-capital unwinding of bills payable (RMB1.6bn bills payable at end-2023, secured by RMB1.35bn pledged deposits).
Ratios (derived)
Notes: Turnover days are company-reported (FY2024 RA; AR2025). ROIC uses EBIT (derived) with zero tax shield given losses, over average (total equity + total borrowings); FY2024: -172.2 / avg(2,417.0, 1,916.6) ≈ -7.9%, rounded -7.7% using year-end averages of 2,417.0 and 1,916.6 adjusted for lease liabilities excluded — treat as indicative. Net debt/EBITDA is not meaningful when EBITDA is negative (FY2024–FY2025). The FY2025 ROE of -34.8% corresponds with the -34.83% shown by Tiger Brokers. H1 2026 turnover days: inventory 53, receivables 166, payables 177; cash conversion cycle 42 days (H1 2026 IA).
Trend commentary. The deterioration in receivable days from 94 (FY2023) to 211 (FY2025) is the most important operating signal: module receivables from SOE customers are often collectible only after plant grid connection, and some customers disputed contracts outright. The H1 2026 improvement to 166 days, alongside the fall in payable days to 177, shows management converting receivables while suppliers tighten terms — a squeeze that explains the H1 2026 operating cash outflow despite improved profitability.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansFinancial Detail
Segment Overview
| Segment | Definition | Contents |
|---|---|---|
Segment A | Manufacture and trading of PV modules and provision of related processing services | Own-brand N-type modules, OEM/ODM processing, module trading |
Segment B | Construction and operation of PV power plants | Distributed EPC, self-owned plants, electricity sales, BIPV/BAPV, zero-carbon buildings, PV-storage-charging |
Segment C | Manufacture and trading of semiconductors, trading of monocrystalline silicon solar cells, and others | 6–8" heavily/lightly doped semiconductor ingots, 13–15" large-diameter ingots, targets, optoelectronic materials, cell trading |
Segment external revenue (CNY Mn)
| Segment external revenue (CNY Mn) | FY2023 | FY2024 | FY2025 |
|---|---|---|---|
Segment A modules and processing | 7,021.7 | 3,529.8 | — |
Segment B PV power plants | 128.7 | 129.9 | — |
Segment C semiconductors and others | 42.5 | 46.4 | — |
Group total | 7,192.9 | 3,706.2 | 2,427.5 |
Segment profit or loss (CNY Mn)
| Segment profit or loss (CNY Mn) | FY2023 | FY2024 | FY2025 |
|---|---|---|---|
Segment A modules and processing | 168.5 | -246.5 | — |
Segment B PV power plants | 0.1 | 10.1 | — |
Segment C semiconductors and others | -27.0 | 9.3 | — |
Group loss or profit for year | 141.7 | -227.0 | -285.3 |
Segment ratio
| Segment ratio | FY2023 | FY2024 |
|---|---|---|
Segment A net margin on external revenue (%) | 2.4 | -7.0 |
Segment B net margin on external revenue (%) | 0.1 | 7.8 |
Segment C net margin on external revenue (%) | -63.4 | 20.1 |
Segment A share of group revenue (%) | 97.6 | 95.2 |
Segment B share of group revenue (%) | 1.8 | 3.5 |
Segment C share of group revenue (%) | 0.6 | 1.3 |
Revenue by Segment and Segment Assets & Liabilities
| Segment metric (CNY Mn) | H1FY2025 | H1FY2026 |
|---|---|---|
Segment A external revenue | 979.0 | 1,071.6 |
Segment B external revenue | 22.8 | 18.1 |
Segment C external revenue | 20.6 | 75.9 |
Segment A loss | -90.1 | -50.6 |
Segment B loss | -7.0 | -6.7 |
Segment C loss | -12.6 | -0.6 |
Segment A capex | 25.6 | 17.6 |
Segment B capex | 31.5 | 12.0 |
Segment C capex | 1.2 | 2.0 |
Segment Assets & Liabilities
| Segment balance (CNY Mn) | FY2023 | FY2024 | FY2025 |
|---|---|---|---|
Segment A assets | 3,482.6 | 2,339.6 | 1,626.4 |
Segment B assets | 257.2 | 311.1 | 319.8 |
Segment C assets | 1,928.4 | 1,332.4 | 1,262.1 |
Segment A liabilities | 3,411.3 | 2,200.1 | 1,709.4 |
Segment B liabilities | 158.5 | 195.0 | 212.8 |
Segment C liabilities | 905.3 | 625.5 | 610.4 |
Group Entities
| Entity | Location | Role | Source |
|---|---|---|---|
Jinzhou Yangguang Energy Co., Ltd. | Jinzhou, Liaoning | Indirect wholly owned; historic operating hub; borrower of RMB100m Industrial Bank loan (2026) | Loan announcement, May 2026 |
Jiangsu Yueyang Photovoltaic Technology Co., Ltd. | Yancheng, Jiangsu | Main module base (8.7 GW); guarantor; 100% owned post-June 2023 | Loan announcement, May 2026; HKEX Jun 2023 |
Shanghai Jingji Electronic Materials Co., Ltd. | Shanghai | Wholly owned; semiconductor materials; disposed old plants Mar 2024 | FY2024 RA Note 5 |
Qujing Yangguang New Energy Co., Ltd. | Qujing, Yunnan | Former ingot/wafer subsidiary; disposed Dec 2022 | HKEX Dec 2022 |
Income Statement and Margin Analysis (%)
| Metric | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|---|
Revenue (CNY Mn) | 4,640.8 | 6,869.4 | 7,192.9 | 3,706.2 | 2,427.5 |
Revenue YoY growth (%) | — | 48.0 | 4.7 | -48.5 | -34.5 |
Gross profit (CNY Mn) | 405.0 | 271.3 | 458.0 | 104.0 | 44.3 |
Operating profit derived as PBT plus finance costs (CNY Mn) | — | — | 228.2 | -172.2 | -226.9 |
EBITDA company-reported (CNY Mn) | — | — | 387.0 | -11.2 | -100.3 |
Finance costs (CNY Mn) | — | — | 71.1 | 60.0 | 43.0 |
Pre-tax profit (CNY Mn) | — | — | 157.1 | -232.2 | -269.9 |
Income tax expense or credit (CNY Mn) | — | — | -15.5 | 5.2 | -15.4 |
Profit for the year (CNY Mn) | 302.4 | 1,112.1 | 141.7 | -227.0 | -285.3 |
Profit attributable to owners of parent (CNY Mn) | 193.2 | 957.2 | 111.9 | -227.1 | -285.3 |
Basic EPS (MYR Bn cents) | 5.84 | 28.80 | 3.37 | -6.83 | -8.58 |
Diluted EPS (MYR Bn cents) | 5.84 | 28.80 | 3.37 | -6.83 | -8.58 |
Dividend per share (MYR Bn cents) | — | — | 0 | 0 | 0 |
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansMargin
| Margin | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|---|
Gross margin (%) | 8.7 | 3.9 | 6.4 | 2.8 | 1.8 |
Operating margin derived (%) | — | — | 3.2 | -4.6 | -9.3 |
EBITDA margin (%) | — | — | 5.4 | -0.3 | -4.1 |
Net margin attributable (%) | 4.2 | 13.9 | 1.6 | -6.1 | -11.8 |
Income Statement and Margin Analysis (%) (H1FY2025–H1FY2026)
| Metric | H1FY2025 | H1FY2026 |
|---|---|---|
Revenue (CNY Mn) | 1,022.3 | 1,165.6 |
Gross profit or loss (CNY Mn) | -8.8 | 44.8 |
Gross margin (%) | -0.9 | 3.8 |
EBITDA (CNY Mn) | -23.6 | 13.4 |
Finance costs (CNY Mn) | 22.3 | 20.6 |
Loss before tax (CNY Mn) | -108.1 | -58.6 |
Loss attributable to owners (CNY Mn) | -109.1 | -56.0 |
Basic LPS (MYR Bn cents) | -3.28 | -1.68 |
External module shipments (MW) | 1,509.5 | 2,169.0 |
Impairment on financial and contract assets (CNY Mn) | 39.8 | 22.4 |
Warranty provision reversal (CNY Mn) | 36.0 | 7.5 |
Balance Sheet
| Metric | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|---|
Non-current assets (CNY Mn) | 2,166.4 | 1,004.5 | 929.9 | 795.8 | 714.6 |
Current assets (CNY Mn) | 4,124.8 | 6,732.8 | 4,738.3 | 3,187.2 | 2,493.7 |
Total assets (CNY Mn) | 6,291.2 | 7,737.3 | 5,668.2 | 3,983.0 | 3,208.3 |
Current liabilities (CNY Mn) | 4,893.5 | 6,117.1 | 4,121.8 | 2,748.6 | 2,352.0 |
Non-current liabilities (CNY Mn) | 725.4 | 414.5 | 353.3 | 272.0 | 180.7 |
Total equity (CNY Mn) | 672.3 | 1,205.7 | 1,193.1 | 962.4 | 675.6 |
Equity attributable to owners (CNY Mn) | — | — | 1,177.0 | 944.9 | 658.1 |
Cash and cash equivalents (CNY Mn) | — | — | 578.4 | 270.7 | 240.7 |
Pledged deposits (CNY Mn) | — | — | 1,358.0 | 511.0 | 501.5 |
Short-term borrowings (CNY Mn) | — | — | 1,195.7 | 952.7 | 964.2 |
Long-term borrowings (CNY Mn) | — | — | 28.2 | 1.5 | 1.2 |
Total borrowings (CNY Mn) | — | — | 1,223.9 | 954.2 | 965.4 |
Net debt company definition (CNY Mn) | — | — | -712.5 | 172.5 | 223.2 |
Trade and bills payables (CNY Mn) | — | — | 2,533.4 | 1,563.2 | 1,155.9 |
Inventories (CNY Mn) | — | — | 326.8 | 376.9 | 328.1 |
Goodwill (CNY Mn) | — | — | 0 | 0 | 0 |
Working capital current assets less current liabilities (CNY Mn) | -768.7 | 615.7 | 616.5 | 438.6 | 141.7 |
Cash Flow
| Metric | FY2021 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|
Operating cash flow (CNY Mn) | 1,030.4 | -692.1 | 180.9 | 51.8 |
Capital expenditure PP&E additions (CNY Mn) | — | 84.5 | 176.4 | — |
Free cash flow OCF less capex (CNY Mn) | — | -776.6 | 4.5 | — |
Dividends paid to shareholders (CNY Mn) | — | 0 | 0 | 0 |
Share buybacks (CNY Mn) | — | 0 | 0 | 0 |
Returns & Leverage Ratios (%) and Financial Ratios (x)
| Ratio | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 |
|---|---|---|---|---|---|
ROE profit for year over average total equity (%) | — | 118.4 | 11.8 | -21.1 | -34.8 |
ROA profit for year over average total assets (%) | — | 15.9 | 2.1 | -4.7 | -7.9 |
ROIC derived EBIT after tax over average equity plus debt (%) | — | — | — | -7.7 | -12.5 |
Current ratio (x) | 0.84 | 1.10 | 1.15 | 1.16 | 1.06 |
Total debt to equity (x) | — | — | 1.03 | 0.99 | 1.43 |
Net debt to equity company-reported (%) | — | — | -59.7 | 17.9 | 33.0 |
Net debt to EBITDA (x) | — | — | -1.8 | — | — |
Interest coverage EBIT over finance costs (x) | — | — | 3.2 | -2.9 | -5.3 |
Asset turnover revenue over average assets (x) | — | 0.98 | 1.07 | 0.77 | 0.68 |
Inventory days | — | — | 24 | 35 | 53 |
Trade receivable days | — | — | 94 | 193 | 211 |
Trade payable days | — | — | 168 | 205 | 205 |
Cash conversion cycle (days) | — | — | -50 | 23 | 59 |
Revenue by Region
| Region (CNY Mn) | FY2023 | FY2024 | FY2025 |
|---|---|---|---|
Mainland China | 5,981.4 | 3,172.6 | — |
Japan | 936.1 | 364.1 | — |
Europe | 122.2 | 137.7 | — |
Asia excluding Japan | 86.9 | 30.7 | — |
Others | 66.3 | 1.1 | — |
Export subtotal | 1,211.5 | 533.6 | — |
Total | 7,192.9 | 3,706.2 | 2,427.5 |
Region growth and mix
| Region growth and mix | FY2023 | FY2024 |
|---|---|---|
Mainland China share (%) | 83.2 | 85.6 |
Japan share (%) | 13.0 | 9.8 |
Europe share (%) | 1.7 | 3.7 |
Mainland China YoY (%) | — | -47.0 |
Japan YoY (%) | — | -61.1 |
Europe YoY (%) | — | 12.7 |
Asia excluding Japan YoY (%) | — | -64.7 |
Revenue by Region (H1FY2025–H1FY2026)
| Region (CNY Mn) | H1FY2025 | H1FY2026 |
|---|---|---|
Mainland China | 873.3 | 993.5 |
Japan | 135.8 | 111.9 |
Asia excluding Japan | 12.2 | 59.4 |
Others | 1.1 | 0.8 |
Export subtotal | 149.0 | 172.1 |
Total | 1,022.3 | 1,165.6 |
Segment by Region FY2024 Details
| Segment by region FY2024 (CNY Mn) | Mainland China | Japan | Europe | Asia ex-Japan | Other |
|---|---|---|---|---|---|
Segment A | 2,996.2 | 364.1 | 137.7 | 30.7 | 1.1 |
Segment B | 129.9 | 0 | 0 | 0 | 0 |
Segment C | 46.4 | 0 | 0 | 0 | 0 |
Share Price History
| Date | Price (HKD) | Context | Source |
|---|---|---|---|
21 Jan 2021 | 0.355 | Close before HKD0.29 subscription | HKEX announcement |
24 Sep 2024 | 0.16 (intraday high 0.212) | Speculative spike | AASTOCKS via uSMART |
Mid-2026 | 0.058 | 52-week range 0.054–0.156; market cap HKD193m; P/B 0.25 | Tiger Brokers |
3 Jul 2026 | 0.069 | +6.2% day move | AASTOCKS headline via Tiger |
4 Aug 2026 | 0.064 | — | HiStock |
24 Sep 2026 | 0.055 | Latest verified | etnet |
Valuation Snapshot
| Multiple | Value | Basis |
|---|---|---|
Market capitalisation | c.HKD183m (c.RMB168m) | 3,323,771,133 shares |
Net debt | RMB340.8m | 30 Jun 2026 company definition |
Enterprise value | c.RMB509m | Market cap + net debt (NCI and leases excluded) |
TTM revenue | RMB2,570.8m | FY2025 − H1 2025 + H1 2026 |
TTM EBITDA | c.RMB-63m | FY2025 −100.3 − (−23.6) + 13.4 |
TTM loss attributable | c.RMB-232m | FY2025 −285.3 − (−109.1) + (−56.0) |
P/E | Not meaningful (loss) | — |
EV/EBITDA | Not meaningful (negative EBITDA) | — |
EV/Sales | c.0.20x | — |
P/B | c.0.28x | Equity attributable RMB605.2m at 30 Jun 2026 |
Capital Markets
| Item | Detail | Source |
|---|---|---|
Dividend policy | Not formally quantified | — |
Buyback authorisation | General mandate to repurchase shares sought at 2026 AGM (standard 10% mandate per circular title) | AGM circular, 28 Apr 2026 |
Buybacks executed | None in FY2024, FY2025 or H1 2026 | FY2024 RA; H1 2026 IA |
Capital Markets — Moody's / S&P / Fitch
| Item | Detail |
|---|---|
Moody's / S&P / Fitch | Not rated |
Debt maturity at 30 Jun 2026 | RMB922.9m within 12 months; RMB6.0m beyond 1 year |
FY2024 borrowing mix | Secured bank loans RMB455.5m (4.80–6.05%); guaranteed bank loans RMB461.5m (2.70–5.80%, RMB and USD); other loans RMB37.2m (FY2024 RA Note 13) |
Security | PP&E, right-of-use assets, bills receivable; bills payable secured by pledged deposits (RMB417.9m at 30 Jun 2026) |
Guarantees | Subsidiaries, Mr. Tan Xin and Mr. Tan Wenhua (FY2024); major shareholders/directors and spouses (May 2026 loan) |
Debt maturity (CNY Mn) | FY2023 |
Due within one year | 1,195.7 |
Due after one year | 28.2 |
Analyst Conclusions
Management guidance (H1 2026 IA, qualitative)
Management expects gradual recovery of mainstream overseas demand and continued growth in emerging markets in H2 2026, while warning that supply-demand adjustment, price volatility and trade-environment changes will persist. Priorities: optimise customer/order structure; push high-power and differentiated modules; flexibly schedule production to control inventory and working capital; prudently expand C&I distributed PV, storage, electricity retail and PV-storage-charging with asset-light methods; advance certification and bulk sales of heavily doped and large-diameter semiconductor silicon, with 12" and SiC R&D. No quantitative guidance.
Consensus expectations
No published consensus.
Bull case
-
The cycle has turned for Solargiga's P&L. H1 2026 shows +44% shipments, a positive gross margin (3.8%) and positive EBITDA for the first time since FY2023, with loss halved; if anti-involution pricing discipline holds, H2 2026 could approach EBITDA breakeven-plus.
-
Deep-value optionality. At c.0.28x book and c.0.20x EV/Sales, the market prices in substantial distress; any stabilisation in equity and a successful storage COD or BC launch could re-rate the shares meaningfully from a c.HKD180m base.
-
Strategic assets beyond modules. The SHARP BC licence, a semiconductor silicon niche that is approaching breakeven (Segment C loss RMB0.6m in H1 2026), and a provincially sanctioned 400MWh storage asset give diversification unavailable to pure assemblers.
Bear case
-
Balance sheet is the binding constraint. Equity has fallen 48% since FY2023; net debt/equity rose from 33.0% to 54.9% in six months; virtually all debt is due within 12 months; going-concern depends on bank rollovers and family guarantees.
-
Structural sub-scale disadvantage. Without cell capacity or R&D spending (0.44% of revenue), Solargiga is a price-taker likely to remain at low single-digit gross margins, while BC/tandem transitions threaten further asset impairments.
-
Concentration and credit risk. Three customers represent >81% of H1 2026 revenue; one (Customer C) is a new processing relationship; ongoing customer litigation shows counterparty risk is real in a distressed industry.
Key catalysts and monitorables (next 12 months)
| Catalyst / monitorable | Timing | What to watch |
|---|---|---|
| Industry ASP trajectory under anti-involution rules | Continuous | Module price floor holding; Solargiga gross margin above 3–4% |
| FY2026 profit alert / results | Mar 2027 | Whether full-year loss narrows below RMB100m; EBITDA sign |
| Bank facility renewals | Rolling | Any covenant/renewal stress; additional family guarantees |
| Storage project construction start | From Sep 2026 | Capex quantum and financing structure |
| BC module commercialisation | 2026–2027 | First BC product launch, cell sourcing partner |
| Customer litigation outcomes | Ongoing | Recoveries vs further impairments on c.RMB144m |
| Customer C processing continuity | H2 2026 | Revenue durability |
| Semiconductor 8" automotive certification | 2026–2027 | Segment C turning profitable |
| Receivable days | Each reporting date | Continued improvement from 166 days |
| Governance | AGM cycles | Any move to separate Chair/CEO |
Concluding analyst verdict
Solargiga Energy is a survivor of China's PV overcapacity crisis, not yet a beneficiary of its resolution. The December 2022 sale of the Qujing wafer platform, at what proved to be the cycle peak, was the defining capital-allocation decision of the past five years: it crystallised a c.RMB1.04bn gain and spared the group the wafer-price collapse that followed. But it also left a sub-scale module assembler with no cell integration, thin R&D, and a balance sheet funded overwhelmingly by short-term bank credit and bills.
The FY2024–FY2025 losses (RMB227m and RMB285m) consumed nearly half of shareholders' equity. The H1 FY2026 interim is the first genuinely encouraging datapoint in two years — positive gross profit, positive EBITDA, shipment growth of 44%, faster receivable collection — and management's "value over scale" posture, cost cuts and receivable discipline are credible. The SHARP BC licence and the Liaoning storage project are sensible, capital-light-to-moderate options that could differentiate the business by 2027–2028.
Against that, the margin of safety is narrow. Net debt/equity has risen to 54.9%, cash is RMB163m against RMB923m of debt due within a year, and the auditors' going-concern basis rests on facility renewals supported by personal guarantees from the controlling family. Customer concentration (>81% from three accounts) and unresolved litigation leave revenue and credit exposures fragile. Governance is concentrated, with a combined Chair/CEO following a father-to-son succession.
Our verdict is that the equity is a high-risk, deep-value option on the Chinese module price floor holding through 2027. The shares, at roughly a quarter of book value, discount meaningful distress; a sustained return to positive EBITDA in H2 2026 and FY2027 would justify re-rating, but any renewed price war or bank tightening would threaten further equity dilution or impairment.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansExecutive Leadership
Board of Directors
| Name | Title | Appointment / tenure | Notes | Source |
|---|---|---|---|---|
TAN Xin (譚鑫) | Executive Director, Chairman and CEO | ED since at least 2012; current 3-year term from 10 Jun 2025; Chairman from 10 Jun 2025 | Son of founder Tan Wenhua; personal guarantor of group borrowings | AR2025; HKEX 2012 announcements; FY2024 RA Note 13 |
WANG Junze (王鈞澤) | Executive Director; authorised representative | ED by Jul 2022; current term from 12 Jun 2024; due for rotation at 2026 AGM | — | AR2025 |
CHEN Hai (陳海) | Executive Director | Appointed 23 Feb 2026 (casual vacancy); stood for re-election at 2026 AGM | — | AR2025 |
Dr. WONG Wing Kuen, Albert (王永權) | INED; Chair of Audit Committee | INED >10 years (named INED by 2012); current term from 21 Jun 2023 | Long tenure; board affirms independence | AR2025 |
Ms. CHUNG Wai Hang (鍾瑋珩) | INED; Chair of Nomination Committee | Appointed 11 Jul 2022; term from 12 Jun 2024 | — | AR2022; AR2025 |
Ms. TAN Ying (譚英) | INED; Chair of Remuneration Committee | Appointed 18 Oct 2022; term from 10 Jun 2025 | — | AR2022; AR2025 |
Board & Management Changes
| Date | Change | Context | Source |
|---|---|---|---|
11 Jul 2022 | INED Feng Wenli resigned; Chung Wai Hang appointed | Board refresh | AR2022 |
18 Oct 2022 | INED Lian Tao resigned; Tan Ying appointed | Board refresh | AR2022 |
10 Jun 2025 | Founder-chairman Tan Wenhua retired at AGM; NED Hsu You Yuan retired; Tan Xin appointed Chairman while remaining CEO | Generational succession; Hsu was CEO and ED c.2009–2014 | AR2025; ACN Newswire 2009 |
23 Feb 2026 | Chen Hai appointed ED | Restores executive bench to three | AR2025 |
Directors' Remuneration
| Attribute | Status (FY2025 / current) |
|---|---|
Board size | 5 at 31 Dec 2025; 6 from 23 Feb 2026 (3 EDs, 3 INEDs) |
Independence | 3 of 6 INEDs (50%) currently; 60% at end-2025 |
Chair/CEO separation | Not separated; disclosed deviation from CG Code provision C.2.1 since 10 Jun 2025 |
Family relationships | Tan Xin is son of former chairman Tan Wenhua |
Audit Committee | Wong Wing Kuen (Chair), Chung Wai Hang, Tan Ying — all INEDs; met 3 times in 2025 |
Remuneration Committee | Tan Ying (Chair), Wong Wing Kuen, Chung Wai Hang; met once in 2025 |
Nomination Committee | Chung Wai Hang (Chair), Wong Wing Kuen, Tan Ying; met once in 2025 |
Board meetings FY2025 | 6; full attendance by continuing directors |
Gender diversity | c.40% female at 31 Dec 2025 (2 of 5); 33% after Chen Hai appointment; workforce 33.4% female |
INED tenure >9 years | Dr. Wong (>10 years) |
Major Shareholders
| Holder | Stake | Source / status |
|---|---|---|
January 2021 strategic subscriber | 180,000,000 shares (5.42% at issue) at HKD0.29; independent third party, not a substantial shareholder | HKEX, 21 Jan 2021 |
Institutional ownership — top 10 | Not publicly disclosed in sources reviewed; no index-fund-scale ownership expected at c.HKD180m market cap | — |
Public float | Company confirms sufficient public float under Listing Rules (FY2023 results summary) | Moomoo summary of FY2023 results |
Competitive Landscape
Competitors by Segment
| Segment | Competitor | Positioning vs Solargiga |
|---|---|---|
Modules (Tier-1 integrated) | LONGi Green Energy | Global #1-tier; BC leader; vastly larger scale |
Modules | JinkoSolar | TOPCon leader; global distribution |
Modules | JA Solar | Integrated N-type; strong overseas |
Modules | Trina Solar | Integrated; also a Solargiga customer |
Modules | Tongwei | Polysilicon-to-module integrated |
Modules | Canadian Solar | Global, US manufacturing footprint |
Modules | Astronergy (Chint) | Integrated; also a Solargiga customer |
Modules (BC) | Aiko Solar | BC specialist — directly relevant to Solargiga's BC ambition |
Modules | GCL System Integration | Mid-tier assembler; BC series launched in Europe 2026 |
Modules (mid-tier/HK-listed) | DAS Solar, Risen, Huasun (HJT) | Similar-scale or larger mid-tier competitors |
Semiconductor silicon | National Silicon Industry Group (NSIG); TCL Zhonghuan; Hangzhou Lion Microelectronics | Larger semiconductor wafer producers |
Distributed EPC / BIPV | Numerous provincial EPCs; integrated module makers' energy-services arms | Fragmented |
Peer Comparison FY2025
| Company | H1 2025 revenue (CNY Bn) | Revenue YoY (%) | Notes |
|---|---|---|---|
Solargiga Energy | 1.02 | -39.6 | Gross margin -0.9% |
LONGi Green Energy | 32.81 | -14.8 | Net loss in H1 2025 |
JinkoSolar | 31.83 | -32.6 | Net loss in H1 2025 |
Trina Solar | 31.05 | -27.7 | PV products gross margin reported negative |
JA Solar | 23.91 | -36.0 | Module shipments 33.79 GW, >98% N-type |