State Gas Limited Overview
State Gas Limited is a Brisbane-based micro-cap natural gas explorer-turned-early-stage developer focused on the southern Bowen Basin (Denison Trough) of Central Queensland. It holds 100% of the Rolleston-West permit (ATP 2062, 1,414 km²) and the Reid's Dome production lease (PL 231, 181 km²), plus 35% of two exploration permits (ATP 2068 and ATP 2069) operated by Santos. In November 2025 Netherland, Sewell & Associates certified a maiden 30.2 PJ 2P (44.1 PJ 3P) coal seam gas reserve at Rolleston West — the company's first bankable reserve — underpinning a staged 10–30 TJ/day pipeline development concept tied to the Queensland Gas Pipeline ~37 km away. In parallel, State Gas owns Australia's first coal-seam-gas-to-High Density Natural Gas (HDNG) compression plant, targeting diesel substitution in Bowen Basin coal-mine haul fleets. The investment case is binary: asset value versus severe liquidity constraint, persistent dilution, a land-access dispute, and a sub-A$10M market capitalisation.
Company's own description (paraphrased from FY2026 Annual Report)
The FY2026 Directors' Report describes State Gas as a natural gas exploration and development company operating in the southern Bowen Basin. Management argues that its 100%-owned exploration projects, combined with joint venture interests over adjoining acreage, form a highly prospective portfolio, and that its proprietary gas compression technology positions it to supply both domestic and export gas users on Australia's East Coast. The stated development approach is low-cost and two-pronged: prospective assets either gain efficient access to conventional pipeline infrastructure, or are commercialised through the company's HDNG and "Rapid Refuel" compressed-gas supply-chain technology.
Independent characterisation
Economically, State Gas is a pre-revenue, pre-development upstream gas company whose value resides almost entirely in (a) capitalised exploration and evaluation assets (A$42.2M at 30 June 2026), (b) certified reserves and contingent resources, and (c) an HDNG plant (net plant and equipment A$8.2M). It generated only trivial gas-sales income (A$17k in FY2024 and A$111k in FY2025 from HDNG pilot sales) and is funded by equity, convertible notes, director loans, government grants and R&D tax incentive refunds.
The company sits at the very top of the upstream value chain (exploration and appraisal), with ambitions to move into production and, via HDNG, into a bundled downstream fuel-supply service (compression, trucking "virtual pipeline", delivery to mine sites). This latter element is unusual for a junior and represents an attempt to generate early cash flow from production-testing gas years ahead of a pipeline project.
Revenue model
| Revenue stream | Status | Model | Pricing basis |
|---|---|---|---|
| Pipeline gas sales (Rolleston West) | Pre-development; first material gas targeted calendar 2029 | Commodity sales into the Queensland Gas Pipeline / Gladstone–Wallumbilla network to domestic buyers or LNG exporters | NSAI reserve economics used calendar-2025 average LNG netback less 5% (tenement not subject to Australian market supply condition) |
| HDNG supply (virtual pipeline) | Pilot completed FY2025; Foundation Customer conditional, targeted Q2 calendar 2027 | Bundled gas-supply service under multi-year contracts | Premium to raw pipeline spot gas; correlated to diesel price on an energy-equivalent basis (FY2025 AR) |
| Government grants / R&D refunds | Recurring but lumpy non-operating inflows | Queensland Frontier Gas Exploration Grant (A$5.5M); R&D tax incentive (A$4.16M received July 2026) | — |
Product vs service vs licensing mix: effectively 100% product (gas) in prospect; the HDNG offer has a service-bundle character. No licensing income is disclosed.
Customer types and end-markets
East Coast domestic gas buyers: (retailers, industrial users, gas-fired power generators) via pipeline.
Gladstone LNG exporters: (who may need new supply to meet proposed domestic reservation obligations).
Bowen Basin coal miners: seeking diesel substitution for haul trucks (company estimates Bowen Basin coal-mine diesel consumption at more than A$2 billion per annum, with HDNG capable of replacing 50–70% of that usage — FY2026 AR).
- Industrial users without pipeline access.
Strategy
Stated strategy themes (paraphrased from FY2026 AR)
-
Become a new East Coast gas supplier by commercialising previously undeveloped Bowen Basin gas through low-capital, low-operating-cost development.
-
Dual pathway commercialisation: pipeline-connected development (Rolleston West) and virtual-pipeline HDNG supply to off-grid users.
-
Leverage regulatory positioning: company projects are not subject to price caps or domestic reservation restrictions, giving optionality to sell to domestic users or LNG exporters.
-
Ride structural demand drivers: declining southern offshore supply, coal-plant retirements, data-centre electricity demand (a Queensland Government priority), Asian LNG demand, and diesel supply-chain insecurity following Middle East disruption.
Strategic initiatives (last 24 months)
| Initiative | Timing | Detail | Status |
|---|---|---|---|
| Maiden 2P reserve certification | Nov 2025 | NSAI 30.2 PJ 2P / 44.1 PJ 3P | Completed |
| Rolleston West Concept Study | H2 FY2026 | Staged 10→30 TJ/day; materially lower capex than reserve-case estimates; water reuse at local mine; compression siting | Substantially complete; value engineering continuing |
| QGP tie-in pre-FEED | FY2026 | ~37 km route to Jemena Rolleston Compression Station | Commenced |
| Co-investment / farm-in process | FY2026–ongoing | Small group of domestic and international parties in structured diligence since June 2026 quarter | Ongoing; no binding terms |
| Petroleum lease application (eastern ATP 2062) | FY2026–FY2027 | Baseline environmental studies planned; ATP extension application lodged Sep 2026 | In progress |
| HDNG Foundation Customer | Target Q2 CY2027 | 12-truck dual-fuel fleet; LEIP to fund majority of capex | Conditional |
| Deeper Permian prospectivity review | FY2026 | Denison Trough analogue to Taroom Trough; up to 96 km² closure in PL 231 | Desktop |
| Santos JV tenure reorganisation | FY2026 | Evaluate integration with Rolleston West | Under evaluation |
| Capital Management Plan | From 27 May 2025 | Reduced overhead/field staff; discretionary capex deferral; director support; R&D refund monetisation | Ongoing |
| Carbon management (mineral carbonation) | 2023–2024 | With Rockminsolutions | Suspended |
Management targets / guidance
| Target | Company timing |
|---|---|
| HDNG Foundation Fleet implementation and first scalable revenue | Q2 calendar 2027 (mid-2027) |
| Regulatory and environmental approvals for Rolleston West | End calendar 2027 |
| Construction start | Early calendar 2028 |
| First material pipeline gas | Calendar 2029 |
| Production scale | 10 TJ/day Stage 1, expanding to 30 TJ/day |
No revenue, EBITDA, or cost-reduction quantified targets are given. Management acknowledges that further capital (partner, government infrastructure funding, project finance, or equity) is required to reach FID.
Products & Services
Rolleston West CSG Project (ATP 2062) — flagship
Description: Coal seam gas from Bandanna Formation coals in the eastern area of ATP 2062, adjacent to Santos's producing Arcadia Valley acreage.
Key technical specifications (FY2025 AR): ~8 m net coal per well, with thickest seams ~2.4 m and ~2.8 m laterally continuous over many kilometres; gas content 5–6 m³/tonne (dry ash free); methane 93.8%–96% (at or near pipeline quality); permeability 26–395 millidarcies; Rougemont-2/3 dual-lateral system demonstrated 474,000 cubic feet/day.
Reserves: 30.2 PJ 2P and 44.1 PJ 3P (NSAI, 20 Nov 2025); 2P supported by 3 existing wells plus 24 future undeveloped vertical wells; 3P assumes a further 16 wells sustaining 10 TJ/day for at least 10 years. No 1P assigned.
Development concept: Stage 1 10 TJ/day expanding to 30 TJ/day; ~37 km tie-in to the QGP at Jemena's Rolleston Compression Station; produced water to be piped to a nearby mine for dust suppression.
Timeline (company target): approvals by end calendar 2027; construction early 2028; first material gas calendar 2029.
Target customers: East Coast domestic buyers; Gladstone LNG exporters.
Pricing: Not contracted; reserve economics assumed LNG netback less 5%.
Reid's Dome Project (PL 231)
Description: Conventional (shallow Cattle Creek Formation, in places only ~130 m deep) and CSG (Reid's Dome Beds) associated with the sharply uplifted Reid's Dome anticline.
Specifications: >30 m net coal in producible zones, proven below 1,100 m; average gas content ~13.75 m³/tonne (dry ash free); Nyanda-4 stabilised ~140 mscf/d.
New angle (FY2026): Re-evaluation of deeper Permian sequences in the Denison Trough (analogous to the Taroom Trough); prior core showed live gas and condensate in an overpressured system; prospective area up to 96 km² within a four-way dip closure. Desktop stage only.
Status: Challenging terrain; company evaluating integrated development with Rolleston West.
Santos JV (ATP 2068 and ATP 2069)
Description: 35% non-operated interests; CSG in Bandanna Formation and conventional targets; ATP 2069 bisected by two high-pressure export pipelines.
Status: Early-stage exploration planning; company exploring tenure reorganisation to integrate with Rolleston West.
HDNG Plant and Virtual Pipeline ("Rapid Refuel")
Description: First-of-its-kind (in Australia) facility converting raw CSG from production-testing wells into high-density compressed natural gas meeting specifications for dual-fuel mine-truck engines; delivered by truck.
Launch: Commissioned mid-2024; six-month pilot with a local coal mine achieved diesel substitution and emissions targets, but the customer elected not to expand for reasons the company says were unrelated to State Gas.
Flagship opportunity: "Foundation Fleet" — 12 haul trucks converted to dual fuel for a Bowen Basin coal miner under a multi-year supply contract, majority of capex conditionally funded by Queensland's Low Emission Investment Program (LEIP); target implementation Q2 calendar 2027.
Pricing model: Premium to spot pipeline gas, indexed to diesel on an energy-adjusted basis.
Carrying value: Included in plant and equipment of A$8.2M (FY2026).
Carbon management (dormant)
Description: Evaluation of in-situ/ex-situ mineral carbonation in the Buckland Basaltic Sequence (western ATP 2062) with Rockminsolutions Pty Ltd at EPM 27596.
Status: Suspended after Queensland's late-2024 policy barring CCS above the Great Artesian Basin.
Financial Narrative
All figures A$ M, fiscal years ending 30 June. FY2024–FY2026 from audited annual reports (FY2025 and FY2026 ARs). FY2022–FY2023 balance sheet totals from Stockopedia/TipRanks (derived from annual reports) cross-checked to FY2025 AR statement of changes in equity; FY2022–FY2023 profit from FY2025 AR remuneration report.
Income statement
Gross profit, gross margin, operating margin, EBITDA margin and net margin are not meaningful given negligible revenue. EBITDA is not disclosed by the company; depreciation charged to profit was immaterial in FY2025 (A$1,050) versus A$197,806 in FY2024, as plant costs are largely capitalised within exploration and evaluation. Revenue CAGR is not meaningful (base near zero).
Since FY2023, losses have run at A$3–3.6M per year. The composition of losses shifted materially: FY2024 was burdened by R&D expensing and a A$0.78M write-off of capitalised engineering costs; FY2025 saw administrative costs double to A$2.18M on legal fees (A$0.53M, land dispute) and HDNG plant operating costs (A$0.76M); FY2026 saw financing costs balloon to A$1.07M as the company relied on 15–20% director loans, a 17% R&D bridging facility and convertible notes. The FY2026 loss was flattered by a A$0.49M non-cash fair value gain on derivative liabilities embedded in the director convertible loans and convertible notes.
Balance sheet
Note: FY2023 contributed equity and accumulated losses are the 1 July 2023 opening balances in the FY2025 AR statement of changes in equity.
Commentary. The balance sheet is asset-heavy but illiquid: ~98% of total assets are non-current exploration and plant balances whose recoverability depends on development success. Cash has repeatedly fallen to near-zero (A$31,751 at 30 June 2024). The FY2026 net current liability of A$6.47M is the worst in the period, but the post-balance-date A$4.16M R&D refund (16 July 2026) allowed repayment of the R&D bridging facility and all director loans, and ongoing note conversions are shrinking the convertible liability. Unused tax losses for which no DTA is recognised stood at A$21.6M at 30 June 2025 (potential benefit A$5.4M).
Cash flow
FY2022–FY2023 financing cash flows from Kalkine data summary (derived from annual reports).
Commentary. FY2024 was the capex peak (HDNG plant construction, A$7.1M). FY2025 capex was substantially offset by A$6.0M of government incentives (Frontier grant and R&D refunds). FY2026 had no incentive inflows (the FY2024 R&D refund was delayed by an ATO review), forcing the company into expensive bridge funding. Cumulative external funding FY2024–FY2026 exceeded A$20M including grants.
Ratios (computed from audited figures)
ROIC, net debt/EBITDA and cash conversion cycle are not meaningful for a pre-revenue explorer (blank). Aggregator Wisesheets reports TTM ROE of -10.06% to December 2025, broadly consistent.
Overall trend assessment. The five-year arc is one of steady asset accretion (total assets up 52% from A$33.9M to A$51.6M) funded by dilution, with equity broadly flat since FY2025 as losses offset new capital. The key inflection is qualitative rather than financial: the November 2025 reserve certification converted part of the capitalised base into a bankable reserve. The key financial vulnerability is that the market capitalisation (~A$5M) is roughly one-eighth of book equity (A$41.7M), signalling deep market scepticism about recoverability, timing, or dilution required to reach FID.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansFinancial Detail
Analytical Segment Details
| Analytical segment | Contents | Status |
|---|---|---|
Rolleston West (ATP 2062) | CSG (Bandanna Formation) and conventional targets; Rougemont well systems; 2P reserve; HDNG plant located here | Pre-development / appraisal |
Reid's Dome (PL 231) | Conventional (Cattle Creek) and CSG (Reid's Dome Beds); deeper Permian unconventional prospectivity | Appraisal / under evaluation |
Santos JV (ATP 2068, ATP 2069) | 35% non-operated CSG and conventional exploration acreage | Early exploration |
HDNG / alternative fuels (functional) | Compression plant and virtual-pipeline supply chain | Pilot completed; foundation contract conditional |
Results by Segment
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
HDNG gas sales (AUD Mn) | — | — | 0.017 | 0.111 | — |
Total other income (AUD Mn) | — | — | 0.069 | 0.112 | 0.425 |
Loss before tax (AUD Mn) | 1.342 | -1.188 | -3.631 | -3.284 | -2.973 |
Project Portfolio
| Project | Permit | Interest | Area km² (100%) | 2P PJ | 3P PJ | 2C PJ |
|---|---|---|---|---|---|---|
Rolleston-West (unconventional) | ATP 2062 | 100% | 1,414 | 30.2 | 44.1 | 231 |
Rolleston-West (conventional) | ATP 2062 | 100% | — | — | — | 18 |
Reid's Dome (unconventional) | PL 231 | 100% | 181 | — | — | 192 |
Reid's Dome (conventional) | PL 231 | 100% | — | — | — | 3.6 |
Santos JV | ATP 2068 | 35% | 727 | — | — | 43 |
Santos JV | ATP 2069 | 35% | 308 | — | — | 17 |
Total | — | — | — | 30.2 | 44.1 | 505 |
Income Statement and Per-Share Data
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Revenue — HDNG gas sales (AUD Mn) | — | — | 0.017 | 0.111 | — |
Total other income (AUD Mn) | — | — | 0.069 | 0.112 | 0.425 |
Administrative and other expenses (AUD Mn) | — | — | 1.087 | 2.178 | 2.159 |
Employee benefits expense (AUD Mn) | — | — | 0.457 | 0.643 | 0.648 |
R&D costs expensed (AUD Mn) | — | — | 1.033 | 0 | 0 |
Capital WIP written off (AUD Mn) | — | — | 0.782 | 0 | 0 |
Share-based payment expense (AUD Mn) | — | — | 0.121 | 0.145 | 0.011 |
Fair value gain on financial liabilities (AUD Mn) | — | — | 0 | 0 | 0.494 |
EBIT — loss before finance costs and tax (AUD Mn, computed) | — | — | -3.411 | -2.855 | -1.899 |
Finance costs (AUD Mn) | — | — | 0.220 | 0.430 | 1.075 |
Pre-tax profit/loss (AUD Mn) | 1.342 | -1.188 | -3.631 | -3.284 | -2.973 |
Net profit/loss (AUD Mn) | 1.342 | -1.188 | -3.631 | -3.284 | -2.973 |
EPS basic (A$ cents) | — | — | -1.4 | -0.9 | -0.7 |
EPS diluted (A$ cents) | — | — | -1.4 | -0.9 | -0.7 |
Dividends per share (A$ cents) | 0 | 0 | 0 | 0 | 0 |
Balance Sheet
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Total assets (AUD Mn) | 33.88 | 40.91 | 48.32 | 51.21 | 51.55 |
Cash and equivalents (AUD Mn) | 3.23 | 0.453 | 0.032 | 2.160 | 0.633 |
Total current assets (AUD Mn) | 3.35 | 0.58 | 0.196 | 2.248 | 0.769 |
Exploration and evaluation assets (AUD Mn) | — | — | 37.29 | 39.26 | 42.15 |
Plant and equipment (AUD Mn) | — | — | 10.43 | 9.30 | 8.23 |
Goodwill and intangibles (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Borrowings — current (AUD Mn) | — | — | 2.137 | 1.787 | 5.379 |
Borrowings — non-current (AUD Mn) | — | — | 0 | 0 | 0 |
Total debt (AUD Mn) | — | — | 2.137 | 1.787 | 5.379 |
Net debt (AUD Mn, computed) | — | — | 2.105 | -0.373 | 4.746 |
Trade and other payables (AUD Mn) | — | — | 2.765 | 4.077 | 1.861 |
Rehabilitation provision (AUD Mn) | — | — | 3.103 | 2.688 | 2.625 |
Total current liabilities (AUD Mn) | 0.262 | 1.37 | 4.902 | 5.864 | 7.240 |
Total liabilities (AUD Mn) | 2.58 | 4.31 | 8.01 | 8.55 | 9.87 |
Total equity (AUD Mn) | 31.30 | 36.61 | 40.32 | 42.66 | 41.69 |
Contributed equity (AUD Mn) | — | 42.92 | 50.01 | 55.49 | 56.69 |
Accumulated losses (AUD Mn) | — | -9.04 | -12.67 | -15.95 | -18.93 |
Working capital (AUD Mn, computed) | 3.09 | -0.79 | -4.71 | -3.62 | -6.47 |
Cash Flow
| Metric | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
Operating cash flow (AUD Mn) | — | — | -2.131 | -2.554 | -1.521 |
Payments for exploration assets (AUD Mn) | — | — | 1.582 | 4.206 | 4.889 |
Payments for plant and equipment (AUD Mn) | — | — | 7.130 | 2.010 | 0 |
Total capex (AUD Mn) | — | — | 8.712 | 6.216 | 4.889 |
Government incentives received (AUD Mn) | — | — | 1.230 | 6.027 | 0 |
Free cash flow — OCF less capex (AUD Mn, computed) | — | — | -10.843 | -8.770 | -6.410 |
Free cash flow after government incentives (AUD Mn, computed) | — | — | -9.613 | -2.743 | -6.410 |
Proceeds from share issues (AUD Mn) | — | — | 7.385 | 4.373 | 0 |
Proceeds from convertible notes (AUD Mn) | — | — | 0 | 0 | 3.200 |
Net borrowings (AUD Mn) | — | — | 1.898 | 0.937 | 1.887 |
Net financing cash flow (AUD Mn) | 7.50 | 6.87 | 9.115 | 4.872 | 4.881 |
Dividends paid (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Share buybacks (AUD Mn) | 0 | 0 | 0 | 0 | 0 |
Returns & Leverage Ratios (%) and Financial Ratios (x)
| Ratio | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|
ROE (% on average equity) | 4.8 | -3.5 | -9.4 | -7.9 | -7.1 |
ROA (% on average assets) | — | -3.2 | -8.1 | -6.6 | -5.8 |
Current ratio (x) | 12.8 | 0.42 | 0.04 | 0.38 | 0.11 |
Debt / equity (x) | — | — | 0.05 | 0.04 | 0.13 |
Interest coverage — EBIT / finance costs (x) | — | — | -15.5 | -6.6 | -1.8 |
Asset turnover (x) | — | — | 0.0004 | 0.002 | — |
Revenue by Region
| Region | FY2024 | FY2025 | FY2026 |
|---|---|---|---|
Australia — HDNG gas sales (AUD Mn) | 0.017 | 0.111 | — |
Rest of world (AUD Mn) | 0 | 0 | 0 |
Per-Share Data
| Metric | FY2021 | FY2022 | FY2023 | FY2024 | FY2025 | FY2026 |
|---|---|---|---|---|---|---|
Share price at 30 June (A$ cents) | 50.0 | 17.0 | 18.0 | 9.3 | 2.1 | 1.7 |
Performance Window Details
| Performance window | Return | Basis |
|---|---|---|
Latest price (1 Oct 2026) | A$0.010 | StockAnalysis |
1-year | approx. -52% (30 Jun 2025 → 1 Oct 2026); FY2026 alone -19% | AR; StockAnalysis |
3-year | approx. -94% (30 Jun 2023 18.0c → 1.0c) | AR; StockAnalysis |
5-year | approx. -98% (30 Jun 2021 50.0c → 1.0c) | AR; StockAnalysis |
All-time high | ~A$1.03 (23 Sep 2020) | TradingView |
52-week range | A$0.010–0.038 | StockAnalysis |
Beta | 0.14 (StockAnalysis) vs 0.98 (TradingView) — sources conflict | Aggregators |
Valuation Snapshot
| Metric | Value | Comment |
|---|---|---|
Market capitalisation | ~A$4.5–6M | Depends on post-conversion share count |
Book equity (30 Jun 2026) | A$41.7M | Audited |
Price / book | ~0.11–0.14x | Computed |
Enterprise value | ~A$5–7M | — |
EV / 2P reserve | ~A$0.17–0.23 per GJ of 2P (≈A$5–7M / 30.2 PJ) | Computed; illustrates the deep discount management highlights |
P/E, EV/EBITDA, EV/Sales | Not meaningful (losses, no revenue) | — |
Capital Markets
| Item | Detail |
|---|---|
Analyst coverage / consensus | None (StockAnalysis lists no analysts or price target) |
Dividend history and policy | No dividends ever paid; none expected |
Credit ratings (Moody's / S&P / Fitch) | Not rated |
Options | 71,266,716 at A$0.05 expiring 3 Aug 2028 |
Recent equity raises | FY2024 A$7.4M shares; Aug–Nov 2024 placement/ANREO ~A$5.9M; Dec 2025 A$3.2M convertible notes |
Analyst Conclusions
Management guidance
Management's priorities for FY2027 are: value engineering toward FID at Rolleston West; supporting co-investment diligence; securing LEIP funding and executing the HDNG Foundation Customer implementation (Q2 CY2027); progressing the petroleum lease application and environmental approvals (target end CY2027); and resolving the land dispute. Construction is targeted for early 2028 and first material gas in 2029. There is no consensus forecast.
Bull case
-
Reserve re-rating: An EV of roughly A$0.2 per GJ of 2P is a small fraction of typical East Coast transaction metrics; a credible farm-in at even modest per-GJ valuations would imply multiples of the current market capitalisation.
-
Strategic scarcity: A pipeline-proximate, reservation-exempt reserve could appeal to LNG exporters needing third-party supply under a reservation regime.
-
Near-term cash flow: The 12-truck HDNG Foundation Fleet, largely government-funded, could deliver the first recurring revenue by mid-2027 and validate a scalable diesel-substitution business.
Bear case
-
Dilution spiral: Variable-price note conversions (A$0.0132 in June 2026) and >110M shares issued since balance date show how quickly per-share value can be eroded; further capital is unavoidable before FID.
-
Execution and access risk: A failed mediation and pending trial at the core asset, plus pending tenure extension, could delay approvals beyond 2027.
-
Track record: Since IPO the company has repeatedly targeted near-term gas sales (Reid's Dome, 2021–2023 offtake plans, HDNG expansion) without achieving material revenue; the HDNG pilot customer did not expand.
Catalysts and monitorables (next 12 months)
| Catalyst | Expected timing | Watch for |
|---|---|---|
| Quarterly report (Sep qtr) | Late Oct 2026 | Cash balance, remaining convertible notes |
| AGM | Nov 2026 (expected) | Capital management resolutions, placement capacity |
| ATP 2062 tenure extension | Pending | Approval and conditions |
| Co-investment outcome | FY2027 | Term sheet, valuation per GJ, carry structure |
| LEIP / Foundation Customer conversion to binding terms | FY2027 | Technical sign-off, funding model |
| Land Court expert evidence / trial | FY2027 | Settlement or judgment; cost exposure |
| Domestic gas reservation final design | FY2027 | Price signals for LNG-netback-linked supply |
| Petroleum lease application lodgement | FY2027 | Environmental baseline progress |
Analyst verdict
State Gas Limited is a classic micro-cap asset-versus-balance-sheet tension. On the asset side, FY2026 delivered the most important milestone in the company's nine-year history: an independently certified 30.2 PJ 2P reserve at Rolleston West, derived from only four wells, sitting within a much larger 231 PJ 2C envelope and about 37 km from an open-access trunk pipeline feeding both domestic buyers and Gladstone LNG. The tenure is exempt from the Australian market supply condition, a genuinely valuable feature as the Federal Government designs a reservation regime that may force exporters to source new third-party supply. The HDNG plant adds a differentiated, if still unproven-at-scale, route to early cash flow, now with a conditional foundation customer and conditional state funding.
On the other side, the company is chronically short of capital. It ended FY2026 with A$0.6M of cash and a A$6.5M working-capital deficit, relied on 15–20% insider loans, and issued variable-price convertible notes whose conversions have driven the share price to a cent. The July 2026 R&D refund repaired the short-term position but does not fund a development that will require partner capital, project finance or substantial new equity. Overlaying this are a land-access dispute at the core asset now headed to trial, a pending tenure extension, and a governance structure in which every non-executive director is also a major shareholder and recent lender.
The market is pricing State Gas at roughly one-eighth of book equity and around A$0.2 per GJ of 2P — effectively assigning a high probability that existing shareholders will be heavily diluted or the asset sold cheaply. The verdict is speculative, event-driven: the equity is a call option on a farm-in transaction struck at a reasonable reserve multiple before further dilution. Absent a binding partner or HDNG contract within 12 months, the funding overhang is likely to dominate.
Unlock Company Financials
Unlock this company profile to view its financial data.
View Subscription PlansExecutive Leadership
Board of Directors
| Name | Title | Tenure | Background (per annual reports) | Committees |
|---|---|---|---|---|
Philip (Phil) St Baker | Non-Executive Chairman | Director from at least FY2024; Chair since 21 Nov 2024 | Entrepreneur, investor and executive with 20+ years in technology, energy and resources; led start-up to large companies | Audit, Risk; Chair of Remuneration |
Doug McAlpine | Managing Director | CEO from 30 Nov 2022; MD since 10 Sep 2024 | 20+ years public company management across finance, mineral exploration and construction; capital allocation and complex commercial negotiation | — |
Tony (A) Bellas | Non-Executive Deputy Chairman | Founding-era director (original Chairman, 2017) | Ex-CEO Seymour Group, Ergon Energy and CS Energy; former Deputy Under Treasurer, Queensland Treasury; Fellow, Geological Society of London; NED of NOVONIX (ASX: NVX); Chair of Green & Gold Minerals (ASX: GG1) | Chair of Audit; Risk; Remuneration |
Greg (G) Baynton | Non-Executive Director | Founding director (2017) | Founder/Executive Director Orbit Capital; investment banking, infrastructure, IPOs; ex-Queensland Treasury and Dept of Mines & Energy | Audit; Remuneration |
Jon (J) Stretch | Non-Executive Director | Director (date not stated in material reviewed) | Former Managing Director, ERM Power (ASX-listed generator/retailer); former EVP and management board member, Landis+Gyr | Chair of Risk |
Suzanne Yeates | Company Secretary (and finance function) | Since 7 Jun 2017 | Chartered Accountant; founder of Outsourced Accounting Solutions | — |
Directors' Remuneration
| Name | Year | Cash salary/fees | Leave | Bonus | Super | Share-based | Total |
|---|---|---|---|---|---|---|---|
D McAlpine | FY2026 | 390,000 | 6,827 | 0 | 30,000 | -19,054 | 407,773 |
D McAlpine | FY2025 | 372,692 | 42,727 | 50,000 | 30,000 | 55,385 | 550,804 |
P St Baker | FY2026 | 70,000 | 0 | 0 | 8,400 | 0 | 78,400 |
A Bellas | FY2026 | 50,000 | 0 | 0 | 6,000 | 0 | 56,000 |
G Baynton | FY2026 | 40,000 | 0 | 0 | 4,800 | 0 | 44,800 |
J Stretch | FY2026 | 40,000 | 0 | 0 | 4,800 | 0 | 44,800 |
Total KMP | FY2026 | 590,000 | 6,827 | 0 | 54,000 | -19,054 | 631,773 |
Total KMP | FY2025 | 828,087 | 28,913 | 50,000 | 83,525 | 55,385 | 1,045,910 |
Board & Management Changes
| Date | Change |
|---|---|
30 Nov 2022 | Doug McAlpine appointed CEO |
30 Nov 2023 | R Towner ceased as director |
10 Sep 2024 | McAlpine appointed Managing Director |
21 Nov 2024 | Richard Cottee resigned as Executive Chairman/director; Phil St Baker appointed Chair |
30 Jun 2025 | M Herrington (COO) ceased |
Major Shareholders
| Holder | Shares | Basis / date | Source |
|---|---|---|---|
Phil St Baker (and related entities) | 61,048,712 (+5,416,671 options) | At date of FY2026 report (30 Sep 2026), after note conversions | FY2026 AR |
Greg Baynton (and related entities) | 44,312,822 (+1,250,001 options) | At date of FY2026 report | FY2026 AR |
Immanuel Developments Pty Ltd | 14,132,674 (3.12%) | Reported 1 Jul 2026 | Investing.com |
Tony Bellas (and related entities) | 12,905,692 (+833,334 options) | At date of FY2026 report | FY2026 AR |
Australian Philanthropic Services Foundation | 11,361,424 (2.51%) | Reported 17 Sep 2025 | Investing.com |
Jon Stretch | 9,942,214 (+833,334 options) | At date of FY2026 report | FY2026 AR |
Doug McAlpine | 1,285,475 (+2,125,000 performance rights) | At date of FY2026 report | FY2026 AR |
Competitive Landscape
Key Competitors
| Competitor | Segment overlap | — |
|---|---|---|
Santos (ASX: STO) | Bowen/Surat CSG; GLNG; JV partner in ATP 2068/2069 | Major integrated producer; adjacent Arcadia Valley production |
Origin Energy / APLNG (ASX: ORG) | Surat/Bowen CSG to LNG and domestic | Major; operator of APLNG upstream |
Shell QGC | Surat CSG, QCLNG | Major |
Arrow Energy (Shell/PetroChina) | Bowen and Surat CSG | Large private developer |
Senex Energy (Hancock / POSCO) | Surat Basin CSG (Atlas, Roma North) | Mid-size private producer expanding domestic supply |
Comet Ridge (ASX: COI) | Galilee/Bowen gas (Mahalo) | ASX junior-to-developer; closest listed peer in Bowen CSG |
Blue Energy (ASX: BLU) | Bowen Basin CSG (North Bowen) | ASX junior |
Galilee Energy (ASX: GLL) | Galilee Basin CSG | ASX junior |
Elixir Energy (ASX: EXR) | Taroom Trough unconventional | ASX junior; relevant to State Gas's deeper Permian thesis |
Omega Oil & Gas (ASX: OMA) | Taroom Trough | ASX junior |
Denison Gas (private) | Denison Trough conventional/CSG | Private operator in the same sub-basin |
Westside Corporation (private) | Bowen Basin CSG (Meridian) | Private producer |
Competitive Advantages & Vulnerabilities
| Advantages | Vulnerabilities |
|---|---|
30.2 PJ 2P reserve ~37 km from QGP | Sub-scale balance sheet; recurring going-concern uncertainty |
Tenure not subject to Australian market supply condition (can sell to LNG exporters) | Dependent on third-party pipeline access (Jemena) |
Proprietary HDNG plant — first-mover in mine diesel substitution | HDNG pilot customer did not expand; foundation deal conditional |
Adjacency to Santos acreage and Arcadia Valley | Land access dispute at the core asset |
Experienced energy-sector board | Board doubles as lender, compromising independence |
Recent Developments
No layoffs announcements beyond staffing reductions noted, no guidance revisions in the formal sense, and no regulatory enforcement actions identified.